Phillips Petroleum Co. v. Bucyrus-Erie Co.

373 N.W.2d 65, 125 Wis. 2d 418, 41 U.C.C. Rep. Serv. (West) 1192, 1985 Wisc. App. LEXIS 3599
CourtWisconsin Supreme Court
DecidedJuly 15, 1985
Docket84-152
StatusPublished
Cited by2 cases

This text of 373 N.W.2d 65 (Phillips Petroleum Co. v. Bucyrus-Erie Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips Petroleum Co. v. Bucyrus-Erie Co., 373 N.W.2d 65, 125 Wis. 2d 418, 41 U.C.C. Rep. Serv. (West) 1192, 1985 Wisc. App. LEXIS 3599 (Wis. 1985).

Opinion

MOSER, J.

Bueyrus-Erie Company (Bucyrus) appeals from a judgment awarding $1,680,646 in compensatory damages to Phillips Petroleum Company (Phillips), for breach of contract and negligence. Phillips cross-appeals arguing that the damages are inadequate. Bucy-rus sold a number of marine cranes to Phillips for use on Phillips’ oil drilling platforms in the Norwegian sector of the North Sea. On February 28, 1974, Phillips was using a crane to unload supplies from a ship in choppy waters. The crane broke off at the base and fell into the sea, but was later retrieved. Phillips alleged that on this crane and other cranes, Bucyrus had provided pedestal adapters made of inadequate steel. A pedestal adapter is that part of a crane’s base which connects it to the pedestal of the oil drilling platform. Phillips sought to recover the expense of replacing the pedestal adapters on all the cranes sold to it by Bucyrus plus incidental damages for such things as labor and helicopter maintenance. The jury found that Bucyrus breached the contract by failing to make the adapters of a specific grade of steel; that Bucyrus breached the contract’s express warranty of merchantability; and that Bucyrus was negligent in the design, manufacture and fabrication of the pedestal adapters. The jury also found that Bucyrus did not breach the implied warranties of merchantability or of fitness for a particular purpose and that the pedestal adapters were not unreasonably dangerous. 1

On appeal, Bucyrus argues that the trial court erred in holding that certain provisions of Bucyrus’ offer, which disclaimed warranties, limited its liability and allowed *422 for the substitution of materials, were not a part of the contract and were unenforceable. Bucyrus also argues that the trial court erred in denying its motion to prohibit Phillips’ damages expert from testifying. We hold that the trial court erred in interpreting the contract between Bucyrus and Phillips; that the disclaimer clause in Bucyrus’ offer was part of the contract; that the remedy therein did not fail of its essential purpose; that the disclaimer clause is enforceable; and that, therefore, Phillips’ damages are limited to the replacement value of the crane and the pedestal adapters as specified in the disclaimer.

We reverse the judgment and remand for a new trial on all issues and further require that if the fact finder is required to find the amount of damages, such finding must be limited to the cost of replacement, as required by the contract. We do this because the trial court, when the terms of a contract are at issue, must determine those terms before presenting any factual issues to the fact finder. We also reject Phillips’ argument on cross-appeal that the $1,680,646 compensatory damage award was inadequate.

Phillips began negotiating with Bucyrus in the early 1970’s to purchase the marine cranes. Bucyrus submitted proposals to Phillips dated March 18 and April 7, 1971. The proposals contained detailed descriptions of the crane equipment, price terms, delivery schedules and other terms. Also included were certain “conditions of proposal” that limited Bucyrus’ warranties, liability and damages. 2 The conditions provided in part as follows:

*423 Manufacturer warrants the machinery, and all spares, replacements, tools, and auxiliary equipment, now or hereafter furnished by it therefor, to be built in a workmanlike manner of sound high-grade material, and, under normal use and proper attention, to operate properly. . . . Manufacturer is to have the option of replacing F.O.B. works any element proved to be defective or of remedying any proved defect, but Manufacturer’s liability in any event shall not exceed the replace *424 ment value of the defective element F.O.B. works. . . . The fore-going [sic] warranty is in lieu of all tort liability and all other warranties or representations or rights of rejection, express or implied, by law or by contract.

In addition, Bucyrus’ proposals specified that: “The right is reserved to make changes in specifications or design which, in the opinion of Manufacturer, are an improvement or are necessary because of the unavailability of materials.” Phillips sent several purchase orders to Bucyrus, some of which were stamped with the following notation: “This order expressly limits acceptance to the terms stated herein. Purchaser objects to any additional or different terms of the seller.” Upon receiving the purchase orders, Bucyrus began manufacturing the cranes.

The final proposal said that Bucyrus would submit specifications and drawings of the pedestal adapter or “turret” to Phillips. There was some discussion between the parties on the type of steel to be used in making the adapters. Phillips ultimately asked that Bucyrus use one of three types of a tougher steel than suggested by Bucyrus to fabricate the pedestal adapters. Bucyrus chose one of the steel types, ASTM-A516 Grade 70 steel, to be used for the adapters on Phillips’ cranes. Since A516 steel could not be obtained in time for Bucyrus to meet Phillips’ delivery schedules, Bucyrus substituted A572 Grade 50 steel in fabricating the pedestal adapters. Bucyrus’ engineers approved the substitution.

Determining the terms of a contract is a matter of law. In matters of law, this court need not defer to the trial court’s judgment. 3

Both Bucyrus and Phillips agree that sec. 402.207, Stats., dealing with the inclusion of additional or differ *425 ent terms to a contract, controls their transaction. Section 402.207 reads as follows:

Additional terms in acceptance or confirmation. (1) A definite and seasonable expression of acceptance or a written confirmation which is sent within a reasonable time operates as an acceptance even though it states terms additional to or different from those offered or agreed upon, unless acceptance is expressly made conditional on assent to the additional or different terms.
(2) The additional terms are to be construed as proposals for addition to the contract. Between merchants such terms become part of the contract unless:
(a) The offer expressly limits acceptance to the terms of the offer;
(b) They materially alter it; or
(c) Notification of objection to them has already been given or is given within a reasonable time after notice of them is received.
(3) Conduct by both parties which recognizes the existence of a contract is sufficient to establish a contract for sale although the writings of the parties do not otherwise establish a contract. In such case the terms of the particular contract consist of those terms on which the writings of the parties agree, together with any supplementary terms incorporated under any other provisions of chs. 401 to 409.

Section 402.207 alters the common-law mirror-image rule whereby the terms of an acceptance must mirror those of the offer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westinghouse Electric Corp. v. Nielsons, Inc.
647 F. Supp. 896 (D. Colorado, 1986)
Phillips Petroleum Co. v. Bucyrus-Erie Co.
388 N.W.2d 584 (Wisconsin Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
373 N.W.2d 65, 125 Wis. 2d 418, 41 U.C.C. Rep. Serv. (West) 1192, 1985 Wisc. App. LEXIS 3599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-petroleum-co-v-bucyrus-erie-co-wis-1985.