Purington Paving Brick Co. v. Metropolitan Paving Co.

4 F.2d 676, 1925 U.S. App. LEXIS 3068
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 7, 1925
Docket6516
StatusPublished
Cited by15 cases

This text of 4 F.2d 676 (Purington Paving Brick Co. v. Metropolitan Paving Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Purington Paving Brick Co. v. Metropolitan Paving Co., 4 F.2d 676, 1925 U.S. App. LEXIS 3068 (8th Cir. 1925).

Opinion

KENYON, Circuit Judge.

As plaintiff in error was plaintiff, and defendant in error, defendant, in the trial court, we so designate them in this opinion. The ease is here on writ of error from the St. Joseph division of the Western district of Missouri.

Plaintiff brought action to recover the purchase price of brick sold to the defendant under written contract, by the terms of which plaintiff was to furnish approximately 2,- 590,000 brick to be used for paving in the city of Marysville, Kan., with which city defendant had a paving contract. The contract between defendant and the city provided for the completion of the work within 180 working days from the date of the contract. Under the terms of the contract between plaintiff and defendant, plaintiff was to commence shipment of brick to defendant when ordered, and was to continue to make shipments “as fast as possible,” until the entire shipment had been made, un *677 less prevented by labor troubles, fire, lack of ears, etc. Defendant was to pay for the brick shipped under the agreement at the rate of $39.19 per 1,000, f. o. b. car tracks at Marysville,’Kan. Payment therefor was to be made by defendant on the 30th day of each month for the brick shipped the preceding month, and the contract further provided that, in case freight rates were increased or decreased during the existence of the agreement, the price of the brick should be increased or decreased accordingly. Freight rates were increased on August 26, 1920. Plaintiff continued to send bills for monthly shipments after that time, which were paid without protest by defendant. Whan all the shipments were received, defendant deducted from the amount due what it had been compelled to pay in increased freight rates, and refused to make payment therefor. For that amount plaintiff sought recovery in the sum of $6,505.52, and on the trial it was admitted that defendant was indebted to plaintiff in that amount on the contract, being the amount of the increase in freight rates after August 26, 1920. Defendant by counterclaim sought to recover from plaintiff damages for delay in the shipment of the brick in question, claiming that plaintiff did not ship the brick “as fast as possible,” as provided in the contract; that the order to ship was given to plaintiff in “September,” 1919, and that no brick wore shipped until April, 1920. Defendant, dur-ing the fall and winter of 1919 and 1920, was continually urging shipments, and plaintiff was claiming that the labor situation and car shortage was preventing sending and making shipments as readily as otherwise could be done.

From April, 1920, through the summer, defendant urged shipment of more brick; plaintiff then claiming shortage of ears as an excuse for nondelivery. In September, 1920, when less than one-half of the brick under the contract had been received, defendant again urged delivery of more brick, and so .the correspondence runs through the record. The last brick necessary to complete the contract were shipped in December, 1920. During the month of September, 1919, plaintiff shipped 309 ears to other parties than defendant; in October, 1919, 290 cars; in November, 1919, 198 ears; in December, 1919, 13 cars; in January, 1920, 151 cars; in February, 1920, 168 ears; in March, 1920, 213 cars; in April, 1920, it shipped 18 ears to defendant and 156 cars to other parties; in May, 1920, it shipped 28 ears to defendant, and 178 cars to other parties; in June, 1920, it shipped 31 cars to defendant, and 257 cars to other parties; in July, 1920, 22 ears to defendant and 356 cars to other parties; and from August 1 to August 26, 1920, the. date of the increase in freight rates, it shipped to defendant 9 cars, and to other parties 347 ears.

The entire controversy arises over the counterclaim, which is based on the delay in the shipment of ears, it being claimed that, if the brick had been shipped to defendant “as fast as possible,” as provided by the contract, it could have completed its work with the city in the 180 working days from July 14, 1919, provided by its contract with the city; that in any event the brick could have been shipped so that defendant could have completed its contract before the increase in freight rates, and hence that it was directly damaged by the delay to the extent of the freight rates. Other damages, such as premium on renewal bond, interest on money borrowed, overhead charges, and other items set forth in the counterclaim, were also claimed.

The jury returned a verdict for plaintiff for $6,505.52, with interest, making a total verdict for plaintiff of $7,318.58, and returned a verdict for defendant upon its counterclaim in the sum of $7,818.58, upon which judgment was duly rendered. Some 40 assigments of error wore filed, but only 6 are presented in argument and relied on by plaintiff. We consider them in the order of their presentation.

I. Plaintiff contends that the instruction requested, to find for it upon defendant’s counterclaim, should have been given, because it is claimed the uneontradieted testb mony shows that labor troubles and lack of cars reduced its normal output; that it was doing everything possible to meet its contracts, and that the record does not show that defendant did not receive during the course of the contract its proportionate part of the reduced output of plaintiff; that plaintiff was supplying briek in some eases under prior contracts for furnishing paving, brick, where the concrete had been laid; and that it would have been justified in suspending shipments upon the conditional contracts and meeting the requirements of the unconditional ones. The contract between plaintiff and defendant had in it this provision:

“The party of the first part agrees to begin shipment of brick under the agreement to the party of the second part when ordered to do so, and to continue to make shipments as fast as possible until the entire shipment has been made, unless prevented by labor *678 troubles, fire, lack of ears, or other unavoidable causes; it being understood and agreed that, if shipments on this agreement are not completed before January 1, 1920,' on account of the inability of the party of the second to receive same, then the party of the first part may, at its option, cancel the balance of this'agreement.” >

Shipments under this provision of the contract were to commence when defendant ordered plaintiff to ship. The eohrt left to the jury to determine from the evidence when the order to commence shipping was given. Without reviewing the evidence on that question, it is sufficient to say that the jury would be warranted in finding the request to ship was made as early as August 18, 1919. The evidence is without dispute that no brick were shipped until April, 1920.

■ From September 1, 1919, to April 1, 1920, plaintiff shipped to other contractors a total of 1,342 cars (13,420,000 brick); none to defendant. From April 1, 1920, to August 26, 1920, the date at which the increased freight rates went into effect, plaintiff shipped 108 ears to defendant (1,080,000 brick) out of a total of 1,399 cars (13,990,-000 brick) shipped. This would seem sufficient to justify a belief on the part of the jury that, as far as defendant’s contract was concerned, there was delay in shipment, and that the brick were not shipped “as fast as possible,” as provided by the contract. The excuse for the delay was labor troubles and shortage of ears.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aquila, Inc. v. C.W. Mining
545 F.3d 1258 (Tenth Circuit, 2008)
Franklin v. Shelton
250 F.2d 92 (Tenth Circuit, 1957)
Robberson Steel Co. v. Harrell
177 F.2d 12 (Tenth Circuit, 1949)
Horning v. Ferguson
52 A.2d 116 (District of Columbia Court of Appeals, 1947)
Danko v. Lewy
149 F.2d 66 (Fifth Circuit, 1945)
Blair v. United States Ex Rel. Gregory-Hogan
147 F.2d 840 (Eighth Circuit, 1945)
Kling v. Crown Finance Corp.
146 P.2d 54 (California Court of Appeal, 1944)
Coca Cola Bottling Co. v. Commissioner
127 F.2d 430 (Eighth Circuit, 1942)
Hartzell v. United States
72 F.2d 569 (Eighth Circuit, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
4 F.2d 676, 1925 U.S. App. LEXIS 3068, Counsel Stack Legal Research, https://law.counselstack.com/opinion/purington-paving-brick-co-v-metropolitan-paving-co-ca8-1925.