Plan-Tec, Inc. v. Wiggins

443 N.E.2d 1212, 1983 Ind. App. LEXIS 2510
CourtIndiana Court of Appeals
DecidedJanuary 11, 1983
Docket1-881A250
StatusPublished
Cited by109 cases

This text of 443 N.E.2d 1212 (Plan-Tec, Inc. v. Wiggins) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plan-Tec, Inc. v. Wiggins, 443 N.E.2d 1212, 1983 Ind. App. LEXIS 2510 (Ind. Ct. App. 1983).

Opinion

RATLIFF, Judge.

STATEMENT OF THE CASE

Defendant Plan-Tec, Inc. appeals from a jury verdict in the Clark Circuit Court awarding plaintiffs Ivan and Janice Wiggins damages for employment-related injuries sustained by Ivan and denying Plan-Tec’s crossclaim against the Blakley Corporation and its third-party complaint against the Terstep Company, Inc. 1 We affirm.

FACTS

This case arises from a construction-related injury suffered by the plaintiff Ivan Wiggins and his wife’s consequent loss of consortium. Wiggins was employed as a journeyman carpenter by Terstep Company, Inc. Terstep was, in turn, one of a number of subcontractors engaged in providing services for the North Clark Community Hospital project in Charlestown, Indiana. The hospital project was not undertaken according to the traditional general contractor/subcontractor model. Rather, Plan-Tec assumed the role of construction manager and, acting as the hospital’s agent, negotiated contracts between the owners and the contractors. As the construction manager, Plan-Tec coordinated the project from inception to completion and was paid a flat fee therefor. The Charlestown job was Plan-Tec’s first job as a construction manager.

On the day of the accident Wiggins was to change expansion joints on the exterior skin of the building in order to suit the architect’s modifications. Plan-Tec informed the Blakley Corporation of the need to change the expansion joints. Blakley discussed this with both its subcontractors for exterior work, one of which was Ter-step. 2 Both said this was not work within the contemplation of their contracts. Plan-Tec then assumed the responsibility for the work order and had it performed by Ter-step.

Wiggins and a co-worker, Frank Bratcher, were assigned to complete the job of changing the expansion joints. Both men went to the roof to check the outrigging and counterweighting of the suspended scaffold from which they would be working. While the outrigging was generally coun- *1217 terweighted by punching holes in the precast concrete roof and anchoring the scaffold to the building via steel cables run through the holes in the roof, in this case the outrigging was counterweighted by five-gallon buckets of hardened concrete. Bratcher informed Wiggins that the roofers were working in that area and it was, therefore, not possible to drive holes into the roof. He also stated that the buckets had been used before.

After testing the scaffold at ground level, the two men raised the scaffold to the sixth floor where they were to work. As Bratcher went to Wiggins’s end of the scaffold to demonstrate the work to be performed, the structure broke loose and fell to the ground below.

Wiggins initiated this action against Plan-Tec, Blakley, Taylor, and Terstep and was awarded $700,000.00 in damages against Plan-Tec for its failure to ensure proper safety on the job. Janice Wiggins was awarded $50,000.00 for loss of consortium. Plan-Tec’s third-party claim against Terstep for indemnity was also denied. From this action Plan-Tec now appeals.

ISSUES

Appellant presents fourteen issues for review. Combined and rephrased, the issues are as follows:

1. Did the trial court err in upholding the jury’s verdict?

2. Did the trial court err in not granting Plan-Tec’s motion for judgment on the evidence at the close of all the evidence?

3. Did the trial court err in giving Ter-step’s instruction number 10B?

4. Did the trial court err in denying Plan-Tec’s motion for continuance?

5. Did the trial court err in giving Wig-ginses’ instructions numbered 2 and 9?

6. Did the trial court err in refusing to give Plan-Tec’s tendered instruction number 9?

7. Did the trial court err in refusing to give Plan-Tec’s tendered instruction number 5?

8. Did the trial court err in allowing certain testimony of Anthony Rago in contravention of Plan-Tec’s motion in limine?

