Northeastern Rural Electric Membership Corp. v. Wabash Valley Power Ass'n

707 F.3d 883, 2013 U.S. App. LEXIS 3692, 2013 WL 646051
CourtCourt of Appeals for the Seventh Circuit
DecidedFebruary 22, 2013
Docket12-2037
StatusPublished
Cited by86 cases

This text of 707 F.3d 883 (Northeastern Rural Electric Membership Corp. v. Wabash Valley Power Ass'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northeastern Rural Electric Membership Corp. v. Wabash Valley Power Ass'n, 707 F.3d 883, 2013 U.S. App. LEXIS 3692, 2013 WL 646051 (7th Cir. 2013).

Opinion

HAMILTON, Circuit Judge.

This appeal tests the boundaries of federal-question subject matter jurisdiction. The issue is whether a claim for breach of a long-term requirements contract for wholesale electricity arises under federal law or state law. We conclude that the claim arises under state law, that the district court therefore lacked jurisdiction to enter its preliminary injunction, and that the case should be remanded to state court.

Defendant Wabash Valley Power Association, Inc. (Wabash Valley) is a not-for-profit power generation cooperative. Plaintiff Northeastern Rural Electric Membership Corporation (Northeastern) is a member of Wabash Valley that purchases electricity from Wabash Valley and resells it to consumers. In 1977, Northeastern and Wabash Valley entered into a wholesale power supply contract under which Northeastern agreed to purchase all of its electric power from Wabash Valley for the next forty years. The contract provided that Northeastern would pay for the electricity at rates to be set by the Wabash Valley board of directors “[s]ub-ject to the approval of the Public Service Commission of Indiana,” though the key contractual provision also stated that revised rates would not be effective unless approved by the ambiguously phrased “applicable regulatory authorities,” as well as the administrator of the federal Rural Electrification Administration.

*886 On January 5, 2012, Northeastern filed this suit in Indiana state court seeking a declaratory judgment that Wabash Valley materially breached the 1977 contract by taking action in 2004 that had the effect of transferring regulation of its rates from the Indiana Commission to the Federal Energy Regulatory Commission (FERC). 1 Northeastern contends that the “applicable regulatory authorities” in the 1977 contract are limited to the Indiana Commission, while Wabash Valley believes that the contract language is flexible enough to permit rate regulation by either regulatory body.

Wabash Valley removed the case to federal court under 28 U.S.C. § 1441(a) on the theory that the claim for breach of contract necessarily arises under the Federal Power Act (FPA), 16 U.S.C. §§ 791a et seq. Northeastern moved to remand to state court while Wabash Valley moved for a preliminary injunction to prevent Northeastern from ceasing performance under the contract. The district court denied Northeastern’s • motion for remand and granted Wabash Valley’s motion for a preliminary injunction, agreeing with Wabash Valley that federal jurisdiction exists because Northeastern’s suit is “a collateral attack on the FERC-filed rate,” and thus raises a question of federal law. Northeastern has appealed both rulings, arguing that the suit does not attack a filed rate.

We have appellate jurisdiction to consider the preliminary injunction under 28 U.S.C. § 1292(a)(1). The appeal of the district court’s denial of remand also fits within the narrow doctrine of pendent appellate jurisdiction because the preliminary injunction appeal presents precisely the same question of subject matter jurisdiction as the motion to remand. The denial of a motion to remand ordinarily cannot be appealed, see 28 U.S.C. § 1447(d), but here the denial of remand is “inextricably intertwined” with the appeal-able preliminary injunction. See, e.g., Research Automation, Inc. v. Schrader-Bridgeport Int’l, Inc., 626 F.3d 973, 977 (7th Cir.2010) (exercising pendent appellate jurisdiction over non-appealable transfer order that presented same issue as appealable denial of injunction to block litigation in transferee district); cf. Abelesz v. Magyar Nemzeti Bank, 692 F.3d 661, 669 (7th Cir.2012) (holding that appellate jurisdiction over denial of motion to dismiss based on foreign sovereign immunity defense did not support pendent appellate jurisdiction over rejection of separate statute of limitations defense).

Turning to the merits of the appeal, we agree with Northeastern and conclude that the federal courts lack subject matter jurisdiction over this case. Northeastern’s claim is limited to a construction of the parties’ rights under the 1977 contract and does not necessarily raise a question of federal law. To prove its claim, Northeastern needs to show only that it had a valid contract and that Wabash Valley’s voluntary action to transfer regulatory jurisdiction from the Indiana Commission to FERC breached the contract. Neither of these elements necessarily raises a question of federal law. While Northeastern may eventually attempt to use a favorable state court judgment to seek FERC’s permission to terminate its obligations under the tariff filed with FERC, Northeastern agrees that such relief cannot be achieved in this suit. If Northeastern prevails on the merits of its claim, it will then need to seek that relief directly from FERC. Northeastern has therefore pled a claim that does *887 not arise under federal law. We vacate the preliminary injunction and order remand of this action to state court.

I. Regulatory, Factual, and Procedural Background

A. Wholesale Electrical Power Regulation

Regulation of the electricity market is divided between federal and state regulators. In general, the federal government through FERC regulates the interstate wholesale electricity market, while the states regulate the retail sale of this power to consumers.

FERC regulates the sale of wholesale electricity through rate regulation. Under the Federal Power Act, public utilities under FERC jurisdiction may charge only “just and reasonable” rates. 16 U.S.C. § 824d(a). The Act grants FERC the exclusive authority to enforce this provision by regulating the rates, terms, and conditions governing the interstate transmission and sale of wholesale energy in interstate commerce. See Mississippi Power & Light Co. v. Mississippi ex rel. Moore, 487 U.S. 354, 371, 108 S.Ct. 2428, 101 L.Ed.2d 322 (1988). In practice, FERC enforces this statutory provision through tariff filing. Public utilities regulated by FERC are required to file tariffs that detail rates and terms of service. 16 U.S.C. § 824d(c); 18 C.F.R. § 35.1(a). The basis for the filed tariff is often a contract negotiated privately between wholesaler and distributor that is then submitted to FERC. FERC will then accept the contract as the basis for the rate as long as the terms are “just and reasonable” and not discriminatory.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
707 F.3d 883, 2013 U.S. App. LEXIS 3692, 2013 WL 646051, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northeastern-rural-electric-membership-corp-v-wabash-valley-power-assn-ca7-2013.