Pham Construction & Co., L.L.C. v. Tran

2024 Ohio 634, 236 N.E.3d 849
Ohio Court of Appeals·Decided February 20, 2024·No. 23 CAE 02 0018·Published·Cited by 8 cases

Opinion

COURT OF APPEALS

DELAWARE COUNTY, OHIO

FIFTH APPELLATE DISTRICT

PHAM CONSTRUCTION AND : JUDGES: COMPANY, LLC :

:

: Hon. W. Scott Gwin, P.J.

Plaintiff-Appellant : Hon. Patricia A. Delaney, J.

: Hon. Andrew J. King, J.

-vs- :

: Case No. 23 CAE 02 0018 :

HUY D. TRAN, ET AL. :

:

:

Defendants-Appellees : OPINION

CHARACTER OF PROCEEDING: Appeal from the Delaware County Court of Common Pleas, 21 CV H 06 0305

JUDGMENT: AFFIRMED

DATE OF JUDGMENT ENTRY: February 20, 2024

APPEARANCES:

For Plaintiff-Appellant: For Defendants-Appellees:

MICHAEL J. ANTHONY MICHAEL T. COX VINCENT P. ZUCCARO 4930 Reed Road, Suite 220 978 S. Front St. Columbus, OH 43220 Columbus, OH 43206

Delaney, J.

{¶1} Plaintiff-Appellant Pham Construction and Company, LLC appeals the December 14, 2022 and January 23, 2023 judgment entries of the Delaware County Court of Common Pleas.

FACTS AND PROCEDURAL HISTORY

{¶2} Plaintiff-Appellant Pham Construction and Company, LLC (“PCC”) is a limited liability company that specializes in interior buildouts for commercial clients. Defendants-Appellees Huy D. Tran and Linh T. Quach are the co-owners of a business known as Perfect 10 Nail Salon. Tran and Quach owned and operated Perfect 10 as a general partnership (hereinafter “Perfect 10”). PCC and Perfect 10 entered into a contract on April 18, 2018 for an expansion buildout of a leased commercial property located in Delaware, Ohio.

Complaint, Counterclaim, and Pre-Trial Proceedings

{¶3} On June 28, 2021, PCC filed a complaint with the Delaware County Court of Common Pleas naming Tran and Quach dba Perfect 10 as defendants. The complaint alleged four causes of action: breach of contract, promissory estoppel, civil theft, and fraud.1 While PCC acknowledged that Perfect 10 had made a first contracted payment of $20,000 on August 29, 2018 and a second contracted payment of $38,722 on October 25, 2018, PCC claimed Perfect 10 failed to make a third contracted payment of $30,000. PCC alleged that Perfect 10 breached the 2018 Contract when it refused to pay the

1 On July 19, 2022, the trial court granted summary judgment in favor of Perfect 10 on PCC’s claims for promissory estoppel and fraud. On October 10, 2022, the trial court granted a directed verdict in favor of Perfect 10 on PCC’s claim for civil damages for the criminal act of passing bad checks. PCC does not raise those judgments in its appeal. We will focus our recitation of the facts on the remaining causes of action at issue in the appeal.

remaining contractual balance of $39,858 and $14,470 for additional work not covered by the 2018 Contract.

{¶4} Perfect 10 filed a motion to dismiss PCC’s claims for civil theft and fraud, which the trial court denied on September 17, 2022. It also filed its answer to the complaint and raised counterclaims for breach of contract, conversion, and civil theft based on the authorized use of property and theft by deception pursuant to R.C. 2307.60 and 2307.61. The breach of contract counterclaim alleged that PCC had breached the 2018 Contract when it failed to complete the improvements to the property within the agreement’s five- month deadline. Perfect 10 also alleged it had made a $30,000 payment and PCC refused to credit that payment to Perfect 10’s balance under the 2018 Contract; thereby, Perfect 10 raised a counterclaim for civil damages for the criminal act of theft by deception.

