Nez Perce Tribe v. Idaho Power Co.

847 F. Supp. 791, 1994 U.S. Dist. LEXIS 3622, 1994 WL 96501
CourtDistrict Court, D. Idaho
DecidedMarch 21, 1994
DocketCiv. No. 91-0517-S-HLR
StatusPublished
Cited by16 cases

This text of 847 F. Supp. 791 (Nez Perce Tribe v. Idaho Power Co.) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nez Perce Tribe v. Idaho Power Co., 847 F. Supp. 791, 1994 U.S. Dist. LEXIS 3622, 1994 WL 96501 (D. Idaho 1994).

Opinion

ORDER ADOPTING FIRST REPORT AND RECOMMENDATION

RYAN, Senior District Judge.

I. INTRODUCTION

On July 30,1993, United States Magistrate Judge Larry M. Boyle entered his Report and Recommendation in the above-entitled action, attached hereto as Exhibit A. In his Report and Recommendation, Judge Boyle recommends that this court grant the defendant’s Motion for Summary Judgment as to all claims set forth in the plaintiff’s Amended Complaint.

Pursuant to 28 U.S.C. § 636(b)(1), the parties had ten days in which to file written objections to the recommendations of Judge Boyle. The court granted the plaintiff an extension of time to file its objections, pursuant to a stipulation entered into by the parties. On August 13, 1993, the plaintiff filed its objections to the Report and Recommendation. Thereafter, on August 30, 1993, the defendant filed its response to the objections.

[793]*793 II. DISCUSSION

In light of the objections filed by the plaintiff, the court is required to engage in a de novo review pursuant to 28 U.S.C. § 636(b)(1). The court has engaged in an exhaustive and detailed review of the entire record in this matter, including all of the memoranda, affidavits, and exhibits filed by the parties in relation to the Motion for Summary Judgment, as well as the plaintiffs objections to the Report and Recommendation and the defendant’s response. The court has also reviewed the eases cited by the parties in their memoranda and by Judge Boyle in his Report and Recommendation. Having conducted this thorough and independent review of the record, in light of the facts presented in this case and the substantive law applicable thereto, this court finds that Judge Boyle did not err when he concluded that the defendant’s Motion for Summary Judgment should be granted.

In its objections, the plaintiff does not offer the court any new authority which would cause it to reverse or modify the Report and Recommendation of Judge Boyle. Nor does the plaintiff offer any new evidence in support of its contentions. The plaintiff simply restates the arguments made to Judge Boyle which he carefully considered and rejected.

With respect to the Motion for Summary Judgment, the court notes that its findings are based upon a careful review of the facts, which has been conducted with the principle in mind that the facts are to be viewed in the light most favorable to the plaintiff as the nonmoving party. In summary, the court is simply not persuaded that the Report and Recommendation entered by Judge Boyle on July 30,1993, warrants modification. On the contrary, the court commends Judge Boyle for his erudite and well-reasoned decision which is well founded in both law and fact. The court finds it unnecessary to explain to the plaintiff again the reasons why it may not recover money damages from this defendant for diminished salmon runs. Rather, the court hereby incorporates the findings, reasoning, and conclusions of Judge Boyle by reference in this order.

The court notes that in the Report and Recommendation entered July 30, 1993, Judge Boyle appropriately did not address the plaintiffs claim for damages for inundation of usual and accustomed fishing places. The conversion claims were apparently raised for the first time at oral argument and were not clearly pleaded in the Amended Complaint. After consideration, this court again referred the defendant’s Motion for Summary Judgment to Judge Boyle for an additional hearing and the preparation of a supplemental report and recommendation on this narrow issue.

In light of these developments, the court will grant the defendant’s Motion for Summary Judgment as to all claims and issues, and on all grounds addressed by Judge Boyle in his Report and Recommendation entered July 30, 1993. The court will deny the motion without prejudice as to the plaintiffs final remaining claim for compensation based on exclusion from its usual and accustomed fishing places. The court will delay entering its final ruling on this last claim until after all objections and responses to objections have been filed with respect to the Second Report and Recommendation entered by Judge Boyle on February 28, 1994.

III. ORDER

Based on the foregoing and the court being fully advised in the premises,

IT IS HEREBY ORDERED that the findings, reasoning, and conclusions contained in the Report and Recommendation entered on July 30, 1993, should be, and are hereby, ADOPTED in their entirety and INCORPORATED herein by reference.

IT IS FURTHER ORDERED that defendant’s Motion for Summary Judgment, filed September 18, 1992, should be, and is hereby, GRANTED as to all claims set forth in the plaintiffs Amended Complaint except the plaintiffs claim for compensation based on exclusion from its usual and accustomed fishing places. The motion is DENIED WITHOUT PREJUDICE as to this remaining claim at this time. The court will enter its final ruling on this claim as explained above.

