Phillips Petroleum Co. v. Bucyrus-Erie Co.

388 N.W.2d 584, 131 Wis. 2d 21, 1 U.C.C. Rep. Serv. 2d (West) 667, 1986 Wisc. LEXIS 1899
CourtWisconsin Supreme Court
DecidedJune 23, 1986
Docket84-152
StatusPublished
Cited by25 cases

This text of 388 N.W.2d 584 (Phillips Petroleum Co. v. Bucyrus-Erie Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips Petroleum Co. v. Bucyrus-Erie Co., 388 N.W.2d 584, 131 Wis. 2d 21, 1 U.C.C. Rep. Serv. 2d (West) 667, 1986 Wisc. LEXIS 1899 (Wis. 1986).

Opinion

*24 HEFFERNAN, CHIEF JUSTICE.

This is a review of a decision of the court of appeals 1 which reversed a judgment of the circuit court for Milwaukee county, Michael D. Goulee, circuit judge, awarding Phillips Petroleum Company, Norway, in excess of $1,600,000 in a breach of contract and negligence action against Bucyrus-Erie Company. We reverse the decision of the court of appeals and reinstate the judgment of the circuit court.

Phillips is an oil company operating drilling platforms in the Norwegian sector of the North Sea. In the early 1970's Phillips invited several crane manufacturers, including Bucyrus-Erie, to submit proposals for the sale of cranes to be used on their off-shore drilling platforms. The invitations described the weather conditions and the stresses of wind and wave under which the cranes would be expected to perform. Bucyrus-Erie, in March and April of 1971, submitted proposals for the sale of certain cranes manufactured by it, including proposals for the fabrication of adapters to allow the placement of the cranes on the various oil rigs operated by Phillips. The proposals were "accepted" by Phillips' "Purchase Order." Bucyrus-Erie proceeded with manufacture and delivery. The cranes and adapters were installed on 13 drilling rigs in the North Sea in 1973. On February 28, 1974, while Phillips was using one of the cranes to unload supplies from a ship, the crane broke loose from the platform and fell into the sea. As a consequence of this incident, it was concluded that the steel in the adapters was too brittle for the in *25 tended use. The use of the cranes was suspended by order of the Norwegian inspection service. Subsequently, the adapter rings were replaced and certification for use was reinstated. Phillips brought this action against Bucyrus-Erie, claiming that the seller had breached its contract by failing to supply adapter rings made from the type of steel specified.

The jury found that Bucyrus-Erie had "breachfed] their contract that the pedestal adapter would be fabricated from steel as requested" by Phillips. It also found that such breach was a cause of the damage to the plaintiffs. The circuit judge sustained the jury's findings and their verdict for damages for replacement costs and consequential damages. 2

In motions after verdict, the circuit court undertook an analysis of the transaction between Phillips and Bucyrus-Erie. It pointed out that the proposal of Bucyrus-Erie constituted an offer and the purchase order of Phillips which followed was an acceptance of that offer. It held that, under the facts, Phillips had created an express warranty for a specified quality of steel in conformity with sec. 402.313, Stats. 3 (Chapter *26 402, Stats., is the Wisconsin enactment of the Uniform Commercial Code — Sales.)

The court elected to disregard the disclaimers of Bucyrus-Erie contained in its proposals, because the purchase order, Phillips' Acceptance, contained on its face the boldface, contrasting colors-over-stamp legend:

"THIS ORDER EXPRESSLY LIMITS ACCEPTANCE TO THE TERMS STATED HEREIN. PURCHASER OBJECTS TO ANY ADDITIONAL OR DIFFERENT TERMS OF THE SELLER."

Under the rationale adopted by the trial court, it first concluded that there was a contract, i.e., the parties had a "deal" to buy and sell cranes and their adapters, the seller had stated certain disclaimers in its offer, and the purchase order of the buyer disavowed *27 being bound by any terms ip the proposals that were not contained in the acceptance, the purchase order.

