Oldcastle Precast, Inc. v. Lumbermens Mutual Casualty Co.

170 Cal. App. 4th 554, 88 Cal. Rptr. 3d 363, 2009 Cal. App. LEXIS 77
CourtCalifornia Court of Appeal
DecidedJanuary 23, 2009
DocketG038645
StatusPublished
Cited by39 cases

This text of 170 Cal. App. 4th 554 (Oldcastle Precast, Inc. v. Lumbermens Mutual Casualty Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oldcastle Precast, Inc. v. Lumbermens Mutual Casualty Co., 170 Cal. App. 4th 554, 88 Cal. Rptr. 3d 363, 2009 Cal. App. LEXIS 77 (Cal. Ct. App. 2009).

Opinion

Opinion

FYBEL, J.

INTRODUCTION

Defendants Lumbermens Mutual Casualty Company (Lumbermens) and Safeco Insurance Company of America (Safeco) (collectively, defendants) appeal from a summary judgment entered in favor of plaintiff Oldcastle Precast, Inc., doing business as Utility Vault Company (plaintiff). In granting the motion for summary judgment, the trial court found no triable issue of material fact existed as to Lumbermens’s liability, as surety, on a payment bond in favor of plaintiff or Safeco’s liability, as surety, on a stop notice bond release for plaintiff.

We affirm the judgment. We publish this opinion because of our analysis of the substantive deficiencies of defendants’ opposition to plaintiff’s motion for summary judgment and the trial court’s proper exercise of discretion in denying defendants’ requests for a continuance of the hearing on the motion and the opportunity to submit a revised responsive separate statement. Parties opposing a motion for summary judgment are not entitled to an automatic do-over of their opposition to the motion. Nothing in Code of Civil Procedure section 437c or in the well-reasoned opinion of Parkview Villas Assn., Inc. v. State Farm Fire & Casualty Co. (2005) 133 Cal.App.4th 1197 [35 Cal.Rptr.3d 411] (Parkview Villas) required the trial court in this case to continue the *558 hearing on the summary judgment motion and permit defendants to file a revised responsive separate statement.

FACTS SHOWN BY MOVING PAPERS

General contractor Pinner Construction Company, Inc. (Pinner), and the Orange County Sheriffs Department entered into a public works construction contract for a project known as the “ ‘OCSD — Theo Lacy Jail Expansion, Phase Three, Building B Project’ ” (the project). Pinner and Intra-American Foundation & Drilling Company, Inc. (Intra-American), entered into a written subcontract agreement, under the terms of which Intra-American agreed to furnish and install the concrete pilings for the project. Pursuant to Civil Code sections 3247 and 3248, Lumbermens, as surety, posted a “Labor and Materials Payment Bond” (the payment bond) with the County of Orange for the project.

Intra-American and plaintiff entered into a sub-subcontract under which plaintiff agreed to supply concrete piling materials to Intra-American for the project. The payment bond posted by Lumbermens, as required by Civil Code section 3248, stated that Lumbermens would pay plaintiff for materials it provided for the project if Intra-American failed to pay plaintiff.

Between May 28 and August 8, 2002, plaintiff furnished prestressed concrete piling materials to Intra-American for use on the project. These materials satisfied the contract documents and were neither defective nor deficient. On July 3, 2002, a release stating plaintiff was owed nothing through June 30, 2002 ($0 release), was mistakenly created. Within 25 to 30 minutes of the $0 release’s creation, plaintiff and Intra-American agreed to rescind the $0 release and agreed to a new replacement release reflecting the sum of $46,909.01. Despite assurances it would discard the $0 release, Intra-American sent it to Pinner. Plaintiff itself never sent the $0 release to Pinner.

Plaintiff supplied Intra-American materials totaling $369,974.47, but was paid only $221,443.97, leaving an unpaid balance of $148,530.50. On January 22, 2003, plaintiff filed a stop notice with the County of Orange in the amount of $148,530.50. Safeco, as surety, posted a stop notice release bond in the amount of $185,663.13 (125 percent of the amount of the stop notice filed by plaintiff) and the County of Orange released money otherwise withheld from Pinner as a result of the stop notice filed by plaintiff. Plaintiff prepared a written notice on bond claim which was received by Lumbermens on October 30, 2003.

