Phillips Construction Co. v. City of New York
This text of 463 N.E.2d 585 (Phillips Construction Co. v. City of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
[950]*950OPINION OF THE COURT
Memorandum.
The order of the Appellate Division should be reversed, with costs, plaintiff’s motion to strike the tenth defense (Statute of Limitations), denied, and defendant’s motion to dismiss the action as time barred under the six-year Statute of Limitations (CPLR 213, subd 2), granted.
This action arises out of the construction of an ice skating rink at Clove Lake Park, Staten Island, New York. The provisions of article 531 of the construction contract prescribed a supplemental period of limitation for assertions of claims against the city. Nothing in the record suggests that the provisions of that article were intended by the contracting parties wholly to supplant the Statute of Limitations prescribed in the CPLR, if indeed the parties were free to do so (Kassner & Co. v City of New York, 46 NY2d 544). Accordingly, the six-year period of limitations prescribed in CPLR 213 (subd 2) is applicable.
In arguing as to the date of accrual of the causes of action alleged in the complaint plaintiff points to certain language lifted out of article 42 of the contract (entitled “Final Payment”): “[T]he certification of the Engineer [on the final payment voucher] and the approval of the Commissioner thereof, shall be a condition precedent to the right of the Contractor to receive any money thereunder.” (Emphasis is that of plaintiff contractor.) This provision is explicitly made applicable, however, only to the right to receive payment under the final voucher; it has no relation to the institution of actions for breach of obligations other than the obligation to make payment under that voucher. The present action for damages for the cost of additional work occasioned by but not included in change orders, for extra [951]*951work performed, and for delay damages is grounded in allegations of liability of the city arising out of the contract but apart from its obligations under the payment provisions of the contract. It is not based on any asserted nonperformance of payment mandated by the final voucher or on any insufficiency in the amount of the final voucher which was not certified until September, 1979, some 20 months after the present action was commenced.
The Statute of Limitations prescribed in CPLR 213 (subd 2) began to run on completion of the actual physical work even though incidental matters relating to the project remained open (State of New York v Lundin, 60 NY2d 987). It was alleged in the city’s moving papers, with documentation, that the project was substantially completed on September 28, 1971. Supreme Court agreed. In some instances the counter proof tendered by a plaintiff might call for an immediate trial of a factual dispute as to when the cause of action alleged in the complaint accrued as prerequisite to a determination whether it was time barred (CPLR 3211, subd [c]). In the present case, however, plaintiff’s submission is insufficient to raise any material question of fact on the issue. Examination of the punch list work directed in the letter of the acting engineer dated October 13, 1971 discloses only incidental items and no proof that actual construction had not already been completed, and the affidavit of the contractor’s president relating to the subsequent preparation of the final payment voucher, cites only work on a single door frame. Accordingly, the present action, commenced on January 17,1978, was time barred.2
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
463 N.E.2d 585, 61 N.Y.2d 949, 475 N.Y.S.2d 244, 1984 N.Y. LEXIS 4185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-construction-co-v-city-of-new-york-ny-1984.