MEMORANDUM

SHERIDAN, District Judge.

This non-jury case was tried before the Court over thirteen separate days in April and May, 2013. After trial, the parties submitted proposed findings of fact and conclusions of law as well as briefs, and thereafter, summations were heard. The Court, having considered the parties’ submissions and having deliberated over the facts and the law, submits this memorandum as its decision.

In broad terms, the issue before the Court is whether the New Jersey Long-Term Capacity Pilot Project Act, P.L. 2001, c. 9, approved Jan. 28, 2011, codified at N.J.S.A. §§ 48:3-51, 48:3-98.2-.4 (“LCAPP” or “Act”), should be declared unconstitutional as violating the Supremacy Clause, and whether the New Jersey Board of Public Utilities (“NJBPU”, “BPU”, or as referred to herein as the “Board”) should be enjoined from engaging in activities in furtherance of the Act because the LCAPP is preempted by the Federal Power Act, 16 U.S.C. § 824 et seq.. That is, whether actions by the State of New Jersey taken pursuant to the LCAPP intrude upon and interfere with the authority delegated to the Federal Energy Regulatory Commission (as referred to herein, “FERC” or “Commission”) by the Federal Power Act.

Before proceeding to the substance of this case, the Court provides two cautionary observations regarding writing style and organization and a general reservation as to the presentation and scope of the findings within this decision. First, on writing style. The electric energy industry has its own jargon which makes great use of acronyms. With so many acronyms being used, the testimony and briefs become like alphabet soup where all the letters swirl around and may confuse the reader. As such, a list of acronyms which have been substantially agreed upon by the parties is attached as Rider A. The Court minimizes use of these acronyms in this [376]*376decision. By way of reservation, the first part of the trial reviewed the extensive history of how the electric energy industry has developed into its present state. This opinion includes an overview of the relevant background for the purpose of providing sufficient information to decide the issues, however, it does not purport to be a historical work. And lastly on organization, there are many non-controversial facts presented within the Court’s overview of the relevant background, and a new term may present itself without prior introduction. In this case, the term will be explained later in the Court’s decision. After sifting through a confluence of facts, the Court has gleaned a set of manageable facts with which to evaluate the preemption issue. The decision is subdivided into several sections: (A) an identification of the parties to the action; (B) an identification of important non-parties; (C) an identification of witnesses who testified at trial; (D) a description of some basic facts regarding electricity; (E) background information on the electric energy industry; (F) a description of the “Reliability Price Model” (“RPM”) process; (G) a description of the LCAPP statute; (H) an explanation of the impacts of the LCAPP; (I) a description of the credibility of witness; (J) analysis; and (K) a conclusion.

A. PARTIES TO THE ACTION

1. Defendants

New Jersey Board of Public Utilities. The defendants are Robert M. Hanna1, Jeanne M. Fox, Joseph L. Fiordaliso, and Nicholas Asselta, all of whom are current or former commissioners of the New Jersey Board of Public Utilities2. Each is named in his official capacity against whom declaratory and injunctive relief is sought. Since each currently serves or formerly served as a commissioner on the Board, this opinion collectively refers to them as the “Board.” The Board has broad statutory authority over the activities of public utilities within the State of New Jersey. See In re Centex Homes, LLC, 411 N.J.Super. 244, 254, 985 A.2d 649 (App.Div.2009). Specifically, Title 48 of the New Jersey Statutes provides that the Board has “general supervision and regulation of and jurisdiction and control over all public utilities.” N.J.S.A. § 48:2-13(a). As part of that authority, the BPU is authorized to require any public utility operating within the State to furnish safe, adequate, and proper service to consumer ratepayers at “just and reasonable” rates. N.J.S.A. § 48:2-21.

CPV Power Development, Inc. CPV Power Development, Inc. (“CPV”) is an Intervenor/Defendant. CPV is a Delaware corporation that, through its subsidiaries, is engaged in the development, ownership, and management of natural gas-fired facilities in North America (T. 1587, 10-24). CPV owns and manages a natural gas-fired generation facility in Riverside County, California, and has taken steps to develop other natural gas-fired facilities, in-[377]*377eluding projects in Maryland, New York and New Jersey. CPV began to develop its Shore Project in New Jersey prior to implementation of the LCAPP Act. (T. 1588, 6 through T. 1589, 17). Most importantly for purposes of this case, CPV was named an eligible generator under the LCAPP by the Board and cleared the RPM Auction on its 2012 bid (T. 1588, 15-22).

2. Plaintiffs

The Plaintiffs are a group of wholesale, retail, and marketing companies who produce and sell energy and are located within the PJM market3. Several Plaintiffs are identified below.

Plaintiff Calpine Corporation is an electric generation and marketing corporation ■with a number of subsidiaries. It is a publicly traded, independent power producer based in Houston, Texas which operates ninety-one (91) power plants throughout the United States and Canada. The Calpine generation companies are physically located in the PJM market and participate in the PJM wholesale energy and capacity markets.

Plaintiff Exelon Generation Company, LLC is a Pennsylvania corporation headquartered in Kennett Square, Pennsylvania. Exelon Generation is a wholly-owned subsidiary of Exelon Corporation. Exelon Generation’s business consists of owning and operating electric generating facilities, wholesale power marketing operations, and competitive retail supply operations. Exelon Generation sells energy and capacity in the PJM interstate market and competes in PJM’s wholesale capacity auctions.

The PPL Parties are a group of related companies principally located in Allentown, Pennsylvania which are market and generation subsidiaries of PPL Corporation. They are physically located in the PJM market and participate in the PJM wholesale energy and capacity markets. Together they control or own about 19,000 megawatts of generating capacity in the United States, some of which is located within the PJM market.

Plaintiff PSEG Power, LLC is a Delaware limited liability company, headquartered in Newark, New Jersey. PSEG Power is a wholly-owned subsidiary of Public Service Enterprise Group, Inc., PSEG Power owns approximately 11,850 megawatts of generating capacity within the PJM area, approximately 9,950 megawatts of which is located in New Jersey. PSEG Power sells energy and capacity at wholesale in interstate commerce, including in PJM’s capacity and energy markets.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
977 F. Supp. 2d 372, 2013 WL 5603896, 2013 U.S. Dist. LEXIS 147273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ppl-energyplus-llc-v-hanna-njd-2013.