Orient Mid-East Lines v. Albert E. Bowen, Inc.

458 F.2d 572, 1972 U.S. App. LEXIS 10043
CourtCourt of Appeals for the Second Circuit
DecidedApril 17, 1972
Docket554, Docket 71-1876
StatusPublished
Cited by30 cases

This text of 458 F.2d 572 (Orient Mid-East Lines v. Albert E. Bowen, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orient Mid-East Lines v. Albert E. Bowen, Inc., 458 F.2d 572, 1972 U.S. App. LEXIS 10043 (2d Cir. 1972).

Opinion

JAMESON, District Judge:

This is an appeal from a decision of the district court holding defendant-appellant, Albert E. Bowen, Inc. (Bowen), a freight forwarding agent, liable to plaintiff-appellee, Orient Mid-East Lines, an ocean carrier, for breach of an oral contract of affreightment.

Orient commenced the action against Bowen for breach of contract and Gener *573 al Motors Corporation for tortious interference with the contract, alleging damages suffered when a shipment of ten dump trucks from New York to Calcutta was withdrawn by the shipper, General Motors Company. Blackwood Hodge (India) Pvt., Ltd., the consignee and Bowen’s principal, was added as a party defendant. Blackwood’s motion to dismiss was denied, 297 F.Supp. 1149, it failed to answer, and a default judgment was entered. In the memorandum opinion holding Bowen liable the court dismissed the complaint against General Motors.

Factual Background

During the summer of 1963 Black-wood began negotiations with General Motors for the purchase of earth moving equipment and trucks. In November, 1963 General Motors received a purchase order from Blackwood for the trucks involved in this litigation. Blackwood was to arrange for the shipment of the trucks and selected Bowen as freight forwarder.

Eagle Ocean Transport, Inc. (Eagle) was Orient’s agent in New York. The negotiations concerning the contract in question were conducted by James Mu-laradelis (known in the trade as Mu-lara), an employee of Eagle, on behalf of Orient, and Joseph A. Lobe on behalf of Bowen.

The negotiations culminated in an oral agreement that Orient would provide a ship to carry the ten dump trucks to Calcutta at a lump sum freight rate of $4,234.00 apiece. Mulara testified that the date of the telephone conversation in which they arrived at this agreement was February 10, 1964. Lobe testified, and the court found, that the date of the oral agreement was January 30, 1964. The court found further that on February 10 Lobe told Mulara the shipment was ready, and Mulara “gave Lobe the name of the vessel, ‘Orient Mariner’, with a date of March 23, 1964.”

On or about February 10, 1964 Mu-lara made a handwritten memorandum (Ex. 3) and had his secretary type a written contract (Ex. 1) which was dated February 10, 1964. He sent the original and a copy to Lobe. Sometime between February 10 and February 14 Mulara was informed that Lobe had not received the contract. He then sent Lobe an identical contract (Ex. 2), except that the second contract was dated February 14, 1964. Lobe testified that he received and read the first contract. Both contracts named Bowen as the contracting party 1 and contained a reference to “on deck” shipment. There is a conflict in the testimony of Mulara and Lobe with respect to the inclusion of the “on deck” provision, which will be discussed later herein. On or about February 18, 1964 Bowen learned that General Motors would not release the trucks for shipment on Orient’s vessel.

The court found that the next time Lobe and Mulara discussed the contract (after February 10) was on February 28, 1964 and with respect to this conversation said:

“Lobe said he was trying to get the cargo to the pier, but that General Motors would not release it. This was the first time that Mularadelis knew that General Motors was the shipper. In the same conversation Mularadelis ascertained for the first time the name of the consignee, who was Bowen’s principal. Efforts were then made to have the consignee put pressure on General Motors to send the trucks on plaintiff’s vessel.”

These efforts were unsuccessful and Orient’s ship sailed without the cargo. The trucks were later shipped via another carrier.

Two issues are presented on this appeal: (1) whether there was a binding *574 oral contract, and (2) whether Bowen is liable as agent of an undisclosed principal.

Was There a Binding Oral Contract?

With respect to the first issue the district court said:

“The question then is whether there was an enforceable contract entered into by Mularadelis and Lobe on behalf of their respective employers. The answer is simple since Lobe testified that an oral booking is the ordinary practice in this situation and it is binding.
“Lobe’s employer does not question his authority to make these bookings. * * * It questions whether there was an agreement to all the material elements of the contract. I find that there was such agreement.”

