Joseph Mike Barnett v. JDH Contracting

CourtIndiana Court of Appeals
DecidedMarch 13, 2014
Docket32A01-1307-CT-332
StatusUnpublished

This text of Joseph Mike Barnett v. JDH Contracting (Joseph Mike Barnett v. JDH Contracting) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Mike Barnett v. JDH Contracting, (Ind. Ct. App. 2014).

Opinion

Pursuant to Ind. Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of establishing Mar 13 2014, 10:08 am the defense of res judicata, collateral estoppel, or the law of the case.

ATTORNEYS FOR APPELLANT: ATTORNEY FOR APPELLEE:

TIMOTHY F. DEVEREUX JAMES J. HUTTON LANCE R. LADENDORF Indianapolis, Indiana Ladendorf & Landendorf Indianapolis, Indiana

IN THE COURT OF APPEALS OF INDIANA

JOSEPH MIKE BARNETT, ) ) Appellant-Plaintiff, ) ) vs. ) No. 32A01-1307-CT-332 ) JDH CONTRACTING, ) ) Appellee-Defendant. )

APPEAL FROM THE HENDRICKS CIRCUIT COURT The Honorable Carol J. Orbison, Senior Judge Cause No. 32C01-1102-CT-16

March 13, 2014

MEMORANDUM DECISION - NOT FOR PUBLICATION

CRONE, Judge Case Summary

Joseph Mike Barnett appeals the trial court’s entry of summary judgment in favor of

JDH Contracting, Inc. (“JDH”), on Barnett’s claim for negligence. Barnett, an employee of a

subcontractor, was injured while performing demolition work on a construction site for

which JDH was acting as general contractor. Barnett filed a complaint for negligence against

JDH alleging, among other things, that JDH was negligent in failing to provide him a safe

workplace. JDH moved for summary judgment asserting that it owed no duty to Barnett as a

matter of law. Barnett responded and asserted that JDH owed a nondelegable duty to him

pursuant to contract, or in the alternative, that JDH gratuitously assumed a duty to him

through affirmative conduct. The trial court entered summary judgment in favor of JDH.

The sole issue presented for our review is whether the trial court erred when it entered

summary judgment in favor of JDH. Finding as a matter of law that JDH did not owe Barnett

a duty pursuant to contract but that a genuine issue of material fact remains as to whether

JDH assumed a duty to Barnett through its affirmative conduct, we reverse and remand.

Facts and Procedural History1

The undisputed facts indicate that, on or about June 30, 2010, JDH entered into a

1 In its appellee’s brief, JDH requests that we strike Barnett’s “Statement of the Case” as improperly including extensive argument and disputed facts rather than a brief description of “the nature of the case, the course of proceedings relevant to the issues presented for review, and the disposition of these issues by the trial court.” Ind. Appellate Rule 46(A)(5). We agree with JDH and exercise our authority pursuant to Indiana Appellate Rule 42 to order the inappropriate and impertinent matter stricken. We also note that Barnett’s counsel included a copy of the summary judgment hearing transcript in the appellant’s appendix in violation of Indiana Appellate Rule 50(F), which says, “Because the Transcript is transmitted to the Court on Appeal pursuant to Rule 12(B), parties should not reproduce any portion of the Transcript in the Appendix.” We recommend that Barnett’s counsel follow our appellate rules in future filings with this Court.

2 verbal contract with PWG Real Estate to perform renovations on a warehouse in Plainfield.

JDH hired a subcontractor, R.F. Mac, Inc. (“R.F. Mac”), to remove a second floor mezzanine

area of the warehouse. JDH had a verbal agreement with R.F. Mac which was based upon a

written bid proposal for the work submitted by R.F. Mac and accepted by JDH. R.F. Mac

began its work on the project on August 9, 2010. Barnett was hired by R.F. Mac to work on

the project shortly thereafter.

On August 19, 2010, Barnett was working at the warehouse removing four-foot-by-

eight-foot pieces of steel decking. As Barnett was attempting to drop one of the pieces of

steel decking from the second floor to the first floor, a sharp edge of the decking made

contact with his left forearm causing a significant cut.

Barnett filed a complaint for negligence against JDH alleging, among other things,

that JDH was negligent in failing to provide him a safe workplace, resulting in his injuries.

JDH subsequently moved for summary judgment arguing that it owed no duty of care to

Barnett as a matter of law. Barnett responded arguing that JDH assumed a nondelegable duty

of care to him pursuant to contract and through its affirmative conduct. Following a hearing,

the trial court entered its order granting summary judgment in favor of JDH. This appeal

ensued.

