El Paso Electric Co. v. Public Utility Commission

917 S.W.2d 846, 1995 Tex. App. LEXIS 1544, 1995 WL 831604
CourtCourt of Appeals of Texas
DecidedJuly 12, 1995
Docket03-93-00661-CV
StatusPublished
Cited by22 cases

This text of 917 S.W.2d 846 (El Paso Electric Co. v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
El Paso Electric Co. v. Public Utility Commission, 917 S.W.2d 846, 1995 Tex. App. LEXIS 1544, 1995 WL 831604 (Tex. Ct. App. 1995).

Opinions

BEA ANN SMITH, Justice.

We withdraw our opinion issued April 5, 1995 and substitute the following in its place.

The Court on its own motion has considered this cause en banc. See Tex.RApp.P. 79(d), (e). El Paso Electric Company (“EPEC”), the City of El Paso, the Office of Public Utility Counsel (“OPUC”), the State of Texas, and the Public Utility Commission (“Commission”)1 appeal from a district-court judgment rendered in a suit for judicial review under the Public Utility Regulatory Act. Tex.Rev.Civ.StatAnn. art. 1446c (West Supp. 1995) (hereafter “PURA”). The district court’s judgment reverses and remands certain aspects of the Commission’s final order and affirms the remainder. We will affirm the district-court judgment in part and reverse and render in part. See Administrative Procedure Act, Tex.Gov’t Code Ann. § 2001.174 (West 1994) (hereafter “APA”).2

BACKGROUND

EPEC is an electric utility that provides retail electric service in Texas and New Mexico and wholesale service in Texas, New Mexico, California, and Mexico. In 1978 the Commission awarded EPEC a certificate of convenience and necessity to expand its power generation system by purchasing an interest in the Palo Verde Nuclear Generating Station. Palo Verde consists of three separate units; EPEC’s ownership interest3 entitles it to 200 megawatts of power from each unit, for a total of 600 megawatts.

This appeal arises from the Commission’s final order in Docket 9945 entered in response to EPEC’s request for a rate increase of $131 million. See Tex.Public Util.Comm’n, Application of El Paso Electric Co. for Auth. to Change Rates, Docket No. 9945, 18 Tex. P.U.C.Bull. 9 (Feb. 6, 1992). As part of its proposed rate increase, EPEC requested inclusion in rate base of the $300 million cost of constructing Unit 3. The Commission permanently disallowed $27.23 million of costs for imprudence resulting in construction delays. The Commission then found that the utility had imprudently failed to reduce its [854]*854massive investment in the Palo Verde project, yielding more capacity than its customers needed. Because the Commission concluded that this “excess capacity” in the form of Unit 3 is not currently “used and useful,” its costs were excluded from rate base at this time. See PURA § 41(a). However, rather than permanently disallow such a huge expenditure because of EPEC’s imprudent level of participation in the project, the Commission decided that inclusion of Unit 3 in rate base be postponed only until the capacity becomes “used and useful.” Anticipating that Unit 3’s capacity would become useful in increments, the Commission proposed to include increasing percentages of Unit 3 costs in rate base as the capacity becomes needed to serve customers. EPEC challenges the Commission’s findings that EPEC imprudently failed to reduce its level of participation in the Palo Verde project, argues that Unit 3 does not represent excess capacity, and complains of the Commission’s postponement of its recovery of Unit 3 construction costs. The other appellants raise additional points of error asserting the res judicata effect of decisional imprudence holdings in prior dockets, and challenging the treatment of income tax expenses, deferred accounting charges, the tariff classification of state agencies, and the award of attorney’s fees.

DISCUSSION

Finality of the Commission’s Order

Before proceeding to EPEC’s points of error, we must address an argument raised by the State challenging the finality of the Commission’s order. The State argues that the Commission’s order was not a final, appealable order because the Commission continued to approve a rate moderation plan that fails to assign revenue responsibility for deferred revenues.4 Cf. City of Corpus Christi v. Public Util. Comm’n, 572 S.W.2d 290, 299-300 (Tex.1978) (only final agency orders are appealable); State v. Public Util. Comm’n, 840 S.W.2d 650, 654 (Tex.App.—Austin 1992), rev’d in part on other grounds, 883 S.W.2d 190 (Tex.1994) (final order leaves nothing open for future disposition). The State contends that the Commission abdicated its responsibility to ensure just and reasonable rates under PURA because it failed to identify the class of consumers that will pay for these costs in the future.

As we have noted in the analogous situation of deferred accounting treatment for capital costs, “the presence of a condition in an order does not automatically destroy its finality.” State v. Public Util. Comm’n, 840 S.W.2d at 654-55. Courts will treat as final an order that is definitive, promulgated in a formal manner, and issued with an expectation of compliance. Office of Pub. Util. Counsel v. Public Util. Comm’n, 843 S.W.2d 718, 723 (Tex.App.—Austin 1992, writ denied) (citing Texas-New Mexico Power Co. v. Texas Indus. Energy Consumers, 806 S.W.2d 230, 232 (Tex.1991)). For example, the Commission may issue an order determining the prudence of a utility’s investment before including the costs in rate base; the order is final because it entitles the utility to recover the costs, even though ratepayers remain unaffected by the order until rates incorporating these costs are set. See id. at 723-24 (order need only establish legal relationship between parties to be final and need not resolve all potential related controversies). Similarly, the Commission’s order did not need to assign responsibility for revenue increases beyond those incorporated in the current rate design to be final. The State’s first point of error is overruled.

In a related point of error, the State argues that the Commission’s order is unreasonable and discriminatory to future ratepayers because the failure to allocate deferred revenues by customer class allows customers who leave the system to escape responsibility for their fair share of the cost of service provided for their benefit. The State’s argument is premature; there has been no show[855]*855ing that the deferred revenues are guaranteed or that the State has been discriminated against by the rate plan currently authorized. Without expressing an opinion on the merits of the State’s argument, we overrule the State’s second point of error as not ripe for our consideration.

Unit 3: Excess Capacity?

PURA section 41(a) provides: “Utility rates shall be based upon the original cost of property used by and useful to the public utility in providing service including construction work in progress at cost as recorded on the books of the utility.” In its first point of error, EPEC asserts that Palo Verde Unit 3 is currently “used and useful” in providing service to its customers and does not represent excess capacity; hence, the costs of this unit should have been included in rate base immediately.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Data Foundry, Inc. v. City of Austin, Texas
575 S.W.3d 92 (Court of Appeals of Texas, 2019)
Mayfield v. Peek
546 S.W.3d 253 (Court of Appeals of Texas, 2017)
Public Utility Commission v. Texas Telephone Ass'n
163 S.W.3d 204 (Court of Appeals of Texas, 2005)
Reliant Energy, Inc. v. Public Utility Commission
153 S.W.3d 174 (Court of Appeals of Texas, 2004)
Central Power & Light Co./Cities of Alice v. Public Utility Commission
36 S.W.3d 547 (Court of Appeals of Texas, 2001)
In Re Citizens Utilities Co.
769 A.2d 19 (Supreme Court of Vermont, 2000)
Southwestern Public Service Co. v. Public Utility Commission of Texas
962 S.W.2d 207 (Court of Appeals of Texas, 1998)
El Paso Electric Co. v. Public Utility Commission
917 S.W.2d 846 (Court of Appeals of Texas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
917 S.W.2d 846, 1995 Tex. App. LEXIS 1544, 1995 WL 831604, Counsel Stack Legal Research, https://law.counselstack.com/opinion/el-paso-electric-co-v-public-utility-commission-texapp-1995.