Appellant contends that no contract was entered into because “there was no agreement on all of the proposed material terms.” Specifically, it is argued that Lobe did not at any time agree that the trucks would be shipped “on deck” and that Mulara’s memorandum and proposed contracts containing the term “on deck” must be considered as a counteroffer which was not accepted by Bowen.

There is a sharp conflict in the testimony of Mulara and Lobe as to whether the “on deck” provision was discussed in the conversation of January 30 (or February 10 according to Mulara’s recollection), which was considered by both Mu-lara and Lobe as a firm booking. Mu-lara testified positively that the provision was discussed and that Lobe agreed to shipment of the trucks on deck on Orient’s vessel. 2 Lobe testified that there was no mention of the “on deck” term in that conversation or in any prior negotiations and that he did not at any time agree that the trucks would be shipped on deck.

Mulara testified further that the written contract, Exhibit 1, encompassed all of the terms of his prior oral agreement with Lobe. It is undisputed that Lobe did not at any time discuss with Mulara the inclusion of the “on deck” term in the written contract. Lobe testified that he did not take much note of the on deck provision in the contract because he was not sure he was going to get the shipment. 3

The district court found that the parties reached an oral agreement on all the material terms of the contract and that they intended to be bound by that agreement. According due weight to the trial court’s appraisal of the credibility of the witnesses, we are satisfied that these findings are not clearly erroneous. See Smith v. Onyx Oil & Chemical Co., 218 F.2d 104, 108 (3 Cir.1955). With those two facts established, it is clear that a binding contract was created. 1 Corbin, Contracts § 30 at 98-99 (1963).

*575 May Appellant be Held Liable as Agent for an Undisclosed Principal?

Orient concedes that Mulara “knew Bowen was a freight forwarder and that as such acted as agent for someone.” Mulara had heard of Blackwood Hodge and knew the nature of its business. He knew that Bowen’s principal was in Calcutta. He was positive throughout his testimony, however, that he did not know that Blackwood was Bowen’s principal. The written freight contract which Mulara prepared on February 10 (Ex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson v. Royal Caribbean Cruises, Ltd.
389 F. Supp. 3d 431 (N.D. Texas, 2019)
A.P. Moller-Maersk A/S v. Safewater Lines (1) Pvt, Ltd.
276 F. Supp. 3d 700 (S.D. Texas, 2017)
Mediterranean Shipping Co. USA Inc. v. AA Cargo Inc.
46 F. Supp. 3d 294 (S.D. New York, 2014)
Ads Plus Advertising, Inc. v. Ault
928 F. Supp. 2d 683 (W.D. New York, 2013)
CMA-CGM (CANADA), Inc. v. World Shippers Consultants, Ltd.
921 F. Supp. 2d 1 (E.D. New York, 2013)
DEUTSCHE BANK SECURITIES INC. v. Rhodes
578 F. Supp. 2d 652 (S.D. New York, 2008)
Magnolia Capital Advisors Inc. v. Bear Stearns & Co.
272 F. App'x 782 (Eleventh Circuit, 2008)
Muller Boat Works, Inc. v. Unnamed 52' House Barge
464 F. Supp. 2d 127 (E.D. New York, 2006)
Hartford Fire Insurance v. Novocargo USA Inc.
257 F. Supp. 2d 665 (S.D. New York, 2003)
Timken Co. v. United States
166 F. Supp. 2d 608 (Court of International Trade, 2001)
Weil v. Murray
161 F. Supp. 2d 250 (S.D. New York, 2001)
May Ship Repair Contracting Corp. v. Barge Columbia New York
160 F. Supp. 2d 594 (S.D. New York, 2001)
Orion Insurance v. The M/V "Humacao"
851 F. Supp. 575 (S.D. New York, 1994)
Getty Oil Co. v. Norse Management Co.(PTE) Ltd.
711 F. Supp. 175 (S.D. New York, 1989)
Thompson v. Continental Emsco Co.
629 F. Supp. 1160 (S.D. Texas, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
458 F.2d 572, 1972 U.S. App. LEXIS 10043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orient-mid-east-lines-v-albert-e-bowen-inc-ca2-1972.