Seibert v. . Dunn

110 N.E. 447, 216 N.Y. 237, 1915 N.Y. LEXIS 797
CourtNew York Court of Appeals
DecidedNovember 16, 1915
StatusPublished
Cited by57 cases

This text of 110 N.E. 447 (Seibert v. . Dunn) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seibert v. . Dunn, 110 N.E. 447, 216 N.Y. 237, 1915 N.Y. LEXIS 797 (N.Y. 1915).

Opinion

Collin, J.

The action is by an assignee of a claim for •a sum of money, which arose under a contract between the defendant and the Eastern Paving Brick Company, a corporation, to recover the sum assigned. The defendant sought by his answer and upon the trial to defeat a recovery, through proof that after the sum demanded by the plaintiff had been assigned by the corporation, the corporation violated the contract under which the sum became payable and thereby caused the defendant damages in a sum greater than the sum claimed by the plaintiff. The trial court held that the defendant could not by such proof defeat the recovery, because the claim of the defendant for his damages did not exist against the corporation at the time it assigned the claim, and directed a verdict for the plaintiff for the sum claimed. The Appellate Division affirmed the judgment.

The cardinal facts, as settled by the verdict, out of which the question arises here are: In July, 1900, the corporation and the defendant entered into a contract in writing whereby the former sold the latter all the vitrified bricks requirable by him for the construction of designated sewers, deliverable as he ordered, at a designated price for each thousand used in the construction, and the latter agreed to pay, about the fifteenth of each month, “ ninety per cent of the monthly estimate or certificate showing the quantity of brick laid during the *240 preceding month ” given by the engineer, and the remaining ten per cent in thirty days after the last delivery of the bricks ordered. In June, 1901, the corporation assigned to plaintiff’s assignor the sum payable for bricks then delivered, and which became due by virtue of the certificate of the engineer about August 18, 1902. ^ About July, 1902, the corporation ceased delivering bricks, leaving the contract in large part unfulfilled and causing the defendant damages in a sum exceeding that assigned to the plaintiff. The defendant asserts, as he has from the commencement of the action, that the damages caused him by the corporation should be applied, as a counterclaim, in the cancellation of the plaintiff’s claim. The action was commenced in October, 1906.

The defense which the defendant adduces was, prior to the adoption of the Code, denominated recoupment. It enabled a defendant to abate, while admitting, a right of recovery of a plaintiff, in the sum of the damages (or a sum thereof equal to plaintiff’s claim), sustained by the defendant because of a violation by the plaintiff of a legal right of the defendant springing from the contract or transaction sued upon. The law cut off so much of the plaintiff’s claim as the damages of the defendant came to. Although consisting of a distinct cause of action in favor of a defendant, it was not identical with, though closely related to, the statutory defense of set-off, from which it differed in several particulars. It sprang from a violation by the plaintiff of a legal right of the defendant created by the. contract or transaction upon which the suit was brought and might not be a demand independent of such contractor transaction; it was a rule of the common law and not the creation of a statute; the fact that the damages of the defendant were unliquidated did not bar its operation; and a defendant could not have a judgment for the sum in which his damages exceeded those of the plaintiff nor could he maintain a subsequent action for such balance — a particular which may or may *241 not, as a statute declares, be true of set-off. (Batterman v. Pierce, 3 Hill, 171; Whitbeck v. Skinner, 7 Hill, 53; Nichols v. Dusenbury, 2 N. Y. 283; Gillespie v. Torrance, 25 N. Y. 306; Frick v. White, 57 N. Y. 103; Martin v. Kunzmuller, 37 N. Y. 396.)

The counterclaim created by our statutes embraces, at law exclusively, and is broader and more comprehensive than recoupment and set-off. Those statutes prescribe and define the fabric and regulate the exercise of a counterclaim. (Code of Civil Procedure, §§ 500-513; Deeves & Son v. Manhattan Life Ins. Co., 195 N. Y. 324; Vassear v. Livingston, 13 N. Y. 248; Fulton County G. & E. Co. v. Hudson River T. Co., 200 N. Y. 287.)

