Northern Corporation v. Chugach Electric Ass'n

518 P.2d 76, 1974 Alas. LEXIS 373
CourtAlaska Supreme Court
DecidedJanuary 16, 1974
Docket1758, 1768
StatusPublished
Cited by16 cases

This text of 518 P.2d 76 (Northern Corporation v. Chugach Electric Ass'n) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Corporation v. Chugach Electric Ass'n, 518 P.2d 76, 1974 Alas. LEXIS 373 (Ala. 1974).

Opinion

OPINION

Before RABINOWITZ, C. J., and CON-NOR and BOOCHEVER, JJ.

BOOCHEVER, Justice.

We are here presented with issues concerning the alleged impossibility of performing a public contract. Northern Corporation (hereafter referred to as Northern), appellant and cross-appellee, entered into a contract with Chugach Electric Association (hereafter Chugach), appellee and cross-appellant, on August 3, 1966 for the repair and protection of the upstream face of the Cooper Lake Dam. The contract was awarded to Northern on the basis of its low bid in the sum of $63,655.

The work to be performed was described as follows:

It is required that the upstream face of Cooper Lake Dam be regraded and rip-rap and filter layer stone quarried, hauled and placed on the upstream face and all other appurtenant work accomplished as required, all in accordance with these plans and specification [sic]. There are about 1750 cubic yards of fil *78 ter material and 3950 cubic yards of rip-rap to be placed. The Contractor shall furnish all labor, equipment, materials, etc. required for this proj ect.

The contract called for completion of the work within 60 days of notice to proceed, which was given on August 29, 1966.

The major expense in performing the contract was to be the procurement and placing of riprap. The bidders on the contract were advised with respect to quarry areas from which rock could be obtained:

A quarry area, with suitable rock outcropping on the stream bank, has been located approximately 2500 feet downstream from the dam. A haul road will have to be constructed, either down the stream bed or along the left bank. The quarry area is shown on the vicinity map.
The Contractor may, at his option, select a quarry different from the site shown on the drawings. In this event, the Contractor shall pay the costs of all tests required to verify the suitability of the rock for this project.

Northern first discovered boulders in the stream bed which would be more economical than the designated quarry and received permission to use this source. According to Northern, approximately 20 percent of the contract requirements were fulfilled before Northern exhausted the supply located in the stream bed. Then in the first week of September, Northern moved to the designated quarry site and commenced shooting rock. On September 19, 1966, Northern wrote to Chugach informing them that the rock in the designated quarry was unusable, but was directed in a letter the following day from Chugach’s engineering firm to proceed with further blasting and exploration of the designated areas. By September 27, however, Chu-gach conceded that suitable rock was not available at the designated site and reformed the agreement accordingly.

Alternate quarry sites were found at the opposite end of the lake from the dam. As a result of negotiations, Chugach wrote to Northern on September 27, 1966 authorizing completion of the contract by use of these alternate quarry sites. The authorization provided for amendments to reflect the circumstance that suitable rock was not available in the stream bed for mining, nor in the quarry which had been designated in the original contract documents. Paragraph 3 of the letter of authorization specified :

Rock will be quarried in suitable sizes and quantities to complete the project and will be stockpiled in or near the quarry, or quarries, mentioned above for transport across Cooper Lake to the dam site when such lake is frozen to a sufficient depth to permit heavy vehicle traffic thereon.”

The contract price was increased by $42,000. Subsequently, the contract was formally amended in accordance with the September 27, 1966 authorization. Work commenced in the new quarry in October 1966; and within about 30 days, all of the required rock was drilled and shot.

Although there is some question as to who first suggested it or how it came about, it was the agreement of the parties that the rock from the new quarry site would be transported in winter across the ice of Cooper Lake. In December 1966, Northern cleared a road on the ice to permit deeper freezing of the ice. By the time the ice was thought to be sufficiently thick to begin hauling, however, a water overflow on the ice one to two feet in depth prohibited crossings by the trucks. Northern complained to Chugach of unsafe conditions on the lake ice, but Chugach insisted on performance. In March 1967, one of Northern’s Euclid loaders went through the ice and sank, and a small crawler tractor subsequently broke through but was recovered. Neither incident involved loss of life. Despite these occurrences, Chugach and its engineering firm continued to insist on performance, threatening default. On March 27, 1967, Chu-gach again threatened to consider North- *79 era in default unless they immediately commenced hauling operations. Northern attempted to commence operations but continued to meet with difficulties, finally ceasing operations on March 31, 1967, apparently with the approval of Chugach.

On January 8, 1968, Chugach advised Northern that it would consider Northern in default unless all rock was hauled by April 1, 1968. On January 20, Northern informed Chugach that they were returning to Cooper Lake, and wrote on January 30 that they anticipated favorable conditions to start hauling rock on January 31. The ice conditions were apparently different from those encountered in 1967 — there was very little snow cover and no overflow problem. The ice varied from 23½ inches to 30 inches thick, and for several days the temperature had been 30 degrees below zero and clear.

On February 1, 1968, Northern started hauling with half-loaded trucks; but within the first few hours, two trucks with their drivers broke through the ice, resulting in the death of the drivers and loss of the trucks. Northern at this point ceased operations; and on February 16, 1968, informed Chugach that it would make no more attempts to haul rock across the lake. On March 28, 1968, Northern advised Chu-gach that it considered the contract terminated for impossibility of performance.

Northern commenced legal action against Chugach in September 1968, seeking recovery for costs incurred in attempted completion of the contract less revenues received. The case was tried in superior court without a jury in December 1971. Northern contended that in the original contract there were express and implied warranties that the designated quarry contained sufficient quantities of suitable rock for the job, and that breach of the warranties entitled Northern to damages. In the alternative, Northern argued that the modified contract was impossible of performance, justifying an award to Northern of reasonable costs incurred in attempted performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alcan Forest Products, LP v. A-1 Timber Consultants, Inc.
982 F. Supp. 2d 1016 (D. Alaska, 2013)
7200 Scottsdale Road General Partners v. Kuhn Farm MacHinery, Inc.
909 P.2d 408 (Court of Appeals of Arizona, 1995)
Golsen v. ONG Western, Inc.
756 P.2d 1209 (Supreme Court of Oklahoma, 1988)
United States Smelting, Refining & Mining Co. v. Wigger
684 P.2d 850 (Alaska Supreme Court, 1984)
Murray E. Gildersleeve Logging Co. v. Northern Timber Corp.
670 P.2d 372 (Alaska Supreme Court, 1983)
Mat-Su/Blackard/Stephan & Sons v. State
647 P.2d 1101 (Alaska Supreme Court, 1982)
Florida Power & Light Co. v. Westinghouse Electric Corp.
517 F. Supp. 440 (E.D. Virginia, 1981)
Matter of Westinghouse Elec. Corp., Etc.
517 F. Supp. 440 (E.D. Virginia, 1981)
Martin v. Maldonado
572 P.2d 763 (Alaska Supreme Court, 1977)
Chugach Electric Ass'n v. Northern Corp.
562 P.2d 1053 (Alaska Supreme Court, 1977)
Northern Corporation v. Chugach Electric Ass'n
20 Cont. Cas. Fed. 83,203 (Alaska Supreme Court, 1974)
City of Valdez v. Valdez Development Company
523 P.2d 177 (Alaska Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
518 P.2d 76, 1974 Alas. LEXIS 373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-corporation-v-chugach-electric-assn-alaska-1974.