Palmer Steel Structures v. Westech, Inc.

584 P.2d 152, 178 Mont. 347, 1978 Mont. LEXIS 575
CourtMontana Supreme Court
DecidedSeptember 13, 1978
Docket14005
StatusPublished
Cited by5 cases

This text of 584 P.2d 152 (Palmer Steel Structures v. Westech, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmer Steel Structures v. Westech, Inc., 584 P.2d 152, 178 Mont. 347, 1978 Mont. LEXIS 575 (Mo. 1978).

Opinions

MR. JUSTICE DALY

delivered the opinion of the Court.

Plaintiff Palmer Steel Structures (Palmer) appeals from orders of the District Court, Yellowstone County, setting aside and refusing to reinstate a temporary restraining order which enjoined defendant Westech, Inc. (Westech) from proceeding with arbitration. Palmer Steel Structures contracted to construct a metal airplane hanger building for Westech, Inc. Article 15 of the parties’ contract provided that:

“All claims or disputes arising out of this Contract or the breach thereof shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. * * *”

Palmer commenced construction on June 17, 1976. By Friday, September 17, 1976, approximately 90% of the construction was complete. To safeguard the structure over the weekend, Palmer’s employees installed braces and a rope anchor. The next day, September 8, 1976, a strong wind caused the structure to collapse.

Westech’s builders’ insurance paid for removal of debris, [349]*349material replacement and reconstruction of the collapsed structure to its status at the time of the loss. Palmer thereafter substantially completed the structure in accord with the basic contract.

Under the contract as modified by the parties, Palmer claimed a balance owing to it from Westech, Inc. of $48,714.17. Possession of the building was given to Westech on about January 15, 1977. Following possession Westech asserted certain claims and offsets against the balance of its account to Palmer. On February 15, 1977, under the contract arbitration clause, Westech submitted its demand for arbitration before the American Arbitration Association. The enumeration of disputes as specified by Westech in its demand for arbitration was:

“ 1. Delay in performance of contract
“2. Breach of contract, failure to perform contract on or before October 1, 1976
“3. Failure to perform the work in a good and workmanlike manner free from faults and defects as the same pertains to the sliding doors which are an integral part of the contract.”

Westech’s “CLAIM OR RELIEF SOUGHT“ was:

“1. Damages for costs, expenses and lost profits resulting from failure to perform work on or before October 1, 1976, in the amount of $150,000.00.
“2. Damages because of failure to adequately and properly correct doors on the hanger facility in the amount of $50,000.00
“3. The right to withhold the amount due under the contract to offset damages.
“4. For filing fees.
“5. For arbitration fees.
“6. To reserve the right to add other items after the initial conference.”

Palmer promptly gave notice that it did not consent to and refused submission of the matter to arbitration. On April 4, 1977, the American Arbitration Association gave notice to Palmer that unless stayed by court order before April 11, 1977, the matter [350]*350would be deemed submitted. On April 6, 1977, Palmer filed an action in District Court seeking to recover the $48,714.17 balance owing under the construction contract and also asking for an injunction against submittal of Westech’s counterclaim to arbitration.

The District Court, Cascade County, issued an order to show cause and a temporary restraining order. The case was then transferred to the District Court, Yellowstone County. The District Court in Yellowstone County on June 2, 1977, ordered that the temporary restraining order against Westech’ arbitration proceedings be set aside. Since the filing of the instant counterclaim against Palmer asserting the same claims, alleged delay in performing the contract, alleged defective and faulty construction based upon the alternate theories of breach of contract, negligence, strict liability and breaches of the warranties of fitness and merchantability.

Palmer presents two issues for review:

1. Is the arbitration provision in the parties’ contract unenforceable?

2. Is Palmer entitled to injunctive relief?

Section 13-806, R.C.M.1947, provides:

“Every stipulation or condition in an contract by which any party thereto is restricted from enforcing his rights under the contract, by the usual proceedings in the ordinary tribunals, or which limits the time within which he may thus enforce his rights, is void.”

This Court has long interpreted section 13-806, R.C.M. 1947, to mean that a contract may require future disputes as to value or quantity to be submitted to arbitration. Wortman v. Montana Central Ry. Co. (1899), 22 Mont. 266, 279, 56 P. 316; School District No. 1 v. Globe & Republic Ins. Co., (1965), 146 Mont. 208, 213, 404 P.2d 889, However, contract provisions which require parties to submit future disputes as to questions of law are void under the statute. Green v. Wolff, (1962), 140 Mont. 413, 372 P.2d 427; State ex rel. Cave Construction Co. v. District Court, (1967), 150 Mont. 18, 430 P.2d 624. Here, the contract provision provided [351]*351that “All claims or disputes arising out of this Contract or the breach thereof shall be decided by arbitration * *

The “claims or disputes” submitted by Westech may be paraphrased as: Did Palmer breach its contract by failing to complete its work by October 1, 1976? Was Palmer negligent in its workmanship and inspection of the building? Did Palmer breach its warranties of merchantability and fitness in erecting the building? All of these questions are issues of law or mixed issues of law and fact. Westech may not require Palmer to submit such questions to arbitration without its consent.

Montana has code provisions for submission of existing disputes to arbitration (Title 93, Chap. 201, Sections 93-201-1 through 93-201-10), but such submission must be voluntary, requiring consent of all parties. Apparently such consent may be revoked up to the time an arbitration award is entered in the District Court. Section 93-201-3, R.C.M. 1947. Here the parties are not proceeding under statutory authority. This is a common law agreement for arbitration, which is unenforceable, (6 C.J.S. Arbitration § 2, pp. 159, 162), when the agreement is to arbitrate all disputes that may thereafter arise. State ex rel. Cave Construction Co. v. District Court, supra. Without the consent of Palmer Steel Structures, therefore, the arbitrators have no authority to act (6 C.J.S. Arbitration § 72, pp. 286, 287) and any action taken by them without such consent is a mere nullity. In that circumstance the court may stay further proceedings in arbitration:

•“* * * So it may be proper to stay arbitration where there is no valid contract to arbitrate * .* * [or] where the contract is unenforceable * * *.” 6 C.J.S. Arbitration § 45, p. 247.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
584 P.2d 152, 178 Mont. 347, 1978 Mont. LEXIS 575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmer-steel-structures-v-westech-inc-mont-1978.