State ex rel. Cave Construction Co. v. District Court of the Third Judicial District

430 P.2d 624, 150 Mont. 18, 1967 Mont. LEXIS 261
CourtMontana Supreme Court
DecidedJuly 6, 1967
DocketNo. 11310
StatusPublished
Cited by3 cases

This text of 430 P.2d 624 (State ex rel. Cave Construction Co. v. District Court of the Third Judicial District) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Cave Construction Co. v. District Court of the Third Judicial District, 430 P.2d 624, 150 Mont. 18, 1967 Mont. LEXIS 261 (Mo. 1967).

Opinion

MR. JUSTICE JOHN C. HARRISON

delivered the Opinion of the Court.

This is an original proceeding on an application for a writ of supervisory control or other appropriate writ.

In August 1960, the petitioner entered into a contract with the Lower Willow Creek Drainage District for the construction of an earthfilled dam and measuring flumes. The petitioner’s successful bid was based on plans and specifications furnished by the Drainage District which included the excavation of materials from the spillway area and the transportation, placing and compaction of materials to form the earthfill dam. Included in the data was information which allegedly represented the subsurface conditions of materials which were to be excavated and compacted.

After construction started petitioner alleged that it found that the data given on the soil conditions was not as represented; and that the drainage district introduced a new method of testing soils not included in the plans and specifications which resulted in more expense to petitioner. This caused a dispute between the petitioner and the Drainage District which resulted in the petitioner and the contracting officer executing change Order No. 6. The change Order made no provisions for an increase in compensation to petitioner for complying with the modifications. Thereafter, petitioner fully complied with all provisions of the contract and completed the work. A claim was submitted for the additional work which was denied by the contracting officer.

Petitioner alleged that in the original contract modification dated April 14, 1961, the words “no extra cost” were written in blanks concerning increase or decrease of the contract cost. He alleges he refused to sign this modification. A copy of the modification before the court has dashes in the spaces concerning the increase or decrease in costs.

[20]*20Due to the dispute between the parties the matter was submitted, as per contract, to the contracting officer, Otto Braach, for arbitration. He entered certain findings and conclusions along with summation and decision holding against petitioner Cave. These were dated December 1,1961.

Petitioner filed a complaint against the Drainage District on December 7, 1964, in the Eighth Judicial District, Cascade County, Montana. On a motion for change of venue by the Drainage District the cause was moved to Granite County in the Third Judicial District, where the Drainage District moved to dismiss the complaint. After numerous pre-trial conferences and memoranda the trial court on March 14,1967, dismissed the cause.

In dismissing the complaint, the respondent district court adopted one of the four defenses of the Drainage District for its holding. It held “that the plaintiff’s claim herein alleged has heretofore been submitted in accordance with the General Contract Provision No. 6, 'General Provisions’ (Construction Contracts) (PL-466), U. S. Dept, of Agriculture, Soil Conservation Service SCS - 43, Rev. 3 - 60, relative to Disputes to the Contracting Officer for decision after hearing the respective claims of the parties hereto, and a decision rendered, as more fully appears in Exhibit 'B,’ annexed hereto, and made a part of this Answer; that said decision is final and conclusive upon the parties hereto, and by reason thereof, the plaintiff is not entitled to recover on his claim against defendant.” The petitioner admitted the alleged defense except: “That said defense is final and conclusive.”

The first question presented is whether applicant has a plain, speedy and adequate remedy by appeal. Respondents contend it has long been the rule in Montana that a judgment entered following the sustaining of a demurrer, when the appellant has elected to stand upon his pleadings is appealable under section 93-8003, R.C.M.1947.

Examining the court file; we find that the respondent dis[21]*21trict court entered both, an order granting motion to dismiss and a judgment of dismissal on March 14, 1967. However, the last paragraph of the order granting motion to dismiss reads as follows:

“IT IS FURTHER ORDERED that all proceedings herein be stayed for a period of thirty (30) days from the date of filing hereof and entry of Judgment within which the plaintiff, if so advised, may apply for a Writ of Supervisory Control, Writ of Prohibition, or other appropriate Writ.”

The writ was applied for and argued and the alternative show cause order issued within the thirty day period as suggested by the court.

The second question in this cause is whether the “dispute clause” of the general provisions of the construction contract entered into between petitioner and respondent Drainage District bars the district court from taking jurisdiction because the findings and conclusions of the contracting officer were “final and conclusive.”

The “dispute clause” reads:

“Any dispute arising under this contract which is not disposed of by agreement will be decided by the Contracting Officer. Before making a decision the Contracting Officer shall afford the Contractor an opportunity to be heard and to present written evidence. The Contracting Officer shall reduce his decision to writing and mail and otherwise furnish a copy thereof to the Contractor. The decision of the Contracting Officer shall be final and conclusive. Pending final decision the Contractor shall proceed diligently with the performance of the contract.”

Petitioner counters the effect of the dispute clause by citing the following statute: Sec. 13-806, R.C.M.1947, “Every stipulation or condition in a contract by which any party thereto is restricted from enforcing his rights under the contract, by the usual proceedings in the ordinary tribunals, or which limits the time within which he may thus enforce his rights, is void.”

[22]*22In Public School District No. 1, etc. v. Globe & Republic Ins. Co., 146 Mont. 208, 404 P.2d 889, 892, Mr. Justice Castles wrote the following relevant discussion concerning this statute:

“Enacted in 1895, this section is a statutory expression of the common-law rule. Wortman v. Montana Central Ry., 22 Mont. 266, 278, 56 P. 316, 321 (1899). The common law regarding arbitration agreements was set forth by this court in Randall v. American Fire Ins. Co., 10 Mont. 340, 25 P. 953 (1891), and prior to enactment of R.C.M.1947, § 13-806, above.

“ * * The question as to how far courts will be governed by a provision in the contract requiring that controversies arising as to the rights and liabilities of parties thereunder be submitted to arbitration has engaged the profound consideration of both American and English courts of last resort. The conclusion reached, and probably settled beyond further controversy, is that a provision in a contract requiring all differences or controversies arising between the parties as to their rights and liabilities thereunder to be submitted to arbitration, will not be allowed to interfere with or bar the litigation of such controversies when brought into court. To enforce such provisions would be to allow parties to barter away the jurisdiction of courts to determine the rights of parties and redress their wrongs. Therefore such provisions are disregarded, as against public policy. But many of the same eminent authorities hold that a provision in a contract requiring that the value or quantity

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garretson v. Mountain West Farm Bureau Mutual Insurance
761 P.2d 1288 (Montana Supreme Court, 1988)
Palmer Steel Structures v. Westech, Inc.
584 P.2d 152 (Montana Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
430 P.2d 624, 150 Mont. 18, 1967 Mont. LEXIS 261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-cave-construction-co-v-district-court-of-the-third-judicial-mont-1967.