Office of Public Utility Counsel v. Public Utility Commission

843 S.W.2d 718, 1992 Tex. App. LEXIS 3073, 1992 WL 361487
CourtCourt of Appeals of Texas
DecidedDecember 9, 1992
DocketNos. 3-91-301-CV, 3-91-237-CV
StatusPublished
Cited by25 cases

This text of 843 S.W.2d 718 (Office of Public Utility Counsel v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Office of Public Utility Counsel v. Public Utility Commission, 843 S.W.2d 718, 1992 Tex. App. LEXIS 3073, 1992 WL 361487 (Tex. Ct. App. 1992).

Opinion

KIDD, Justice.

The central issue presented on appeal is whether an order rendered by the Public Utility Commission of Texas (the “Commission”) was final and appealable. The Commission opened Docket 66681 solely to determine the prudence of the construction expenditures in the South Texas Project (“STP”) by two utilities, Houston Lighting & Power Company (“HL & P”) and Central Power & Light Company (“CPL”).2 Following extensive discovery and hearings, the Commission rendered its last order in Docket 6668, and the “Ratepayers”3 and HL & P sought judicial review of that order in separate causes in district court. The Commission, in both causes, and CPL, in the Ratepayers’ cause, moved to dismiss on the grounds that the last order in Docket 6668 was not a final administrative order, and, therefore, was not appealable. The trial court granted the motions to dismiss. The Ratepayers and HL & P bring separate appeals challenging the trial court’s dismissal. We will affirm in part and reverse in part.

BACKGROUND AND PROCEDURAL HISTORY

The procedural history of this case is long and tortuous. Docket 6668 originally developed from a request by HL & P and CPL in August 1985 that the Commission resolve all prudence issues arising during the Brown & Root construction era at STP.4 The Commission, however, declined to limit the prudence inquiry to Brown & Root. The Commission, anticipating that it would eventually have to adjudicate all prudence issues in upcoming rate cases and that discovery of STP prudence issues would require much more time than a rate case would permit, directed its general counsel to open a full inquiry into all STP prudence issues. The Commission opened that inquiry on January 3, 1986, as Docket 6668. The Commission created Docket 6668 as an economical and practical procedure both to handle the massive discovery and to ensure a fair hearing regarding STP prudence matters. In its January 3, 1986, general counsel’s original petition of inquiry, the Commission made clear that Docket 6668 would determine all STP prudence issues for both Units 1 and 2 of the project.

STP Unit 1 achieved commercial operation on August 25,1988. On November 23, 1988, pursuant to section 43(a) of the Public Utility Regulatory Act,5 HL & P filed its application for a rate increase in which it sought to include its share of the construction cost of STP Unit 1 in its rate base. The Commission styled this rate case as Docket 8425. On December 20, 1988, the [721]*721hearings examiner in Docket 6668 rendered examiner’s order number 42, ordering a joint hearing on STP prudence issues in Docket 6668, Docket 8425, and any future rate case filed by CPL. In this order, the Commission again expressed its intent that Docket 6668 would be the single vehicle for the final determination of all STP-related prudence issues. Specifically, examiner’s order number 42 provided that “the scope of the hearing in this case shall include all prudence issues, and shall be such as to finally determine all those issues.”

CPL filed its STP Unit 1 rate case, Docket 8646, on February 15, 1989. The Commission began hearings in Docket 6668 on May 22,1989. After extensive fact-finding on prudence issues, the Commission issued its examiner’s report on April 19, 1990. In the examiner’s report, the administrative law judge (“AU”) wrote that the Commission’s goal in joining the STP prudence issues included in Dockets 8425 and 8646 with Docket 6668 “was to determine the most expeditious and least expensive means of producing a full record for the Commission’s consideration of these issues. That goal has been achieved, together with the opportunity for the Commission to deal with all the STP construction-related issues consistently in a final order.” The report also identified the units to which it was applicable. Noting that only CPL opposed the inclusion of Unit 2 in Docket 6668, the ALJ ordered that Docket 6668 would apply to both Units 1 and 2. The AU also ruled that the findings in Docket 6668 relating to Unit 2 would be final and given res judicata effect. The parties opposed to the conclusions of the examiner’s report timely filed exceptions on which the Commission heard oral arguments.

On June 20,1990, the Commission issued its final substantive order in Docket 6668. The Commission held that the examiner’s report and its findings of fact and conclusions of law in Docket 6668 applied only to HL & P and should neither be rejected nor adopted as to CPL.6 The Commission severed all issues in Docket 6668 pertaining to CPL and assigned them to a separate docket," Docket 9995.

In the June 20 order, the Commission also issued, among others, the following three conclusions of law:

Conclusion of Law No. 21: The powers given the Commission in PURA §§ 16(a) and (h), 17(a) and (e), 29(c), 39(a), and 41(a) need not be decided only within the context of a rate case filed by a utility.
Conclusion of Law No. 22: The reasonable and prudent investment of HL & P in Unit 2 of STP is properly decided in this case.
Conclusion of Law No. 23: The findings in this case regarding HL & P’s prudence with respect to Unit 2 of STP will be final and will carry full res judica-ta effect when the order in this case becomes final.

On August 3, 1990, the Commission rendered an order partially granting the motions for rehearing of OPC, CFUR, Houston Coalition of Cities, LUCES, and the Commission. Additionally, the order extended the time for ruling on the rest of the motions for rehearing.

On September 18, 1990, the Commission issued its last order in Docket 6668, entitled “Order on Rehearing,” denying all motions for rehearing and incorporating the June 20th order, including all accompanying findings of fact and conclusions of law, in its entirety.

Under section 19(a) of the Administrative Procedure and Texas Register Act7 and section 69 of PURA, the Ratepayers filed an original petition in district court seeking [722]*722judicial review of the Commission’s order.8 The Commission and CPL filed pleas to the jurisdiction, alleging that the order was not final and appealable. The court sustained the pleas to the jurisdiction, dismissing the Ratepayers’ action.

The Ratepayers subsequently appealed the district court’s order of dismissal in cause number 3-91-301-CV. They bring one point of error: The district court erred in granting the pleas to the jurisdiction and, thus, dismissing the case. Joining the Commission and CPL as a party in cause number 3-91-301-CV, HL & P responds that the order was not final and appealable.

On the basis that the Commission had erroneously calculated the amount of HL & P’s imprudent investment in STP, HL & P filed a separate lawsuit in district court seeking judicial review of the order. In its district-court petition, HL & P admitted that the order became final and appealable when the Commission denied HL & P’s motion for rehearing in the September 18th order. The district court dismissed HL & P’s suit for judicial review on two grounds: (1) the order was not final and appealable and (2) HL & P did not timely file its motion for rehearing with the Commission.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coastal Habitat Alliance v. Public Utility Commission
294 S.W.3d 276 (Court of Appeals of Texas, 2009)
Henry Gauna v. State
Court of Appeals of Texas, 2006
Texas Mutual Insurance Co. v. Texas Department of Insurance
214 S.W.3d 613 (Court of Appeals of Texas, 2006)
Save Our Springs Alliance v. City of Austin
149 S.W.3d 674 (Court of Appeals of Texas, 2004)
City of Waco v. Texas Natural Resource Conservation Commission
83 S.W.3d 169 (Court of Appeals of Texas, 2002)
El Paso Electric Co. v. Public Utility Commission
917 S.W.2d 846 (Court of Appeals of Texas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
843 S.W.2d 718, 1992 Tex. App. LEXIS 3073, 1992 WL 361487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/office-of-public-utility-counsel-v-public-utility-commission-texapp-1992.