Southwestern Electric Power Company v. Public Utility Commission of Texas

CourtCourt of Appeals of Texas
DecidedNovember 4, 2011
Docket07-10-00108-CV
StatusPublished

This text of Southwestern Electric Power Company v. Public Utility Commission of Texas (Southwestern Electric Power Company v. Public Utility Commission of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Electric Power Company v. Public Utility Commission of Texas, (Tex. Ct. App. 2011).

Opinion

NO. 07-10-00108-CV

IN THE COURT OF APPEALS

FOR THE SEVENTH DISTRICT OF TEXAS

AT AMARILLO

PANEL A

NOVEMBER 4, 2011

SOUTHWESTERN ELECTRIC POWER COMPANY, ET AL., APPELLANTS

v.

PUBLIC UTILITY COMMISSION OF TEXAS, APPELLEE

FROM THE 261ST DISTRICT COURT OF TRAVIS COUNTY;

NO. D-1-GN-008-003871; HONORABLE LORA J. LIVINGSTON, JUDGE

Before CAMPBELL and HANCOCK and PIRTLE, JJ.

OPINION

Southwestern Electric Power Company (SWEPCO) and Texas Industrial Energy

Consumers (TIEC) appeal from the trial court’s judgment affirming an order of the Public

Utility Commission of Texas (the PUC) granting a certificate of convenience and

necessity (CCN) to SWEPCO. We will affirm. Factual and Procedural History

The PUC Order

On August 12, 2008, the PUC entered an order with which nearly all concerned

parties were dissatisfied. By a 2-1 vote, the PUC granted SWEPCO an amendment to

its existing CCN permitting SWEPCO to build a coal-fired ultra-supercritical generating

plant, referred to as the Turk plant, a few miles northeast of Texarkana, in Arkansas.

The PUC granted the amendment subject to specified conditions and caps on the future

recovery of yet-to-be-incurred costs.

The Turk plant is planned as a generation facility that will serve both SWEPCO’s

retail and wholesale customers in three states. Because SWEPCO intends to serve

captive retail customers in Texas, it was required to seek a CCN from the PUC. See 16

TEX. ADMIN. CODE § 25.101(b)(2) (2011) (Pub. Util. Comm’n of Tex., Certification

Criteria). In this context, SWEPCO is a hybrid entity–an electric utility monopoly

obligated to serve captive Texas ratepayers in certain areas of the state and a power

generation company competing in the multistate wholesale market.

Litigation in the Trial Court

SWEPCO was displeased with the cost caps and, therefore, sought judicial

review of their legality. TIEC sought judicial review contesting the PUC’s determination

of the necessity of the Turk plant. The two cases were consolidated. In the trial court,

SWEPCO unsuccessfully contested the PUC’s authority to impose the two caps at

2 issue. Equally unsuccessful, TIEC argued that the PUC improperly considered

SWEPCO’s wholesale load in determining the need for the Turk plant.

Just before the hearing in the trial court, SWEPCO filed a letter questioning

whether its own issues relating to the cost caps were ripe for judicial review. SWEPCO

pointed out that any effect from the caps would be felt only if (1) the plant was built and

used to serve retail customers, (2) its prudent costs exceeded the cap and/or yet-to-be-

passed legislation resulted in carbon containment costs in excess of the cap, and (3)

the then-current PUC in some future rate case determined to follow the cost cap

provisions. So, SWEPCO argued to the trial court, the issues might not be ripe and it

might be asking the trial court to enter an unconstitutional advisory opinion.

The trial court suggested SWEPCO file a nonsuit in the case if it maintained that

subject-matter jurisdiction was lacking. SWEPCO declined, and the trial court

concluded that it did have subject-matter jurisdiction. The trial court affirmed the PUC

order in all respects by judgment signed February 10, 2010.1 This appeal followed and

was originally filed in the Third Court of Appeals but, pursuant to the Texas Supreme

Court’s docket equalization efforts, was transferred to this Court. See TEX. GOV’T CODE

ANN. § 73.001 (West 2005).

1 As a prerequisite to obtaining judicial review of an administrative order, the appealing party must have filed a motion for rehearing in the underlying administrative proceeding. See TEX. GOV’T CODE ANN. § 2001.145(a) (West 2008); Hammack v. Pub. Util. Comm’n of Tex., 131 S.W.3d 713, 732 (Tex.App.—Austin 2004, pet. denied). It appears that this prerequisite was satisfied. 3 Appeal

SWEPCO’s appeal stems from its request for a CCN amendment from the PUC,

required when a utility in a still-regulated portion of the State provides service to a

captive retail customer base. The PUC granted SWEPCO’s CCN but did so with

conditions the imposition of which, SWEPCO contends, was beyond the PUC’s

authority. TIEC appeals the same order, contending that the PUC did not have the

authority to enter the order based on consideration of SWEPCO’s wholesale load rather

than solely on the capacity to serve captive retail customers. The PUC maintains that it

has broad regulatory authority, broad enough to authorize it to grant the CCN

amendment and to do so with the particular restrictions, especially in light of the

complex transition-to-full-deregulation climate and considering that SWEPCO is a hybrid

entity serving captive retail customers and competing in the wholesale market.