{¶5} Perfect 10 filed a motion for summary judgment seeking judgment as a matter of law on all of PCC’s causes of action. The trial court granted summary judgment in favor of Perfect 10 on PCC’s claims for promissory estoppel and fraud. It denied summary judgment on PCC’s claims for breach of contract and civil theft.

Jury Trial

{¶6} The matter proceeded to a jury trial on October 4, 2022. Prior to sending the matter to the jury, the trial court granted directed verdicts on PCC’s claim for civil damages for the criminal act of passing bad checks and Perfect 10’s counterclaims for conversion and civil damages for the criminal act of unauthorized use of property. The only claims for the jury to decide were PCC’s claim for breach of contract and Perfect 10’s counterclaims for breach of contract and civil damages for the criminal act of theft by deception. The following facts, relevant to this appeal, were adduced at trial.

{¶7} On April 18, 2018, Calvin Pham and Thanh Tam Nguyen (partners in Pham Construction) entered into a contract with Huy Duc Tran for the buildout extension of the Perfect 10 nail salon in the amount of $98,580. Pham, Nguyen, and Tran signed the 2018 Contract at the Chase Bank before a notary. At the time of the signing, PCC believed that Perfect 10 was in the process of obtaining a loan from Chase Bank to pay for the construction. Perfect 10 denied that it told PCC it had applied for a loan with Chase Bank; rather, it had inquired into a loan and found the terms unacceptable. Article 1 of the 2018 Contract stated the work was divided into three phases, with the work to be completed in five months. Article 4 of the 2018 Contract outlined the payments:

* * * the Owner shall make progress payments to the Contractor as follows:

1st Payment (50% of $98,580): OR must make this payment to PCC to start the project.

2nd Payment (30% of $98,580): OR must make this payment to PCC after the completion of PHASE 1 construction work.

3rd Payment (10% of $98,580): OR must make this payment to PCC after the completion of PHASE 2 construction work.

4th Payment (Final Payment 10% of $98,580): OR must make this payment to PCC within 7 days of receiving Certify of Opening from CITY OF DELAWARE.

Article 15 of the 2018 Contract contained a provision if the Owner failed to make a payment for a period of 7 days through no fault of the Contractor, the Contractor could, upon 7 days written notice to the Owner, terminate the contract. PCC admitted that during its dealings with Perfect 10, it did not always follow the terms of the 2018 Contract.

{¶8} On July 1, 2018, Tran gave PCC a check for $49,290. Tran told PCC to hold the check and not cash it because he did not have the funds to cover the check. He never told PCC to return the check to Perfect 10. PCC started the construction project a few days later. On July 2, 2018, Tran testified that he gave Nguyen $30,000 as payment towards the project ($20,000 in cash from Tran’s mother and a $10,000 money order from Tran’s brother). Tran testified that he forgot to ask Nguyen for a receipt for the $30,000 payment. Tran’s mother and brother testified at the trial that they provided Tran with the funds, and he had since paid them back.

{¶9} Prior to beginning the project, PCC informed Perfect 10 that it could work with Perfect 10’s commercial landlord to receive funds towards the project as a Tenant Allowance. Perfect 10’s landlord offered $41,000 towards the project for a HVAC system and demising wall, and 150 days of free rent.

{¶10} PCC completed Phase 1 of the project in August 2018. On August 29, 2018, the parties agree that Tran gave PCC $20,000 as payment towards the project (a $15,000 check and $5000 in cash). PCC provided Tran with a receipt for the $20,000 payment. Tran testified that on August 29, 2018, he also asked PCC for a receipt for the $30,000 payment made by him in July 2018. He stated that PCC provided him with a receipt for the $30,000 payment but Pham testified the August 29, 2018 receipt showing a $30,000 payment was a forgery. Pham testified that he did not keep for his own records the copies of the receipts he provided to his customers.

Free access — add to your briefcase to read the full text and ask questions with AI

Pham Construction & Co., L.L.C. v. Tran, 2024 Ohio 634, 236 N.E.3d 849 (Ohio Ct. App. 2024).

2024 Ohio 634 (Pham Construction & Co., L.L.C. v. Tran) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related