Mendelsohn v. City of New York (19th Precinct)

89 A.D.3d 569, 934 N.Y.2d 3
CourtAppellate Division of the Supreme Court of the State of New York
DecidedNovember 17, 2011
StatusPublished
Cited by8 cases

This text of 89 A.D.3d 569 (Mendelsohn v. City of New York (19th Precinct)) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mendelsohn v. City of New York (19th Precinct), 89 A.D.3d 569, 934 N.Y.2d 3 (N.Y. Ct. App. 2011).

Opinion

The court correctly determined that, pursuant to CPLR 213 (2), this action for breach of a construction contract had to be commenced within six years of substantial completion of the work and was time-barred (see Phillips Constr. Co. v City of New York, 61 NY2d 949, 951 [1984]; 645 First Ave. Manhattan Co. v Silhouette Dry wall Sys., 212 AD2d 394 [1995]). The City submitted a letter dated May 21, 1992 showing that the work was substantially complete on April 9, 1992, more than six years before plaintiff commenced this action.

Plaintiff failed to raise an issue of fact as to when the work was substantially complete. To the contrary, plaintiffs own document, a contractor’s certificate seeking partial payment dated May 7, 1992, indicates that 98% of the work was complete as of that date. The June 29, 1992 and August 5, 1992 memoranda, and the October 1, 1993 and November 22, 1993 letters, merely show that work incidental to the electrical work on the building, namely a fire alarm system and items on a punch list, was incomplete (see Phillips Constr., 61 NY2d at 951).

Additionally, plaintiff’s purported claim to recover its guarantee monies pursuant to article 24 of the contract has not been considered here, as it was not raised below, either in the [570]*570pleadings or the motion papers and thus, was not preserved for appellate review.

We have considered plaintiffs remaining contentions and find them unavailing. Concur — Tom, J.E, Saxe, Moskowitz, DeGrasse and Abdus-Salaam, JJ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lantern Endowment Partners, LP v. Bluefin Servicing Ltd.
2021 NY Slip Op 07081 (Appellate Division of the Supreme Court of New York, 2021)
San Lim v. MTA Bus Co.
2021 NY Slip Op 00121 (Appellate Division of the Supreme Court of New York, 2021)
Nexbank, SSB v. Soffer
2016 NY Slip Op 7395 (Appellate Division of the Supreme Court of New York, 2016)
RAD & D'Aprile Inc. v. Arnell Construction Corp.
49 Misc. 3d 189 (New York Supreme Court, 2015)
Leitner v. 304 Associates, LLC
129 A.D.3d 415 (Appellate Division of the Supreme Court of New York, 2015)
ACE Securities Corp. v. DB Structured Products, Inc.
40 Misc. 3d 562 (New York Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
89 A.D.3d 569, 934 N.Y.2d 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mendelsohn-v-city-of-new-york-19th-precinct-nyappdiv-2011.