Thus, following the approach of White and Summers, Uniform Commercial Code (West hornbook series) and as indicated by sec. 402.316(1), Stats., 4 the trial judge concluded that, where the contract documents contain conflicting warranty terms, none of them became a part of the contract and, instead, the implied warranties of the code are imported into the contract as "gap fillers." 5 This approach, as Judge *28 Goulee believed, was specifically approved by this court in Air Products & Chemicals, Inc. v. Fairbanks Morse, Inc., 58 Wis. 2d 193, 206 N.W.2d 414 (1973). 6

The principal provisions in the proposal of Bucyrus-Erie eliminated by the trial court were the warranties and disclaimers appearing in 3A:

"WARRANTY
"3A. Manufacturer warrants the machinery, and all spares, replacements, tools and auxiliary equipment, now or hereafter furnished by it therefor, to be built in a workmanlike manner of sound high-grade material, and, under normal use and proper attention to operate properly. Any claim made under this warranty must be presented in writing to Manufacturer at South Milwaukee, Wisconsin, within six months after shipment or, in the case of Transit Crane carrier units whether or not sold separately, or any parts thereof, within six months after shipment or 4,000 miles travel, whichever first occurs. Manufacturer is to have the option of replacing F.O.B. works any element proved to be defective or of remedying any proved defect, but Manufacturer's liability in any event shall not exceed the re *29 placement value of the defective element F.O.B. works, and in the case of units or parts purchased by Manufacturer, Manufacturer's liability shall not exceed the settlement which Manufacturer is able to obtain from its supplier. Manufacturer is to have a reasonable length of time, after recognition of claim, in which to exercise its above option, and shall have the right to require the return of the alleged defective element, transportation charges prepaid, before recognizing any claim. No allowance will be made for repairs or alterations undertaken without Manufacturer's written consent. If parts other than of the original manufacturer are used in replacement without Manufacturer's written consent, or if the purchaser falls in arrears in making any payment, or if, without Manufacturer's written consent, the machinery is repaired or altered in such a way as in Manufacturer's judgment to reduce its stability or reliability, or if the machinery is subjected to misuse, negligence or accident, all warranties are thereby waived. The fore-going warranty is in lieu of all tort liability and all other warranties or representations or rights of rejection, express or implied, by law or by contract. More specifically, but without restriction thereto, there is no representation or express or implied warranty that the machinery complies with the highway or other laws of any state. No agent, distributor or other person is authorized to give any other warranty, nor to assume any other liability."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanchelima Int'l, Inc. v. Walker Stainless Equip. Co.
920 F.3d 1141 (Seventh Circuit, 2019)
Tankstar USA, Inc. v. Navistar, Inc.
2019 WI App 1 (Court of Appeals of Wisconsin, 2018)
Southern Financial Group, LLC v. McFarland State Bank
763 F.3d 735 (Seventh Circuit, 2014)
Peterson v. Cornerstone Property Development, LLC
2006 WI App 132 (Court of Appeals of Wisconsin, 2006)
Rite Aid Corp. v. Levy-Gray
894 A.2d 563 (Court of Appeals of Maryland, 2006)
Rich Products Corp. v. Kemutec, Inc.
66 F. Supp. 2d 937 (E.D. Wisconsin, 1999)
Chapman v. Mutual Service Casualty Insurance
35 F. Supp. 2d 699 (E.D. Wisconsin, 1999)
Champlain Enterprises, Inc. v. United States
957 F. Supp. 26 (N.D. New York, 1997)
Comp-U-Aid, Inc. v. Berk-Tek, Inc.
547 N.W.2d 640 (Michigan Supreme Court, 1995)
Grube v. Daun
496 N.W.2d 106 (Court of Appeals of Wisconsin, 1992)
Elite Professionals, Inc. v. Carrier Corp.
827 P.2d 1195 (Court of Appeals of Kansas, 1992)
Ragen Corporation v. Kearney & Trecker Corporation
912 F.2d 619 (Third Circuit, 1990)
Ragen Corp. v. Kearney & Trecker Corp.
912 F.2d 619 (Third Circuit, 1990)
Midwhey Powder Co. v. Clayton Industries
460 N.W.2d 426 (Court of Appeals of Wisconsin, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
388 N.W.2d 584, 131 Wis. 2d 21, 1 U.C.C. Rep. Serv. 2d (West) 667, 1986 Wisc. LEXIS 1899, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-petroleum-co-v-bucyrus-erie-co-wis-1986.