Those statutes provide: “The counterclaim * * *, must tend, in some way, to diminish or defeat the plaintiff’s recovery, and must be one of the following causes of action against the plaintiff, or, in a proper case, against the person whom he represents, and in favor of the defendant, or of one or more defendants, between whom and the plaintiff a separate judgment may be had in the action: 1. A cause of action arising out of the contract or transaction, set forth in the complaint as the foundation of the plaintiff’s claim, or connected with the subject of the action. 2. In an action on contract, any other cause of action on contract, existing at the commencement of the action.” (CodeCiv. Pro. § 501.) Section 502 of the Code declares rules expressly relating only to a counterclaim specified in subdivision second of section 501 and need not be here set forth. Section 503 provides that where an established counterclaim equals the plaintiff’s demand the judgment must be for the defendant; where it is less, the plaintiff must have judgment for the residue only, and where it exceeds the plaintiff’s demand, the defendant must have judgment for the excess, “or so much thereof as is due from the plaintiff.” From the facts as already stated, it is fairly apparent that the claimed counterclaim here is not within the second subdivision of *242 section 501. It arose out of the contract set forth in the complaint as the foundation of the plaintiff’s claim, to wit, the contract of July, 1900. The contract discloses with clarity and certainty that it was an entire and not a divisible contract. Full and complete performance on the one side constituted the consideration for performance on the other. The corporation was bound to deliver all the vitrified brick which the construction required. The subsidiary stipulations as to delivering them as ordered and as to paying for the quantity laid monthly do not split the contract into as many distinct parts or contracts as there shall be shipments or payments. The payments were merely advancements upon the whole price and not ratable payments for the performance of distinct parts. (Norrington v. Wright, 115 U. S. 188; Pakas v. Hollingshead, 184 N. Y. 211; Barrie v. Earle, 143 Mass. 1; Olmstead v. Bach, 78 Md. 132; Prautsch v. Rasmussen, 133 Wis. 181.)

The alleged counterclaim, if lawful and established, would defeat the plaintiff’s recovery. We are, therefore, brought, by the language of section 501, against the question, was it, as a cause of action, against the person whom the plaintiff represents. The common law, as generally administered, would have permitted the defendant to recoup. In Rockwell v. Daniels (4 Wis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riviera Finance of Texas, Inc. v. Capgemini US, LLC
511 F. App'x 92 (Second Circuit, 2013)
Peerless Insurance v. Michael Beshara, Inc.
75 A.D.3d 733 (Appellate Division of the Supreme Court of New York, 2010)
In Re September 11 Property Damage
481 F. Supp. 2d 253 (S.D. New York, 2007)
Enrico & Sons Contracting, Inc. v. Bridgemarket Associates
252 A.D.2d 429 (Appellate Division of the Supreme Court of New York, 1998)
Sloan v. Kubitsky, No. 309828 (Sep. 23, 1996)
1996 Conn. Super. Ct. 5598 (Connecticut Superior Court, 1996)
Leirer v. Caputo
181 A.D.2d 119 (Appellate Division of the Supreme Court of New York, 1992)
Septembertide Publishing v. Stein & Day, Inc.
884 F.2d 675 (Second Circuit, 1989)
Telmark, Inc. v. C & R Farms, Inc.
115 A.D.2d 966 (Appellate Division of the Supreme Court of New York, 1985)
Motors Insurance v. Coral Service Corp.
100 Misc. 2d 468 (Civil Court of the City of New York, 1979)
Constantino v. State
99 Misc. 2d 362 (New York State Court of Claims, 1979)
Cosmopolitan Ins. v. Feil
91 Misc. 2d 59 (Civil Court of the City of New York, 1977)
Fehlhaber Corp. v. State
90 Misc. 2d 374 (New York State Court of Claims, 1977)
Sampson v. United States
529 F.2d 1299 (Court of Claims, 1976)
Schenck v. Coordinated Coverage Corp.
50 A.D.2d 50 (Appellate Division of the Supreme Court of New York, 1975)
Allstate Insurance v. Babylon Chrysler, Plymouth, Inc.
68 Misc. 2d 1092 (Suffolk County District Court, 1972)
Goldberg v. Rothman
66 Misc. 2d 981 (Civil Court of the City of New York, 1971)
James Talcott, Inc. v. Winco Sales Corp.
199 N.E.2d 499 (New York Court of Appeals, 1964)
James Talcott, Inc. v. Winco Sales Corp.
28 Misc. 2d 612 (Appellate Terms of the Supreme Court of New York, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
110 N.E. 447, 216 N.Y. 237, 1915 N.Y. LEXIS 797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seibert-v-dunn-ny-1915.