Discussion and Decision

Barnett appeals the trial court’s grant of JDH’s motion for summary judgment. We

are reminded that:

When reviewing a grant or denial of a motion for summary judgment our well- settled standard of review is the same as it is for the trial court: whether there

3 is a genuine issue of material fact, and whether the moving party is entitled to judgment as a matter of law. Summary judgment should be granted only if the evidence sanctioned by Indiana Trial Rule 56(C) shows that there is no genuine issue of material fact and the moving party deserves judgment as a matter of law. All factual inferences must be construed in favor of the non- moving party, and all doubts as to the existence of a material issue must be resolved against the moving party.

Kroger Co. v. Plonski, 930 N.E.2d 1, 4-5 (Ind. 2010) (citations omitted). The party appealing

a trial court’s grant of summary judgment bears the burden of persuading this Court that the

ruling was erroneous. Morris v. Crain, 969 N.E.2d 119, 123 (Ind. Ct. App. 2012).

Barnett’s claim against JDH sounds in negligence. To prevail on a negligence claim,

the plaintiff must show: (1) a duty owed to the plaintiff by the defendant; (2) a breach of duty

by allowing conduct to fall below the applicable standard of care; and (3) a compensable

injury proximately caused by the defendant’s breach of duty. Kroger, 930 N.E.2d at 6.

Summary judgment is rarely appropriate in negligence cases. Rhodes v. Wright, 805 N.E.2d

382, 387 (Ind. 2004). However, summary judgment is appropriate when the undisputed

material evidence negates one element of a negligence claim. Winfrey v. NLMP, Inc., 963

N.E.2d 609, 612 (Ind. Ct. App. 2012). Absent a duty, there can be no breach, and therefore

no recovery in negligence. Pfenning v. Lineman, 947 N.E.2d 392, 398 (Ind. 2011). “The

existence of a duty is a pure question of law for the court to determine.” Stumpf v. Hagerman

Constr. Corp., 863 N.E.2d 871, 876 (Ind. Ct. App. 2007), trans. denied.

In support of its motion for summary judgment, JDH asserted that it owed no duty to

provide Barnett a safe workplace. It is well established in Indiana that an employer or

general contractor does not have a duty to supervise the work of an independent contractor to

4 assure a safe workplace, and accordingly, is not liable for the negligence of an independent

contractor. Capitol Constr. Servs., Inc. v. Gray, 959 N.E.2d 294, 298 (Ind. Ct. App. 2011).

“The rationale behind this rule is that a ‘general contractor typically exercises little, if any,

control over the means or manner of the work of its subcontractors, and requires only that the

completed work meet the specifications of the owner of its contract with the general

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hunt Construction Group, Inc. v. Garrett
964 N.E.2d 222 (Indiana Supreme Court, 2012)
Pfenning v. Lineman
947 N.E.2d 392 (Indiana Supreme Court, 2011)
Kroger Co. v. Plonski
930 N.E.2d 1 (Indiana Supreme Court, 2010)
Rhodes v. Wright
805 N.E.2d 382 (Indiana Supreme Court, 2004)
Plan-Tec, Inc. v. Wiggins
443 N.E.2d 1212 (Indiana Court of Appeals, 1983)
Smith v. King
902 N.E.2d 878 (Indiana Court of Appeals, 2009)
Insuremax Insurance Co. v. Bice
879 N.E.2d 1187 (Indiana Court of Appeals, 2008)
Bagley v. Insight Communications Co., LP
658 N.E.2d 584 (Indiana Supreme Court, 1995)
Stumpf v. Hagerman Construction Corp.
863 N.E.2d 871 (Indiana Court of Appeals, 2007)
Beatty v. LaFountaine
896 N.E.2d 16 (Indiana Court of Appeals, 2008)
Robinson v. Kinnick
548 N.E.2d 1167 (Indiana Court of Appeals, 1989)
Merrill v. Knauf Fiber Glass GmbH
771 N.E.2d 1258 (Indiana Court of Appeals, 2002)
Harris v. Kettelhut Construction, Inc.
468 N.E.2d 1069 (Indiana Court of Appeals, 1984)
Dunaway v. Allstate Insurance Co.
813 N.E.2d 376 (Indiana Court of Appeals, 2004)
Marks v. Northern Indiana Public Service Co.
964 N.E.2d 238 (Indiana Court of Appeals, 2011)
Winfrey v. NLMP, INC.
963 N.E.2d 609 (Indiana Court of Appeals, 2012)
Morris v. Crain
969 N.E.2d 119 (Indiana Court of Appeals, 2012)
Marks v. Northern Indiana Public Service Co.
954 N.E.2d 948 (Indiana Court of Appeals, 2011)
Capitol Construction Services, Inc. v. Gray
959 N.E.2d 294 (Indiana Court of Appeals, 2011)
Shawnee Construction & Engineering, Inc. v. Stanley
962 N.E.2d 76 (Indiana Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Joseph Mike Barnett v. JDH Contracting, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-mike-barnett-v-jdh-contracting-indctapp-2014.