North Central Construction, Inc. v. Siouxland Energy & Livestock Cooperative

232 F. Supp. 2d 959, 2002 U.S. Dist. LEXIS 22175, 2002 WL 31553317
CourtDistrict Court, N.D. Iowa
DecidedNovember 12, 2002
DocketC02-4041-MWB
StatusPublished
Cited by1 cases

This text of 232 F. Supp. 2d 959 (North Central Construction, Inc. v. Siouxland Energy & Livestock Cooperative) is published on Counsel Stack Legal Research, covering District Court, N.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Central Construction, Inc. v. Siouxland Energy & Livestock Cooperative, 232 F. Supp. 2d 959, 2002 U.S. Dist. LEXIS 22175, 2002 WL 31553317 (N.D. Iowa 2002).

Opinion

MEMORANDUM OPINION AND ORDER REGARDING PLAINTIFF’S MOTION TO COMPEL ARBITRATION AND STAY PROCEEDINGS PENDING ARBITRATION

BENNETT, Chief Judge.

TABLE OF CONTENTS

I. INTRODUCTION AND PROCEDURAL BACKGROUND Gi

A. The Parties, The Arbitration Clauses, And The Underlying Disputes 05

B. Procedural Background . Gi

II. LEGAL ANALYSIS. Co G5 bo

A. North Central’s Motion to Compel Arbitration and Stay Proceedings 0 O to

B. Waiver. íü G5 CO

1. Inconsistent action (D Gl ^

2. Prejudice. ío Gi OD

C. Conclusion. CD Gi CO

/. INTRODUCTION AND PROCEDURAL BACKGROUND

A. The Parties, The Arbitration Clauses, And The Underlying Disputes

The plaintiff North Central Construction, Inc. (“North Central”), is a North Dakota corporation maintaining its principal place of business in Fargo, North Dakota. Def.’s Answer and Counterclaim, at Ex. A. The defendant Siouxland Energy and Livestock Cooperative (“Siouxland”), is a cooperative organized under the laws of the state of Iowa and maintains its principal place of business in Sioux Center, Iowa. Def.’s Answer and Counterclaim. North Central is engaged in the construction business and subsequently entered into a written contract on December 28, 2000 with Siouxland to build the Siouxland Ethanol Facility (“The Facility”) in Sioux Center, Iowa. Pl.’s Reply to Def.’s Answer and Counterclaim, at (# 6). In return for North Central’s construction of the Ethanol Facility, Siouxland agreed to compensate North Central in the amount of $7,648,000. Def.’s Answer and Counterclaim, at Ex. A.

Several documents comprise the written contract between the parties. In particular, the parties direct the court’s attention to the -document entitled the “General Conditions of the Construction Contract” identified as Construction Management Association of America (CMAA) Document A-3. Def.’s Answer and Counterclaim, at Ex. A. According to Article 14.1.1 of the General Conditions, North Central and Siouxland were to initially address any unresolved disputes arising out of or relating to the contract through mediation in Des Moines, Iowa, before instituting against the other party a demand for arbitration “unless delay in initiating or prosecuting a proceeding in an arbitration or judicial forum would prejudice the Owner or Contractor.” Def.’s Answer and Counterclaim, at Ex. A, 57. Further, Article 14.1.2 provides that “All unresolved disputes relating to this Contract or the *961 breach thereof (“disputes”) shall be decided by arbitration in Des Moines, Iowa.” Additionally, the contract grants the owner and contractor with the power to select an arbitrator(s) and to determine the rules and procedures that will govern the arbitration. However, if the owner and contractor are unable to reach an agreement regarding the format of the arbitration, the contract identified the American Arbitration Association as the association providing the then current “Construction Industry Rules” to govern the arbitration proceeding. Def.’s Answer and Counterclaim, at Ex. A, 58.

Disputes regarding the performance of the contract apparently erupted causing North Central to file a mechanic’s lien, which it perfected on May 6, 2002 by filing an amended mechanic’s lien.

B. Procedural Background

On May 17, 2002 North Central filed a petition in Iowa District Court to foreclose its perfected mechanic’s lien in the amount of $2,708,293. In its petition, North Central alleged that it “performed all labor and furnished materials as provided in the contract,” both having been actually used in the construction of The Facility. PL’s Pet., at 1. Furthermore, North Central’s petition asserted that it had performed all of the conditions of the contract within the specified time. PL’s Pet., at 1. In response to North Central’s attempt to foreclose on its mechanic’s lien, Siouxland filed a Notice of Removal on June 12, 2002 and the case was subsequently assigned to Chief Judge Mark Bennett, United States District Court for the Northern District of Iowa (# 4). In its notice of removal, Siouxland admitted that aside from North Central’s filing its petition, no further proceedings took place in Iowa District Court.

On June 14, 2002, Siouxland answered North Central’s petition and counterclaimed against North Central, alleging in Count I that North Central failed to perform its obligations under the contract and was in breach. Consequently, Siouxland seeks compensatory damages for the costs of design alterations it undertook, as well as for repairs and replacement costs it incurred to cure North Central’s defective work and equipment. In addition, Sioux-land seeks consequential and incidental damages and requests that punitive damages be awarded.

Instead of moving to compel arbitration and stay ’proceedings, on June 24, 2002 North Central answered Siouxland’s counterclaim but failed to assert affirmative defenses. However, on July 10, 2002 North Central amended its answer to include six affirmative defenses, the first of which alleged that Siouxland’s counterclaim for breach is governed by the arbitration agreement between the partie§. PL’s Am. Reply to Counterclaim, at 2. According to the record, Siouxland next filed a motion to consolidate the present action and Siouxland’s lawsuit against Michael Gaylor and Gaylor Engineering, No. 02-4033, filed on August 19, 2002. North Central filed its resistance to Siouxland’s motion on September 5, 2002. However, Siouxland’s motion to consolidate is not presently before the court, thus the court will not address its merits.

Alongside filing its resistance to Sioux-land’s motion to consolidate, North Central filed a motion to compel arbitration and stay proceedings. North Central maintains that under the agreement, Siouxland is precluded from pursuing its claim in court and must instead submit its claim to arbitration. North Central asserts that the Federal Arbitration Act (“FAA”) applies to this action and requests that this court stay proceedings pursuant to 9 U.S.C. §§ 3-4, which state in pertinent part that “[a] party aggrieved by the alleged failure of another to arbitrate under *962 a written agreement for arbitration may-petition any United States district court for an order directing that such arbitration proceed in the manner provided for in such agreement ...9 U.S.C. § 4, and that a court “upon being satisfied that the issue involved in [a] suit or proceeding is referable to arbitration under [an] agreement [between the parties], shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement.” 9 U.S.C. § 3.

Siouxland filed its resistance to North Central’s motion on September 26, 2002.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
232 F. Supp. 2d 959, 2002 U.S. Dist. LEXIS 22175, 2002 WL 31553317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-central-construction-inc-v-siouxland-energy-livestock-iand-2002.