Ace Plumbing & Heating, Inc. v. Helena Flats School District 15

662 P.2d 1327, 204 Mont. 81, 1983 Mont. LEXIS 697
CourtMontana Supreme Court
DecidedMay 12, 1983
Docket82-434
StatusPublished
Cited by1 cases

This text of 662 P.2d 1327 (Ace Plumbing & Heating, Inc. v. Helena Flats School District 15) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ace Plumbing & Heating, Inc. v. Helena Flats School District 15, 662 P.2d 1327, 204 Mont. 81, 1983 Mont. LEXIS 697 (Mo. 1983).

Opinion

MR. JUSTICE SHEEHY

delivered the opinion of the Court.

This is an appeal from a judgment issued by the District Court of the Eleventh Judicial District, Flathead County, ordering in part that the third-party defendant, Simons and Associates (Simons) pay the defendant, Helena Flats School District 15 (Helena Flats) $1,806.49 for a debt incurred in the construction of a school building. We affirm the judgment of the District Court in all respects.

Helena Flats received a federal grant for expansion and remodeling of the Helena Flats elementary school. The school district contracted with Simons for architectural, planning and supervisory services. Simons provided all the contract documents and design specifications. Included within the plans and specifications and contracts for the project were requirements for a well and water system.

Defendant Stewart and Janes, was selected as the general contractor. Plaintiff Ace Plumbing & Heating, Inc. (Ace) was selected by Stewart & Janes as mechanical subcontractor. Ace subcontracted the drilling of a water well to O’Keefe drilling.

On August 25, 1978, Helena Flats and Simons entered into a supplemental agreement. This agreement provided that Simons was responsible for “insuring” completion of the project. This obligation included “insuring” that the contractors performed in accordance with the contract documents. This agreement also increased Simons’ fee.

In the summer of 1978 problems developed in the water system. Sand was being pumped into the tanks and lines rendering the water unusable for drinking purposes and *84 damaging and clogging the fixtures. The cause of the problem was disputed by the parties.

Simons claims the well was improperly drilled. He sent repeated requests to the general contractor suggesting the general contractor require the subcontractors to comply with the specifications, and provide an additional screen for the sand.

The school district claimed the problem was Simons’ faulty design. On February 13, 1979, the school district decided to ask Ace to correct the plumbing. Thereafter, Ace installed five extra tanks and a cut-off valve at a cost of $1,806.49. The problem was corrected. Ace sent a bill to the school district, the school district refused to pay.

Ace filed this action against the school district and Stewart and Janes seeking payment. The school district filed a third-party complaint against Simons for the amount claimed by Ace. A non-jury trial was had on the third-party complaint. The District Court held against Simons and for the school district. The District Court found that the storage system, as designed, was inadequate to assure proper recycling and by reason of the recycling system, continued turbidity in the well itself caused excessive sand to permeate the entire system. The District Court further found that the school board discussed the problem with the architect and general contractor many times.

The District Court concluded that by reason of the contract, Simons failed to take action that would resolve the problem and that any inadequacy in the specifications was the responsibility of the architect to the school board. The District Court ordered Simons to pay the school board the amount paid to Ace for installation of the tanks and other parts. Simons appeals.

The issues presented for review are:

1. Whether it is mandatory to invoke a standardized arbitration clause in an architect’s service contract.

2. Who is responsible for payment to Ace for the subsequent modification of the water system.

*85 3. Whether the ten percent contingency fund provided in the contract should be used to pay the debt.

The first question is whether Simons can now claim that since the school district did not arbitrate they cannot now seek reimbursement for the payment to Ace. It is well settled in Montana that when there are issues of law or mixed issues of law and fact, arbitration is not mandatory without the consent of the parties involved. In this case, the underlying questions to be resolved by the District Court were: Was the architect negligent in his workmanship and inspection of the building? Does liability attach if the plans and specifications of the architect were properly followed? Who is responsible for payment to Simons? These are questions of law and mixed questions of law and fact.

Section 28-2-708, MCA, provides:

“Restraints upon legal proceedings void. Every stipulation or condition in a contract by which any party thereto is restricted from enforcing his rights under the contract by the usual proceedings in the ordinary tribunals or which limits the time within which he may thus enforce his rights is void.”

This Court has held that contract provisions which require parties to submit future disputes as to questions of law or mixed questions of law and fact are void under this section. Palmer Steel Structures v. Westech, Inc. (1978), 178 Mont. 347, 350, 584 P.2d 152, 154. In this case, neither party consented to arbitrate the dispute. Without the consent of the parties the clause was unenforceable.

Furthermore, the defense of the arbitration provision of the contract was not raised by Simons in his answer and third-party complaint. The right to raise enforcement of the arbitration clause may be waived by failure to assert it in a timely manner. If a party fails to raise the right to arbitrate in his pleadings, he waives his right. 5 Am.Jur. Arbitration and Award §51, at 556, 557. In this case, Simons did not raise the issue of arbitration until much later in the proceedings.

*86 For these reasons Simons is precluded from claiming that the dispute should have been submitted to arbitration.

The second issue is who is responsible for payment for the construction and modification of the water system.

The District Court found that: “The specifications submitted pertaining to the drilling of the well, the development of the water supply, storage and water system, were inadequate; and were not in sufficient detail compared to specifications on other matters relating to said project.”

There was testimony presented at trial to show that the plans and specifications were insufficient, thereby rendering the system inoperative. Tom Smith, an expert in the field of well drilling, testified, that the system was installed as provided in the plans and specifications and that this system was inadequate. He further testified that he felt the problem was apparent from the outset of the project. Simons testified that the tanks and pump were installed according to the architect’s design.

On review, this Court must determine whether there is sufficient evidence in the record to sustain the findings of the District Court. Only when the findings of the District Court are clearly erroneous will they be set aside. Rule 52(a), M.R.Civ.P.; McConnell v. Dempster (1982), 200 Mont. 276, 650 P.2d 799

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reichenbach v. Watco Inc.
Montana Supreme Court, 1997

Cite This Page — Counsel Stack

Bluebook (online)
662 P.2d 1327, 204 Mont. 81, 1983 Mont. LEXIS 697, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ace-plumbing-heating-inc-v-helena-flats-school-district-15-mont-1983.