*559 PROCEDURAL BACKGROUND

Plaintiff sued to recover the outstanding balance Intra-American had failed to pay it under their contract. Plaintiff’s first amended complaint alleged the following claims: (1) breach of written and oral contracts against Intra-American; (2) open book account against Intra-American; (3) account stated against Intra-American; (4) common counts for “Work, Labor, Services and/or Materials Furnished” against Intra-American; (5) action on a payment bond against Lumbermens; (6) action on a contractor’s license bond against Star Insurance Company; and (7) action on a stop notice release bond against Safeco. The complaint prayed for judgment in the total amount of $148,530.50. 1

No cause of action was alleged against Pinner, although it was identified as a defendant in the caption and in the body of the first amended complaint. Pinner participated in the lawsuit, however, through trial and postjudgment motions. Pinner, Lumbermens, and Safeco filed an answer containing a general denial and affirmative defenses.

Before trial, plaintiff argued that evidence of Pinner’s reliance on the $0 release was inadmissible because it did not support an equitable estoppel defense for the sureties as a matter of law. The trial court rejected plaintiff’s argument; the court concluded the doctrine of equitable estoppel was available as a defense to the sureties under the circumstances of this case, and approved a special verdict form asking the jury to make findings of fact relevant to whether the defense had been proven.

The jury found in favor of Pinner, Lumbermens, and Safeco, and made the special finding that Pinner reasonably relied on the $0 release. Judgment was entered in favor of Pinner, Lumbermens, and Safeco. The court granted Pinner, Lumbermens, and Safeco’s motion for prevailing party attorney fees and costs.

Plaintiff appealed from both the judgment and the postjudgment order awarding Pinner attorney fees and costs, arguing (1) the trial court erred by concluding, as a matter of law, that the defense of equitable estoppel was available to Lumbermens on the payment bond claim, based solely on Pinner’s reliance on the $0 release; (2) substantial evidence did not support the jury’s finding plaintiff intended that others rely on the $0 release; and (3) the trial court erred by awarding Pinner attorney fees and costs.

In an unpublished opinion, this court reversed the judgment, holding the trial court erred by concluding that Lumbermens could assert equitable *560 estoppel as a defense against plaintiff’s action on the payment bond, based solely on Pinner’s reliance on an incorrect release. (Oldcastle Precast Inc. v. Pinner Construction Co., Inc. (May 11, 2006, G035133) [nonpub. opn.].) In light of our holding, we did not reach plaintiff’s other arguments regarding the sufficiency of the evidence plaintiff intended others to rely on the $0 release or the award to Pinner of attorney fees and costs.

Following remand, plaintiff filed a motion for summary judgment, or for summary adjudication, of three specified causes of action: (1) the breach of written contract claim against Intra-American; (2) the action for recovery on the payment bond against Lumbermens; and (3) the action for recovery on the stop notice release bond against Safeco.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PTI US Towers II v. Sinclaire CA3
California Court of Appeal, 2026
Ortiz v. Morley Construction Co. CA2/5
California Court of Appeal, 2025
Mandell-Brown v. Novo Nordisk Inc.
California Court of Appeal, 2025
City of South Gate v. Robles CA2/2
California Court of Appeal, 2024
Garcia v. Bowman CA4/3
California Court of Appeal, 2024
Seraphim Energy Group v. HSZ Energy CA1/3
California Court of Appeal, 2024
Fitness International v. KB Salt Lake III
California Court of Appeal, 2023
Park v. Beverly OB & GYN Medical Center CA2/8
California Court of Appeal, 2023
Degreed v. Viventis Search Asia CA1/2
California Court of Appeal, 2023
Green v. Suzuki CA2/7
California Court of Appeal, 2022
Garcia v. Border Transportation Group
California Court of Appeal, 2018
Garcia v. Border Transportation Group, LLC
California Court of Appeal, 2018
Rush v. White Corp.
California Court of Appeal, 2017
Rush v. White Corp.
221 Cal. Rptr. 3d 240 (California Court of Appeals, 5th District, 2017)
Mares v. Lien Enforcement CA4/1
California Court of Appeal, 2016
Wells Fargo Bank v. Thornton CA1/5
California Court of Appeal, 2015

Cite This Page — Counsel Stack

Bluebook (online)
170 Cal. App. 4th 554, 88 Cal. Rptr. 3d 363, 2009 Cal. App. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oldcastle-precast-inc-v-lumbermens-mutual-casualty-co-calctapp-2009.