PHA-JMR JV

CourtArmed Services Board of Contract Appeals
DecidedAugust 1, 2014
DocketASBCA No. 59032
StatusPublished

This text of PHA-JMR JV (PHA-JMR JV) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PHA-JMR JV, (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) PHA-JMR JV ) ASBCA No. 59032 ) Under Contract No. FA4686- l O-C-0018 )

APPEARANCES FOR THE APPELLANT: Martin R. Salzman, Esq. Kevin S. Dale, Esq. David M. Gersh, Esq. Hendrick Phillips Salzman & Flatt, P.C. Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Col Robert J. Preston II, USAF Acting Air Force Chief Trial Attorney Christopher M. McNulty, Esq. Capt Eric J. Singley, USAF Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE JAMES ON JURISDICTION

On 25 February 2014, the Board, sua sponte, asked the parties to briefthe question whether the 30 April 2013 Contract Disputes Act (CDA) certification signed by Scott Manning, treasurer of subcontractor Progressive Roofing as "Attorney-in-fact for JMR," one of the PHA-JMRjoint venturers, by a limited power of attorney that expired on 31 January 2013, was a valid CDA certification. Both parties submitted briefs. At the parties' request, the Board also heard oral argument. Upon review of the parties' briefs, attached exhibits and the transcript of the oral argument, we refocus the question as follows: whether either appellant's 25 January 2013 claim or 30 April 2013 claim is within the CDA jurisdiction of this Board.

STATEMENT OF FACTS (SOF)

I. On 11 August 2010, the U.S. Air Force 9th Contracting Squadron entered into Contract No. FA4686-10-C-0018 (the contract) with PHA-JMR JV to construct roof sections A and B for Building No. 1086 at Beale Air Force Base, California (R4, tab 1 at 1-3).

2. For PHA-JMR JV, "PHILIP L. HA WK.INS, MANAGING PARTNER" signed the contract and its bilateral Modification Nos. P00002, P00003 and P00004 (R4, tabs 1, 3-5). 3. "JMR" subcontracted with Progressive Services, Inc. (Progressive) for a portion of the contract roofing work, including demolition (Salzman aff., ex. 1 at 1). As our following Statement of Facts demonstrate, there are many confusing aspects of this appeal. We place "JMR" in quotes for the following reasons, and note that neither the Progressive subcontract nor the Joint Venture agreement is in evidence. The "JMR" citation is to appellant's undated initial "claim" letter (see SOF if 8). The "claim" is on the subcontractor's letterhead and is signed by the subcontractor's treasurer. While it is denominated as PHA-JMR JV's claim, the body of the letter stated: "Please accept the letter as PHA-JMR's (' JMR') certified claim submission and request for a final Contracting Officer's decision on behalf of its subcontractor, Progressive Services, Inc. d/b/a Progressive Roofing." It is unclear in the record what appellant intended by its parenthetical ("JMR") in this sentence. In various documents sometimes PHA-JMR JV is used to refer to the contractor and appellant in this appeal, and sometimes JMR is used. Of course, JMR is only one of the JV partners and not the contractor itself.

4. On 1 November 2010, during the initial roof demolition, Progressive's "Roof Warrior" cutting device struck several metal plates atop the concrete deck underlying the existing roofing. Progressive notified the government of this discovery on the next day. (Salzman aff., ex. 1 at 2, exs. IA, lB)

5. PHA-JMR JV's Request for Information 003 (RFI #3) dated 10 November 2010 was authored by John Morrill of JMR, who provided further information to the government regarding the alleged differing site condition (Salzman aff., ex. lE).

6. On 3 June 2011 Progressive sent JMR a $57,210.00 change request consisting of$51,080 for labor and $6,130 for "Overhead & Profit@ 12%" relating to the metal plates (supp. R4, tab 10 at 4of9).