9. Did the trial court err in refusing to permit Plan-Tee relief from Wigginses’ motion in limine?

10. Did the trial court err in excluding certain deposition testimony of James Vest?

11. Did the trial court err in permitting Nicholas Hatfield to testify regarding Ter-step’s inability to negotiate the terms of the general conditions of the contract?

DISCUSSION AND DECISION

Issue One

The trial court did not err in upholding the jury’s verdict.

Central to Plan-Tec’s argument on appeal is its contention that Plan-Tec owed no duty to Wiggins as a matter of law. Since no duty existed, argues Plan-Tec, the award by the jury was contrary to law and the trial court, therefore, erred in upholding the jury’s verdict. Wigginses argue that a duty arose from the contract itself or, in the alternative, that Plan-Tec gratuitously assumed the duty of care for the employees of Terstep and that a breach of such duty gave rise to actionable negligence. We agree with the Wigginses’ latter contention.

In reviewing an allegation that a jury verdict is contrary to law, the verdict will be set aside only where it is against the evidence, where there is a total lack of evidence, or where it is contrary to uncontradicted evidence. Sutton v. Roth, Wehrly, Heiny, Inc., (1981) Ind.App., 418 N.E.2d 229, 232, trans. denied. This court will not reweigh evidence or resolve the credibility of witnesses. Riverside Insurance Co. v. Pedigo, (1982) Ind.App., 430 N.E.2d 796, 803. Rather, our inquiry is limited to determining whether the verdict is sustained by substantial evidence of probative value. Id. Further, this court will indulge every reasonable presumption in favor of the correctness of the jury’s verdict. Illinois Central Gulf Railroad Co. v. Parks, (1979) Ind.App., 390 N.E.2d 1073, 1074, trans. denied. *1218 Where the evidence is susceptible to reasonably differing interpretations, the jury’s verdict will not be disturbed.

In bringing a negligence action the burden of proving negligence is upon the plaintiff. Hi-Speed Auto Wash, Inc. v. Simeri, (1976) 169 Ind.App. 116, 119, 346 N.E.2d 607, 608. In order to prevail upon an allegation of negligence, the plaintiff’s evidence must be sufficient to demonstrate the existence of all the requisite elements of the cause of action. Koroniotis v. LaPorte Transit, Inc., (1979) Ind.App., 397 N.E.2d 656, 659. One of those elements is a duty owed to the plaintiff by the defendant. Bowling v. Holdeman, (1980) Ind.App., 413 N.E.2d 1010, 1014; Koroniotis. Absent such a duty there can be no actionable negligence.

A duty of care, the breach of which will support a negligence action, may arise contractually.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Judy Reece v. Tyson Fresh Meats, Inc.
Indiana Court of Appeals, 2020
Daniel Lee and Hui Luo Lee v. GDH, LLC
25 N.E.3d 761 (Indiana Court of Appeals, 2015)
Christian Dailey v. David Building Group
Indiana Court of Appeals, 2014
Joseph Mike Barnett v. JDH Contracting
Indiana Court of Appeals, 2014
Jeff Clade v. Hunt Construction Group, Inc.
Indiana Court of Appeals, 2013
Hunt Construction Group, Inc. v. Garrett
964 N.E.2d 222 (Indiana Supreme Court, 2012)
Hunt Construction Group, Inc. v. Garrett
938 N.E.2d 794 (Indiana Court of Appeals, 2010)
As v. LaPORTE REGIONAL HEALTH SYSTEM
921 N.E.2d 853 (Indiana Court of Appeals, 2010)
Lumbermens Mutual Casualty Co. v. Combs
873 N.E.2d 692 (Indiana Court of Appeals, 2007)
Del Signore v. Asphalt Drum Mixers
182 F. Supp. 2d 730 (N.D. Indiana, 2002)
Schrieber v. Walker
79 F. Supp. 2d 965 (N.D. Indiana, 1999)
Helen C. Holtz v. J.J.B. Hilliard W.L. Lyons, Inc.
185 F.3d 732 (Seventh Circuit, 1999)
Delta Tau Delta, Beta Alpha Chapter v. Johnson
712 N.E.2d 968 (Indiana Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
443 N.E.2d 1212, 1983 Ind. App. LEXIS 2510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plan-tec-inc-v-wiggins-indctapp-1983.