With that said, we must consider the following issues: (1) whether the PUC had

the authority to consider SWEPCO’s wholesale load in determining whether to grant the

CCN and, if so, (2) whether the PUC had the authority to impose caps on what costs

SWEPCO could recoup through rates applicable to captive Texas ratepayers. As a

preliminary matter, though, we must decide (3) whether the issues concerning

imposition of the cost caps are ripe for judicial review.

4 Ripeness

SWEPCO raises this issue, contending, as it did below, that the issue concerning

the cost caps may not yet be ripe for review.2 We address the issue of this Court’s

subject-matter jurisdiction first because, if we do lack jurisdiction to review the matter,

review of the cost caps issue would be precluded. See Patterson v. Planned

Parenthood of Houston & Se. Tex., Inc., 971 S.W.2d 439, 442 (Tex. 1998); Garrett

Operators, Inc. v. City of Houston, No. 01-09-00946-CV, 2011 Tex. App. LEXIS 3583, at

*6 (Tex.App.—Houston [1st Dist.] May 12, 2011, pet. filed).

SWEPCO contends that the contingencies built into the cost caps render the

issues concerning the caps unripe. SWEPCO first points out that it has not sustained a

concrete injury as a result of the cost caps. By its own admission, the construction cost

estimates at the time of briefing was in excess by four percent of the caps, but, as it

emphasized, those figures are simply estimates. Then, with respect to the cost caps

relating to carbon dioxide emission control, SWEPCO contends that Congress has yet

to pass federal legislation to govern this aspect of the plant’s operation and, therefore,

no one can determine the costs of compliance or, consequently, whether the cost caps

2 SWEPCO’s position on ripeness has been somewhat equivocal in that it advances the issue but, ultimately, maintains that, because this proceeding is a review of an agency action, the issue is ripe for review. It also urges, however, that both the Texas Supreme Court and the Austin Court of Appeals have issued opinions that would support the conclusion that the cost caps issue is not ripe. See Pub. Util. Comm’n of Tex. v. Houston Lighting & Power Co., 748 S.W.2d 439, 442 (Tex. 1987); Reliant Energy, Inc. v. Pub. Util. Comm’n of Tex., 153 S.W.3d 174, 183 (Tex.App.—Austin 2004, pet. denied).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Centerpoint Energy, Inc. v. Public Utility Commission
143 S.W.3d 81 (Texas Supreme Court, 2004)
State v. Holland
221 S.W.3d 639 (Texas Supreme Court, 2007)
First American Title Insurance Co. v. Combs
258 S.W.3d 627 (Texas Supreme Court, 2008)
State v. Public Utility Com'n of Texas
344 S.W.3d 349 (Texas Supreme Court, 2011)
Reliant Energy, Inc. v. Public Utility Commission of Texas
62 S.W.3d 833 (Court of Appeals of Texas, 2001)
Central Power & Light Co./Cities of Alice v. Public Utility Commission
36 S.W.3d 547 (Court of Appeals of Texas, 2001)
Reliant Energy, Inc. v. Public Utility Commission
153 S.W.3d 174 (Court of Appeals of Texas, 2004)
USA Waste Services of Houston, Inc. v. Strayhorn
150 S.W.3d 491 (Court of Appeals of Texas, 2004)
Browning-Ferris, Inc. v. Brazoria County
742 S.W.2d 43 (Court of Appeals of Texas, 1987)
Texas-New Mexico Power Co. v. Texas Industrial Energy Consumers
806 S.W.2d 230 (Texas Supreme Court, 1991)
State v. Public Utility Com'n of Texas
883 S.W.2d 190 (Texas Supreme Court, 1994)
Jones v. Fowler
969 S.W.2d 429 (Texas Supreme Court, 1998)
Perry v. Del Rio
66 S.W.3d 239 (Texas Supreme Court, 2001)
City of Corpus Christi v. Public Utility Commission of Texas
51 S.W.3d 231 (Texas Supreme Court, 2001)
Railroad Commission of Texas v. Coppock
215 S.W.3d 559 (Court of Appeals of Texas, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Southwestern Electric Power Company v. Public Utility Commission of Texas, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-electric-power-company-v-public-utili-texapp-2011.