Peterson v. Dayton Metro. Housing Auth., Unpublished Decision (7-21-2000)

CourtOhio Court of Appeals
DecidedJuly 21, 2000
DocketC.A. Case No. 17306, T.C. Case No. 96-4149.
StatusUnpublished

This text of Peterson v. Dayton Metro. Housing Auth., Unpublished Decision (7-21-2000) (Peterson v. Dayton Metro. Housing Auth., Unpublished Decision (7-21-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peterson v. Dayton Metro. Housing Auth., Unpublished Decision (7-21-2000), (Ohio Ct. App. 2000).

Opinion

OPINION
This case arises from a contract dispute between Plaintiff-Appellant, Jeffrey B. Peterson Associates ("Peterson"), and Defendant-Appellee, Dayton Metropolitan Housing Authority ("DMHA"). In July, 1995, DMHA asked for bids to replace the roofs, fascia, gutters, and down spouts on eight residential units located at Channingway Court, in Huber Heights, Ohio. The bid request resulted from a violation notice issued to DMHA by the City of Huber Heights. Unfortunately, the original bid amounts exceeded the limit for small procurement contracts, and the project had to be re-advertised as a large procurement contract. DMHA then received another round of bids in September, 1995.

Peterson was awarded the job on the second round, and entered into a contract with DMHA on September 19, 1995. According to the contract, work was to begin on October 16, 1995, and was to be completed within ninety days. The total contract amount was $57,148. After the award, Peterson began work, but a number of problems caused delay. Ultimately, the work was not finished on time, and DMHA terminated the contract for default on June 17, 1996.

Subsequently, Peterson filed suit against DMHA for breach and wrongful termination of the contract. In particular, Peterson requested damages for overhead expenses, lost profits, indemnification costs due to Peterson's surety, money due for work performed on the project, prejudgment interest, attorney fees, loss of productivity, and loss of bonding capacity. DMHA filed an answer, claiming that default was proper because Peterson had failed to complete the contract.

The case was referred to a magistrate for findings of fact and conclusions of law on all issues of law and fact. After hearing evidence, the magistrate issued a decision on November 7, 1997, finding that DMHA had breached the contract. However, the magistrate went on to conclude that Peterson's damages were limited by Section 34(b) of the contract, which applied when contracts were terminated for convenience. Accordingly, the magistrate recommended that Peterson should be awarded damages in the amount of $26,292.66, plus statutory interest. This amount included the last pay application of $13,868.80, $1,783.45 in stored materials, home office overhead of $5,274.41, termination expenses of $1225, and retainage of $4,187.1 The magistrate rejected Peterson's remaining claims for damages, because Section 34(b) did not allow recovery of damages for loss of bonding ability.

Additionally, the magistrate found that Peterson was entitled to "reasonable attorneys fees expended to litigate this matter." However, the magistrate did not recommend awarding any attorney fees, because no evidence had been presented as to their reasonableness.

On June 11, 1998, the trial court affirmed the magistrate's decision, except for the issue of attorney fees. This issue was recommitted for the magistrate "to determine adequate fees." The court also addressed the issue of prejudgment interest, which had been raised in Peterson's objections. In this regard, the court found that Peterson was made whole by the damages award and was not entitled to prejudgment interest.

Although an immediate appeal was taken from the trial court's decision, the parties later asked us to stay the appeal and remand the case for a decision on attorney fees. We agreed to do so, and the magistrate then held an attorney fee hearing on October 19, 1998. However, this time the magistrate found that Section 34(b) limited Peterson's attorney fees to those incurred before litigation. Accordingly, the magistrate awarded attorney's fees of only $3,070.50. The trial court then adopted this decision in full on June 4, 1999.

Peterson now appeals both the June 11, 1998 and June 4, 1999 decisions of the trial court, and raises the following assignments of error:

I. The trial court erred when it did not find that the Contracting Officer's termination of the contract was arbitrary, capricious and an abuse of discretion.

II. The trial court erred when it interpreted the contract as limiting Appellant's damages.

III. The trial court erred when it failed to award Peterson all of its attorneys fees and expenses expended to litigate this matter.

IV. The trial court erred when it failed to award Appellant prejudgment interest on all damages recovered.

After reviewing the record and assignments of error, we find the first and third assignments of error without merit. The second assignment of error has merit in part, and the fourth assignment of error also is meritorious. Accordingly, the trial court decision will be affirmed in part, reversed in part, and remanded for consideration of two issues. An explanation of our opinion follows.

