Buddy's Plant Plus Corporation v. Viking Masek Global Packaging Technologies, LLC

CourtCourt of Appeals of Wisconsin
DecidedJuly 30, 2025
Docket2023AP002428
StatusPublished

This text of Buddy's Plant Plus Corporation v. Viking Masek Global Packaging Technologies, LLC (Buddy's Plant Plus Corporation v. Viking Masek Global Packaging Technologies, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buddy's Plant Plus Corporation v. Viking Masek Global Packaging Technologies, LLC, (Wis. Ct. App. 2025).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. July 30, 2025 A party may file with the Supreme Court a Samuel A. Christensen petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2023AP2428 Cir. Ct. No. 2020CV145

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT II

BUDDY’S PLANT PLUS CORPORATION,

PLAINTIFF-APPELLANT,

V.

VIKING MASEK GLOBAL PACKAGING TECHNOLOGIES, LLC,

DEFENDANT-THIRD-PARTY PLAINTIFF-RESPONDENT,

M&S AUTOMATED FEEDING SYSTEMS INC.,

THIRD-PARTY DEFENDANT.

APPEAL from a judgment of the circuit court for Sheboygan County: GEORGE A. LIMBECK, Judge. Affirmed.

Before Neubauer, Grogan, and Lazar, JJ. No. 2023AP2428

¶1 NEUBAUER, J. Viking Masek Global Packaging Technologies, LLC entered into a contract with Buddy’s Plant Plus Corporation under which Viking agreed to manufacture a custom machine that Buddy’s planned to use to prepare and package bedbug detection products for one of its customers. Despite considerable efforts by the parties, Viking ultimately failed to deliver the machine. Buddy’s sued, and after a bench trial, the trial court concluded that Viking had breached the contract.1 But the court construed language in a warranty clause of the contract stating that Viking’s “maximum liability hereunder is limited to the amount paid to [it]” as limiting Buddy’s recoverable damages to the amounts it had paid Viking. The court denied Buddy’s request for consequential damages.

¶2 Buddy’s appeals from the judgment entered after the trial, contending that the trial court erred in limiting its recovery and that it was entitled to recover consequential damages under the Wisconsin Uniform Commercial Code (UCC or Code). Specifically, Buddy’s argues that: (1) the warranty clause does not apply to Viking’s failure to deliver the machine; (2) the limited remedy failed of its essential purpose and thus does not bar an award of consequential damages; and (3) the contractual language limiting Viking’s liability is unconscionable. Buddy’s also challenges the court’s conclusion that it failed to prove its consequential damages to a reasonable certainty.

¶3 As explained below, we conclude that the warranty clause does apply to Viking’s breach of contract. Furthermore, the limitation of liability language in the clause does not fail of its essential purpose and is not unconscionable. Because we conclude that the clause applies to Viking’s breach

1 Viking does not challenge the trial court’s conclusion that it breached the contract.

2 No. 2023AP2428

and is enforceable, we need not reach the issue of whether Buddy’s proved its damages to a reasonable certainty. We affirm.

BACKGROUND

¶4 Buddy’s blends, fills, and packages products for retail sale. Its largest client, Scotts MiracleGro, approached it about packaging a bedbug detection product. The product consists of a small plastic tube containing liquid lure. The tube is packaged into a foil stick pack that is then placed inside the product. A user activates the product by pushing a button on the plastic case which punctures a hole in the stick pack, allowing the odor from the liquid lure to spread into the area surrounding the product and draw bedbugs into it.

¶5 Buddy’s owner, Edward Studer, testified about how Buddy’s began manufacturing the products and eventually entered into the contract with Viking at issue here. According to Studer, after Scotts approached Buddy’s about assembling and packaging the products, the two companies worked to design a machine that would place the liquid lure in the tubes and seal the tubes at both ends. Buddy’s built multiple of these “lure machines,” which drop the tubes into buckets after sealing them. The tubes would then be collected and vacuum tested to make sure they did not leak. After the testing was completed, a Buddy’s employee would collect the tubes and take them to a second, “prototype” stick pack machine, where they would be fed into the machine “one by one” to be sealed in the foil stick pack. According to Studer, this “prototype … was sufficient for our initial start-up procedure, but we knew [it] was not a method that we could keep.” It was labor intensive—requiring an employee to work “multiple shifts” each day feeding the tubes into the prototype machine—and created a “bottle neck” in the production process because the lure machines could make and

3 No. 2023AP2428

seal the tubes faster than they could be fed through the prototype. So, in 2016, Buddy’s contacted several companies about manufacturing a stick pack machine that would wrap the tubes more quickly and require less labor to operate.