[794]*794EXHIBIT A

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO

NEZ PERCE TRIBE,

Plaintiff,

v.

IDAHO POWER COMPANY,

Defendant.

Case No. CV 91-0517-S-HLR

REPORT AND RECOMMENDATION

BOYLE, United States Magistrate Judge.

I.

INTRODUCTION

The Nez Perce Indian Tribe (hereinafter the “Tribe”) brought this action seeking an award of monetary damages from Idaho Power Company for the negative effect the power company’s construction and maintenance of three dams on the Snake River has had on the fall and spring chinook and steel-head runs. Idaho Power Company and/or its predecessors (hereinafter “Idaho Power”) began construction of the dams in 1955, when the Federal Power Commission issued it a license pursuant to the Federal Power Act (hereinafter “FPA”), 16 U.S.C. § 791a et seq. Pursuant to that license, the Hell’s Canyon dam, the Oxbow dam and the Brownlee dam (hereinafter the “Hell’s Dam Complex”) were constructed during the mid 1950’s and early 1960’s.

The Tribe bases its claims on the terms of the 1855 treaty with the United States which reserved to the Tribe exclusive rights to take fish in streams “where running through or bordering” its reservation, as well as “the right of taking fish at all usual and accustomed places in common with citizens of the Territory.” Art. Ill, Treaty with the Nez Perce, 12 Stat. 957 (June 11, 1855) (hereinafter the “treaty”).

The Tribe alleges that the manner in which Idaho Power has constructed and operated the Hell’s Dam Complex violates its treaty fishing rights by reducing the number of fish on the annual runs and claims it is entitled to compensation for that loss in the form of monetary damages.1 Idaho Power denies that it constructed or operated the Hell’s Dam Complex in a negligent manner or that it has violated FPA regulations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skokomish Indian Tribe v. Goldmark
994 F. Supp. 2d 1168 (W.D. Washington, 2014)
PPL MONTANA, LLC v. State
2010 MT 64 (Montana Supreme Court, 2010)
United States v. Nicholson
Ninth Circuit, 2009
United States v. Milner
583 F.3d 1174 (Ninth Circuit, 2009)
Metcalf v. Coquille Indian Tribal Council
9 Am. Tribal Law 1 (Coquille Indian Tribal Court, 2009)
Skokomish Indian Tribe, a Federally Recognized Indian Tribe in Its Own Capacity as a Class Representative and as Parens Patriae Denny S. Hurtado Gordon A. James Joseph Pavel Anne Pavel Maures P. Tinaza Celeste F. Vigil Roslynne L. Reed Gary W. Peterson Rita C. Andrews Tom G. Strong Marie E. Gouley Victoria J. Pavel Dennis W. Allen Joseph Andrews, Sr. Zetha Cush Elsie M. Allen Alex L. Gouley, Jr. Lawrence L. Kenyon Doris Miller Gerald B. Miller Helen M. Rudy Ronald D. Twiddy, Sr. Nick G. Wilbur, Sr. v. United States of America Tacoma Public Utilities, a Washington Municipal Corporation City of Tacoma, a Washington Municipal Corporation William Barker, Tacoma Public Utilities Board Member in His Official Capacity Tom Hilyard, Tacoma Public Utilities Board Member in His Official Capacity Robert Lane Tim Strege G.E. Vaughn, Skokomish Indian Tribe, a Federally Recognized Indian Tribe in Its Own Capacity as a Class Representative and as Parens Patriae Denny S. Hurtado Gordon A. James Joseph Pavel Anne Pavel Maures P. Tinaza Celeste F. Vigil Roslynne L. Reed Gary W. Peterson Rita C. Andrews Tom G. Strong Marie E. Gouley Victoria J. Pavel Dennis W. Allen Joseph Andrews, Sr. Zetha Cush Elsie M. Allen Alex L. Gouley, Jr. Lawrence L. Kenyon Doris Miller Gerald B. Miller Helen M. Rudy Ronald D. Twiddy, Sr. Nick G. Wilbur, Sr., Skokomish Indian Tribal Members for Themselves and All Others Similarly Situated v. Tacoma Public Utilities, a Washington Municipal Corporation City of Tacoma, a Washington Municipal Corporation William Barker, Tacoma Public Utilities Board Member in His Official Capacity Tom Hilyard, Tacoma Public Utilities Board Member in His Official Capacity Robert Lane Tim Strege G.E. Vaughn United States Internal Revenue Service
401 F.3d 979 (Ninth Circuit, 2005)
Skokomish Indian v. Tacoma Public Utilities
401 F.3d 979 (Ninth Circuit, 2005)
United States v. Southern California Edison Co.
300 F. Supp. 2d 964 (E.D. California, 2004)
Menominee Indian Tribe of Wisconsin v. Thompson