7. The 16 June 2011 letter of JMR's John Morrill to contracting officer (CO) Pank, on PHA-JMR JV letterhead, forwarded Progressive's 3 June $57,210.00 request, to which was added "MIU $8,582.00" ("Profit overhead=@ 15%") and "Bond $1,144.00" for a total of$66,936.00 (supp. R4, tab 10 at 2-3 of9).

8. The undated letter to CO Pank on the letterhead of Progressive Roofing, signed by Scott Manning, submitted a $240,767 equitable adjustment for "Unforeseen Site Conditions," for the metal plates, and requested a CO's final decision. The $240,767 adjustment included the $66,936 requested by Progressive and JMR on 16 June 2011 and added "extended overhead in the sum of at least $173,831.00 for which }MR/Progressive is entitled to be reimbursed" (emphasis added). (Salzman aff., ex. 1 at 1-2) We find that PHA-JMR JV or JMR added "$8,582.00" (for profit and overhead at 15%), "Bond $1,144.00" and "$173,831.00" in extended overhead costs, to Progressive's $57,210 claim that included $6, 13 0 for "Overhead & Profit @ 12 %. "

2 9. Accompanying Progressive's letter were two documents each entitled "CONTRACTOR'S CERTIFICATION." The first was on plain bond, whose text complied with FAR 33.207(c) and was signed by "Scott Manning, Attorney-in-fact for JMR." The second was on Progressive letterhead, signed by "Scott Manning, Treasurer," its text was the same as the other certification. (Salzman aff., ex. 1 at 1, 5-7) Mr. Salzman mailed the foregoing "written certified claim ... to the [CO] on behalf of Appellant on or about January 25, 2013" (Salzman aff. at 1).

10. On 13 March 2013 CO Sandra Siiberg rejected the claim because it did not appear to originate from the prime contractor, PHA-JMR JV, but was presented on a subcontractor's letterhead, and the claim certifier "is variously represented as either the apparent claim author ... designated attorney for a partial component (JMR) of the prime contractor PHA-JMR JV (with no firm letterhead representation), or, a principal (treasurer) of the ... subcontractor" (Salzman aff., ex. 2).

11. The 30 April 2013 letter of "PHA-JMR JV ('JMR')" to CO Siiberg repeated the statements and included the "CONTRACTOR'S CERTIFICATION" signed by "Scott Manning, Attorney-in-fact for JMR" in its January 2013 claim letter, and appended the following:

LIMITED POWER OF ATTORNEY

KNOW ALL MEN BY THESE PRESENTS:

JMR Construction Corp .... pursuant to a separate Joint Prosecution agreement, JMR is. pursuing the claims of Progressive Services, Inc .... ("Progressive") against the Project Owner pertaining to a differing site condition alleged by Progressive pertaining to roofing removal and replacement in connection with ... the Air Force Contract for Repair Roof, Flightline Support, B 1086 at Beale AFB, California.... In connection with the pursuit of the said claims, the Contract Disputes Act requires a Contractor Certification that the claims are made in good faith, that the supporting data is accurate and complete to the best of the contractor's knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable. JMR does not have sufficient or personal knowledge, particularly as to Progressive' s supporting data, to execute such a certification.

3 Scott Manning, Treasurer for Progressive, does possess such knowledge.

Accordingly, the undersigned hereby names, nominates and appoints Scott Manning .. .in JMR's name, place and stead, to sign its name and execute on its behalf the Contractor's Certification. The undersigned does hereby consent to, ratify and confirm everything which the said attorney-in-fact, pursuant to the powers herein contained, shall legally do by virtue of these presents.

This Limited Power of Attorney shall not be affected by any disability and shall expire January 31, 2013.

IN WITNESS WHEREOF, the undersigned have hereunto executed this document on this 21st day of December, 2012. JMR Construction Corp. JoAnne [illegible] By: Ron [illegible] Witness Its: Vice President

(Gov't resp., attach. 1 at 8 of 8)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
PHA-JMR JV, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pha-jmr-jv-asbca-2014.