PMTech, Inc. v. United States

95 Fed. Cl. 330, 2010 U.S. Claims LEXIS 812, 2010 WL 4323203
CourtUnited States Court of Federal Claims
DecidedOctober 20, 2010
DocketNo. 10-458 C
StatusPublished
Cited by16 cases

This text of 95 Fed. Cl. 330 (PMTech, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PMTech, Inc. v. United States, 95 Fed. Cl. 330, 2010 U.S. Claims LEXIS 812, 2010 WL 4323203 (uscfc 2010).

Opinion

OPINION

BUSH, Judge.

Now pending before the court are the parties’ cross motions for judgment on the administrative record, which have been fully briefed and are ripe for a decision by the court. Although the parties’ motions were not captioned as such, the court believes that the motions are most appropriately treated as cross motions for judgment on the administrative record pursuant to Rule 52.1(c) of the Rules of the United States Court of Federal Claims (RCFC). Plaintiff PMTech, Inc. (PMTech) challenges defendant’s decision to override an automatic stay of the performance of a task order that is the subject of a pending bid protest before the Government Accountability Office (GAO).

Because PMTech has failed to demonstrate that defendant’s decision to override the automatic stay of performance was arbitrary, capricious, an abuse of discretion or otherwise contrary to law, the court is unable to award the relief plaintiff seeks. Accordingly, PMTech’s motion for judgment on the administrative record is hereby denied, and defendant’s motion for judgment on the administrative record is granted. Subsequent to oral argument, and after careful consideration, the court orally denied PMTech’s motion on August 3, 2010. This opinion articulates that determination.

BACKGROUND2

I. Factual History

A. Procurement History and Protests

The Oak Ridge National Laboratory (ORNL) is located in Oak Ridge, Tennessee and is part of a larger United States Departs ment of Energy (DOE) complex known as the Oak Ridge Reservation (ORR). AR at 410. The ORR was established in the early 1940s as part of the World War II Manhattan Project to support the development of the world’s first atomic weapon. Id. DOE’s activities on the ORR over the past sixty years have resulted in significant radioactive and other hazardous contamination at a number of facilities on the site. Id. The ORNL is currently operated and managed by UT-Bat-telle, LLC (UT-Battelle) under a five-year contract with DOE. Compl. Ex. O.

DOE is the lead agency responsible for the environmental remediation of the entire ORR complex, including the ORNL. AR at 410-11. The environmental cleanup of the ORR is managed under DOE’s Environmental Management (EM) program. AR at 411. On November 7, 2003, defendant issued a solicitation for, inter alia, the deactivation, demolition and removal of contaminated buildings at various DOE facilities. Compl. ¶ 11. DOE awarded several indefinite-delivery, indefinite-quantity (IDIQ) base contracts for such work under the EM program. AR at 576. Individual projects are awarded as task orders under the base contracts. On Oeto-[335]*335ber 7, 2004, both plaintiff and Safety and Ecology Corporation (SEC) were awarded IDIQ base contracts.3 See AR at 566, 576. The base contracts were in effect between October 7, 2004 and April 6, 2010.4

On June 15, 2009, defendant issued a solicitation for various environmental remediation services at two buildings located at the ORNL. Compl. ¶¶ 4, 12. Defendant advertised the solicitation as a full and open competition. Id. ¶ 2. On July 20, 2009, plaintiff filed the first of three bid protests with the GAO related to the remediation work at issue in this case. AR Tab 21. In that protest, plaintiff argued that defendant was required to limit competition for the task order to small businesses. See AR at 579-81. In response, defendant elected to take corrective action and moved to dismiss PMTeeh’s bid protest as academic on August 3, 2009. AR Tab 22.

On October 1, 2009, defendant issued a request for task proposals (RFTP) for the proposed work on Buildings 3026 and 3038 and limited participation in the procurement to small businesses with IDIQ base contracts. AR Tab 1. The task order involves the demolition and disposition of several nuclear’ radiation containment chambers, known as “hot cells,” located within Building 3026 at the ORNL. AR at 9. Under the task order, the contractor is required to decontaminate and demolish the hot cells to grade, remove and dispose of the resulting debris, and decontaminate the remaining slab. AR at 14, 23. The RFTP also calls for the removal and disposal of legacy material from Building 3038, also located at the ORNL, in preparation for its subsequent disposition and demolition. AR at 14-16, 23. Finally, the RFTP includes optional line items for the disposition and demolition of Building 3038 and the removal of legacy material and related work on two other buildings at the ORNL. AR at 17-21. The RFTP indicates that the task order would be funded through the American Recovery and Reinvestment Act of 2009 (ARRA), Pub.L. No. 111-5, 123 Stat. 115, on a eost-plus-award-fee basis. AR at 4-5, 43-48. Under the statement of work, the task order is to be completed no later than September 30, 2011. AR at 22. Defendant received proposals from only two offerors, PMTech and SEC, and subsequently awarded the task order to SEC on March 30, 2010. AR Tab 2. Although plaintiff was the lowest-cost offeror, defendant concluded that SEC had submitted a technically superior proposal that would provide the best value to the government. AR at 214.

Following the submission of task order proposals by plaintiff and SEC, the roof of Building 3026 collapsed, disabling the facility’s fire-protection system. PL’s Reply Ex. A. In January 2010, Clauss Construction (Clauss), under a subcontract with UT-Bat-telle, completed the removal of the building’s entire wooden superstructure. Id. Before removing the superstructure, Clauss sprayed the building’s hot cells with a polyurea coating to prevent the spread of contamination on the site. AR at 588. The debris from the demolition project, which was highly contaminated with radiation, was temporarily piled in the charging room area of the building and was subsequently removed from the site. AR at 589. During one particularly heavy storm in January 2010, rainfall overwhelmed the runoff containment system and contamination spread onto the ramp adjacent to Building 3026 leading to a nearby public roadway. AR at 589. Those areas were subsequently decontaminated by pressure washing and scabbling, and the government discovered no evidence that the contamination had spread to the storm drains. Id.

Since the removal of the building’s superstructure, the hot cells have been exposed to [336]*336the elements, and multiple decontamination efforts have been required with respect to the hot cells and the adjacent charging room area. AR at 591-94. In addition, the polyu-rea fixative has been damaged by the rain, requiring remediative work by Clauss and InstaCote, the vendor of the sealant. AR at 592, 595.

On April 2, 2010, plaintiff filed a size protest with the Small Business Administration (SBA), in which it argued that SEC exceeded the size limitation set forth in the RFTP. Compl. ¶ 31. One week later, plaintiff filed a second bid protest with the GAO. AR Tab 4. In that protest, plaintiff argued that the substantial adjustments made to SEC’s proposed costs reflected a lack of technical understanding on the part of SEC that was not reflected in defendant’s evaluation of SEC’s technical proposal. AR at 236-39. Defendant once again elected to take corrective action in response to the protest, and the GAO therefore dismissed that protest as academic on May 19, 2010. AR Tab 6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
95 Fed. Cl. 330, 2010 U.S. Claims LEXIS 812, 2010 WL 4323203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pmtech-inc-v-united-states-uscfc-2010.