Per Curiam.

The threshold question posed for resolution in this cause is whether the determination of the commission, which found Unit No. 1 of the Davis-Besse nuclear generating facility used and useful, as of the date certain, in rendering the utility service for which rates are to be charged, was unlawful or unreasonable. R. C. 4903.13.

Appellant contends that the commission improperly included Unit No. 1 in the valuation of Toledo Edison’s rate base when the evidence demonstrates that the unit, as of the date certain, was not "‘used or useful” in providing service to the jurisdictional ratepayers of Toledo Edison within the intended meaning of R. C. 4909.15(A) (1). Appellant avers that as of the date certain, Unit No. 1 did not contribute to Toledo Edison’s overall electric demand requirements, and did not render “useful” service to its ratepayers. Appellant argues further that the unit, as of the date certain, was involved in extensive start-up testing, designed primarily to determine whether the unit would provide safe, dependable, and reliable service in the proximate future. Appellant urges this court to reverse the commission, and points out that the premature inclusion in the [453]*453rato base of a generating unit may result in a rate increase for Toledo Edison’s consumers when the rendition of service by the unit may ultimately prove not to be feasible for •an extended period of time.

In R. C. 4909.15, the (General Assembly has provided a legislative formula for the commission to follow in determining the value of property to be included in a public utility’s rate base for purposes of determining just and reasonable rates. R. C. 4909.15(A)(1) expressly provides that, in determining the extent to which property of a utility may be included in its rate base, the commission shall determine “ [t] he valuation as of the date certain of the property of the public utility used and useful in rendering the public utility service” to the utility’s ratepayers. Incorporated in this statutory language is the generally accepted principle that a utility is not entitled to include in the valuation of its rate base property not actually used •or useful in providing its public service, no matter how useful the property may have been in the past or may yet be in the future. Denver Union Stock Yard Co. v. United States (1938), 304 U. S. 470.

Whether property is used and useful in providing service to the customers of a utility is a question which of necessity must be resolved on the basis of a case-by-oaise analysis. That status cannot be determined through the application of a rigid formula, but should be ascertained by the trier of the facts in light of all the circumstances. Columbus Gas & Fuel Co. v. Pub. Util. Comm. of Ohio (1934), 292 U. S. 398; Petition of New England Tel. & Tel. Co. (1949), 115 Vt. 494, 66 A. 2d 135; Kansas Gas & Electric Co. v. State Corp. Comm. (Kan. 1976), 544 P. 2d 1396. Upon review of such factual conclusions, a finding of the commission will not be reversed unless it appears from the record that it is manifestly against the weight of the evidence or is so clearly unsupported by the record as to show misapprehension, mistake, or a willful clisi-eg-ard of duty. City of Kenton v. Pub. Util. Comm. (1965), 3 Ohio St. 2d 71, 73, 209 N. E. 2d 430; Cleveland Elec. Illuminating Co. v. Pub. Util. Comm. (1975), 42 Ohio St. 2d 403, 330 N. E. [454]*4542d 1, certiorari denied 423 U. S. 986, paragraph eight of the syllabus.

The commission concluded, under the instant facts and circumstances, that Unit No. .1 of the Davis-Besse nuclear facility was used and useful as of the date certain, 'and in so doing the commission selected the initial synchronization of the unit to Toledo Edison’s transmission system as the critical event in which the unit acquired used and useful status. The commission’s conclusion was based, in part, on testimony adduced at the hearing indicating that synchronization represents a distinct, significant and readily identifiable physical occurrence which demonstrates the operational status of a generating unit. The commission noted further “that while initial synchronization of a major generating unit will be the initial point at which a property is determined to be used and useful the circumstances surrounding the initial synchronization of any generating unit mil be carefully examined and scrutinized” to determine if the “synchronization was in any way manipulated or, subsequent to the initial synchronization of a major defect or design flaw is discovered, rendering the plant inoperative for significant periods of time * * Finding no such evidence herein, the commission determined that the synchronization of Unit No. 1 reflects initial used and useful status.

In Glenwood Light & Water Co. v. Glenwood Springs (1936), 98 Colo. 340, 55 P. 2d 1339, the Colorado Supreme Court held, at page 343:

“The test of whether the value of any given property shall be included in the rate base of a public utility is whether it is used and useful' in.supplying the commodity or service that utility has undertaken to furnish.”

To the same effect is Providence Gas Co. v. Burman (R. I. 1977), 376 A. 2d 687, wherein the court reasoned at page 691:

“A. utility’s rate base represents the total .investment in or the fair value of the used and useful property which it', necessarily devotes to the rendering of the regulated service ***.”•.

[455]*455.. The express language of R. C. 4909.15(A) (1.) closely parallels the test enunciated by the above authorities in requiring property to be determined to be “used and useful'in rendering the public utility service” to the utility’s jurisdictional customers before it can be properly included in the valuation of the utility’s rate base.

While the initial synchronization of a nuclear generating unit to its transmission system presents some indi■cation that a generating facility is useful for purposes of supplying service to ratepayers, as the commission found, we conclude that, under the facts and circumstances at bar, the manifest weight of the evidence demonstrates that, ■at the date certain, the unit in question was undergoing ■start-up testing, which was not completed until November 12,1977. Until that time, it was unknown whether the unit's systems would function in an integrated manner and continue to do so in the proximate future.

Furthermore, the uncontroverted facts demonstrate that prior to September 1, 1977, the date certain, the unit in question provided no beneficial service to the ratepayers of the utility. The record shows that even though the unit was synchronized with Toledo Edison’s transmission system, and Mode 1 start up was achieved on August 30, 1977, positive net electrical generation on a daily basis •did not result until September 20, 1977, several weeks after the passage of the date certain. Although, as the commission noted, the unit produced electricity on August 28, 1977, as part of the Mode 2 testing process, the evidence in the record is to the effect that the output of the. unit was less than the' amount consumed from Toledo Edison’s transmission system in order to operate the unit.

Free access — add to your briefcase to read the full text and ask questions with AI

Office of Consumers' Counsel v. Public Utilities Commission, 391 N.E.2d 311, 58 Ohio St. 2d 449, 12 Ohio Op. 3d 378, 1979 Ohio LEXIS 457 (Ohio 1979).

391 N.E.2d 311 (Office of Consumers' Counsel v. Public Utilities Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re Application of Suburban Natural Gas Co. (Slip Opinion)
2021 Ohio 3224 (Ohio Supreme Court, 2021)
Industrial Energy Users-Ohio v. Public Utilities Commission
117 Ohio St. 3d 486 (Ohio Supreme Court, 2008)
Columbus Southern Power Co. v. Pub. Util. Comm.
1993 Ohio 67 (Ohio Supreme Court, 1993)
Columbus Southern Power Co. v. Public Utilities Commission
620 N.E.2d 835 (Ohio Supreme Court, 1993)
Ohio Edison Co. v. Public Utilities Commission
589 N.E.2d 1292 (Ohio Supreme Court, 1992)
Pacific Power & Light Co. v. Public Service Commission
677 P.2d 799 (Wyoming Supreme Court, 1984)
Dayton Power & Light Co. v. Public Utilities Commission
447 N.E.2d 733 (Ohio Supreme Court, 1983)
Consumers' Counsel v. Public Utilities Commission
447 N.E.2d 749 (Ohio Supreme Court, 1983)
Office of Consumers' Counsel v. Public Utilities Commission
424 N.E.2d 300 (Ohio Supreme Court, 1981)
City of Cleveland v. Public Utilities Commission
406 N.E.2d 1370 (Ohio Supreme Court, 1980)