I
As we mentioned, Peterson alleges in the first assignment of error that the trial court erred in not finding the contract termination to be arbitrary, capricious, and an abuse of discretion. However, our review of the record indicates that neither the magistrate nor the trial court ever specifically considered this issue.

In this regard, we note that Peterson filed a motion for partial summary judgment on April 30, 1997, asking for summary judgment on liability only. In the motion, Peterson argued that termination for default was wrongful because DMHA could not reasonably justify the termination. In particular, Peterson focused on the fact that the contracting officer (DMHA Executive Director, Roland Turpin) abused his discretion by failing to make any investigation. Peterson additionally relied on the fact that DMHA failed to consider whether project delays were the result of excusable delay.

DMHA responded by noting that the Executive Director properly relied on the judgment of others in the administrative hierarchy. Further, DMHA contended that Peterson's lack of diligence and poor workmanship justified termination for default.

Subsequently, the magistrate denied the motion for summary judgment. In the decision, the magistrate focused solely on Section 32(a) and (b) of the contract, which allowed DMHA to terminate the contract if the work was not timely performed. Regarding this issue, the magistrate noted that there was no dispute about untimeliness, i.e, the work was not finished by the contract deadline. However, the magistrate then commented that DMHA did not have the right under the contract to terminate for default: 1) if the delay arose from unforeseeable causes beyond the control and without the fault of the contractor; and 2) the contractor timely notified DMHA of the causes of the delay. After receiving timely notice, DMHA was contractually required to ascertain the facts and extent of delay, grant an extension if warranted, and issue a written decision. The magistrate found genuine issues of fact concerning the causes for the delay and whether both parties met the requirements of the contract for the termination process. However, the magistrate did not comment on abuse of discretion, arbitrariness, etc.

At trial, both sides made opening statements, but neither side mentioned abuse of discretion in connection with damages. Instead, Peterson focused on whether the delay was excusable and whether DMHA was justified in terminating for default (without specifically mentioning abuse of discretion). By contrast, DMHA argued that Peterson was partly responsible for the delay, that Peterson failed to set up a reasonable completion date for the contract, and that DMHA had no choice but to terminate the contract.

After the hearing, both sides filed post-trial briefs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acme Process Equipment Co. v. United States
347 F.2d 538 (First Circuit, 1965)
Krygoski Construction Company, Inc. v. United States
94 F.3d 1537 (Federal Circuit, 1996)
T & M Distributors, Inc. v. United States
185 F.3d 1279 (Federal Circuit, 1999)
District of Columbia v. Organization for Environmental Growth, Inc.
700 A.2d 185 (District of Columbia Court of Appeals, 1997)
Dayton Monetary Associates v. Becker
710 N.E.2d 1151 (Ohio Court of Appeals, 1998)
Matrka v. Delta Airlines, Inc.
688 N.E.2d 1130 (Ohio Court of Appeals, 1997)
Fada v. Information Systems & Networks Corp.
649 N.E.2d 904 (Ohio Court of Appeals, 1994)
Shaffer v. Shaffer
671 N.E.2d 1317 (Ohio Court of Appeals, 1996)
Manor Care Nursing & Rehabilitation Center v. Thomas
704 N.E.2d 593 (Ohio Court of Appeals, 1997)
Century 21 American Landmark, Inc. v. McIntyre
427 N.E.2d 534 (Ohio Court of Appeals, 1980)
Collins v. Click Camera & Video, Inc.
621 N.E.2d 1294 (Ohio Court of Appeals, 1993)
D'Agastino v. Uniroyal-Goodrich Tire Co.
717 N.E.2d 781 (Ohio Court of Appeals, 1998)
Domestic Linen Supply & Laundry Co. v. Kenwood Dealer Group, Inc.
672 N.E.2d 184 (Ohio Court of Appeals, 1996)
Barrett v. Waco International, Inc.
702 N.E.2d 216 (Ohio Court of Appeals, 1997)
Watkins v. Brown
646 N.E.2d 485 (Ohio Court of Appeals, 1994)
Textron Financial Corp. v. Nationwide Mutual Insurance
684 N.E.2d 1261 (Ohio Court of Appeals, 1996)
State v. Scherer
671 N.E.2d 545 (Ohio Court of Appeals, 1995)
Mutual Finance Co. v. Politzer
256 N.E.2d 606 (Ohio Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
Peterson v. Dayton Metro. Housing Auth., Unpublished Decision (7-21-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/peterson-v-dayton-metro-housing-auth-unpublished-decision-7-21-2000-ohioctapp-2000.