¶6 Viking was one of the companies that submitted a bid to manufacture a stick pack machine for Buddy’s. Viking proposed to build a stick pack machine that would have ten vertical lanes into which the tubes would drop and be encased in the stick pack. Viking’s bid included two additional components: a printer and an “Inline Track Feeder” system that would be manufactured by M&S Automated Feeding Systems Inc. As described by Viking’s project manager at the time, the feeder system would include two bowls that would sit on top of the machine. The tubes would be dropped into the bowls, which would vibrate and cause the tubes to become “oriented with the long axis of the [tubes] in the direction of travel, end to end, single file in each of ten lanes,” at which point a trigger mechanism would “drop a single tube from each of the 10 lanes into” the stick pack machine.

¶7 Viking’s bid identified a total price of $259,450 for the stick pack machine, M&S feeder system, and printer. Studer signed the bid on June 2, 2017, and Buddy’s issued a purchase order for the contract price.

¶8 Viking’s bid, which became the parties’ contract, required Buddy’s to pay 50% of the total contract price upon signing the bid, an additional 45% when Viking sent a second invoice near the end of its work, and the remaining 5% upon delivery or within 30 days of shipment. The contract did not specify a date for delivery: under the heading “DELIVERY,” the contract states, “Lead time is to be determined upon receipt of signed order.” Moreover, the contract specifies that “with respect to the Delivery Date, time will not be deemed to be of the

4 No. 2023AP2428

essence.” After Buddy’s accepted Viking’s bid, Viking provided a project timeline indicating a closeout date of October 18, 2017. Buddy’s paid half of the purchase price, $129,725.00, in June 2017.

¶9 The contract also contained a set of terms and conditions set forth in 13 numbered paragraphs over 2 pages. The numbered paragraphs are separated by double spaces. The text within each numbered paragraph is single-spaced and small, but legible.

¶10 Paragraph 2(b), entitled “Custom Equipment and Change Orders,” addresses the parties’ obligations if the product ordered is custom or unique. It states in part:

If the Equipment is unique in design or function according to Buyer’s specifications …, failure of [Viking] to effect Delivery of the Equipment in good faith by the Delivery Date will not be a breach of the Contract by [Viking] and will not excuse [Buddy’s] performance thereunder. Instead, [Buddy’s] and [Viking] will cooperate as necessary to achieve [Viking]’s performance under the Contract.

¶11 Paragraph 6, which begins with the bolded word “Warranty,” appears at the bottom of the first page and continues onto the second page.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deminsky v. Arlington Plastics MacHinery
2003 WI 15 (Wisconsin Supreme Court, 2003)
Phillips Petroleum Co. v. Bucyrus-Erie Co.
388 N.W.2d 584 (Wisconsin Supreme Court, 1986)
Huml v. Vlazny
2006 WI 87 (Wisconsin Supreme Court, 2006)
Kaloti Enterprises, Inc. v. Kellogg Sales Co.
2005 WI 111 (Wisconsin Supreme Court, 2005)
Solowicz v. Forward Geneva National, LLC
2010 WI 20 (Wisconsin Supreme Court, 2010)
Aul v. Golden Rule Insurance
2007 WI App 165 (Court of Appeals of Wisconsin, 2007)
Murray v. Holiday Rambler, Inc.
265 N.W.2d 513 (Wisconsin Supreme Court, 1978)
Gorton v. Hostak, Henzl & Bichler, S.C.
577 N.W.2d 617 (Wisconsin Supreme Court, 1998)
Seitzinger v. Community Health Network
2004 WI 28 (Wisconsin Supreme Court, 2004)
Trinkle v. Schumacher Co.
301 N.W.2d 255 (Court of Appeals of Wisconsin, 1980)
Kearney & Trecker Corp. v. Master Engraving Co.
527 A.2d 429 (Supreme Court of New Jersey, 1987)
Lefebvre Intergraphics, Inc. v. Sanden MacHine Ltd.
946 F. Supp. 1358 (N.D. Illinois, 1996)
Wisconsin Auto Title Loans, Inc. v. Jones
2006 WI 53 (Wisconsin Supreme Court, 2006)
W. R. Weaver Co. v. Burroughs Corp.
580 S.W.2d 76 (Court of Appeals of Texas, 1979)
Dry Dock, LLC v. Godfrey Conveyor Co., Inc.
717 F. Supp. 2d 825 (W.D. Wisconsin, 2010)
Southern Financial Group, LLC v. McFarland State Bank
763 F.3d 735 (Seventh Circuit, 2014)
Estate of Stanley G. Miller v. Diane Storey
2017 WI 99 (Wisconsin Supreme Court, 2017)
Laughland v. Beckett
2015 WI App 70 (Court of Appeals of Wisconsin, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Buddy's Plant Plus Corporation v. Viking Masek Global Packaging Technologies, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buddys-plant-plus-corporation-v-viking-masek-global-packaging-wisctapp-2025.