Nexus Gas Transmission v. City of Green, Ohio

Court of Appeals for the Sixth Circuit·Decided December 7, 2018·No. 18-3325·Unpublished

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 18a0613n.06

No. 18-3325

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT

NEXUS GAS TRANSMISSION, LLC, )

) FILED Plaintiff-Appellee, ) Dec 07, 2018 ) DEBORAH S. HUNT, Clerk v. )

) ON APPEAL FROM THE CITY OF GREEN, OHIO, ) UNITED STATES DISTRICT ) COURT FOR THE NORTHERN Defendant, ) DISTRICT OF OHIO )

JUDY JANE HAMRICK; JOHN SELZER; ELAINE ) OPINION SELZER, )

)

Defendants-Appellants. )

BEFORE: NORRIS, STRANCH, and LARSEN, Circuit Judges JANE B. STRANCH, Circuit Judge. Ohio landowners John Selzer, Elaine Selzer, and Judy Jane Hamrick (Landowners) have been in a longstanding dispute with Nexus Gas Transmission, LLC (Nexus) regarding Nexus’s right to use a 1.4-acre tract of land on Landowners’ property to build part of an interstate natural gas pipeline. During the first stage of this dispute, the Federal Energy Regulatory Commission (FERC) gave Nexus the authority to condemn private tracts of land along the pipeline’s route, including Landowners’ property. Nexus then obtained a preliminary injunction in the district court requiring Landowners to give Nexus immediate access to their property. In this appeal, Landowners argue that (1) the district court erred in issuing that injunction and (2) the court should not have issued the injunction without

first allowing further discovery and holding an evidentiary hearing. Though we acknowledge Landowners’ concern for the property rights at stake in this litigation, we find no basis for vacating the district court’s injunction. Because the district court properly considered the relevant factors and no additional discovery or evidentiary hearing was necessary, we AFFIRM.

I. BACKGROUND

In November 2015, Nexus asked FERC for authorization to build an interstate natural gas pipeline cutting across parts of Ohio and Michigan. FERC began lengthy notice-and-comment proceedings in response to Nexus’s application. Almost two years later, FERC issued a certificate of public convenience and necessity giving Nexus permission to build and operate the pipeline.

Although Nexus soon negotiated voluntary easements on 97% of the 2,070 tracts of land that lay in the path of the pipeline, several dozen owners of land—including Landowners—refused to grant easements. Under the Natural Gas Act (NGA), if a company with a FERC certificate in hand cannot reach voluntary agreement on the terms of an easement with an affected landowner, then the company may acquire the landowner’s property “by the exercise of the right of eminent domain in the district court . . . in which such property may be located.” 15 U.S.C. § 717f(h). Nexus accordingly filed suit in the district court seeking to condemn the remaining landowners’ properties under the NGA. Owners of the remaining properties later settled or provided immediate access, with the exception of Landowners.

In December 2017, the district court granted partial summary judgment in favor of Nexus, finding (among other things)1 that Nexus had established its statutory right to condemn Landowners’ property under the NGA. But Nexus and Landowners still could not agree on the compensation owed to Landowners for the easement. In March 2018, Nexus filed a motion requesting immediate access to Landowners’ property to start construction while the parties negotiated the terms of the easement. Nexus attached an affidavit submitted by Lawrence D. Smore, the Senior Project Manager of Nexus, stating that the disputed 1.4-acre tract on Landowners’ property was an integral part of Nexus’s construction plan, that building around Landowners’ property would cause significant delays, that Nexus would have to spend as much as $800,000 per day to retain its construction crew during those delays, and that circumventing the property would cost Nexus around $553,000 in additional construction costs.

Although the district court initially scheduled an evidentiary hearing, the court later canceled that hearing and discovery in a written order. The court stated: “At this stage, the Court sees no cause to schedule an evidentiary hearing or argument. . . . No further discovery shall be conducted on the motion absent leave from the undersigned.” On April 5, 2018, the district court granted Nexus’s motion and ordered Landowners to give Nexus immediate access to the property. The court also ordered Nexus to post a bond of $100,000 pending calculation of the proper compensation owed to Landowners.

1 The district court’s December 2017 order also gave Nexus the right of immediate access to Landowners’ property for the narrow purpose of conducting certain surveys, tree felling, clearing, and environmental and utility work. Landowners appealed that injunction, but we granted Nexus’s motion to dismiss the appeal on mootness grounds because Nexus had already completed those preliminary tasks by the time Landowners’ appeal had reached this court. See Nexus Gas Transmission, LLC v. City of Green, No. 18- 3113, 2018 WL 2072606 (6th Cir. Apr. 3, 2018). Nexus has not similarly moved to dismiss on mootness grounds in this appeal, so we assume that Nexus remains on the property.

In this appeal, Landowners argue that the district court (1) erred in issuing the April 5 preliminary injunction order and (2) should not have issued that order without first allowing additional discovery and holding an evidentiary hearing.2 II. ANALYSIS

A. Preliminary Injunction Order We review a district court’s decision to grant a preliminary injunction for abuse of discretion. McGirr v. Rehme, 891 F.3d 603, 610 (6th Cir. 2018). We will not disturb that decision unless it “relied upon clearly erroneous findings of fact, improperly applied the governing law, or used an erroneous legal standard.” Hunter v. Hamilton Cty. Bd. of Elections, 635 F.3d 219, 233 (6th Cir. 2011) (citation omitted).

District courts weigh four factors when deciding whether to grant a preliminary injunction:

“(1) whether the movant has a strong likelihood of success on the merits; (2) whether the movant would suffer irreparable injury absent the injunction; (3) whether the injunction would cause substantial harm to others; and (4) whether the public interest would be served by the issuance of

Free access — add to your briefcase to read the full text and ask questions with AI

Nexus Gas Transmission v. City of Green, Ohio, (6th Cir. 2018).

Nexus Gas Transmission v. City of Green, Ohio (Nexus Gas Transmission v. City of Green, Ohio) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Weinberger v. Romero-Barcelo
456 U.S. 305 (Supreme Court, 1982)
Hunter v. Hamilton County Board of Elections
635 F.3d 219 (Sixth Circuit, 2011)
Doe v. Sundquist
106 F.3d 702 (Sixth Circuit, 1997)
Jones v. Caruso
569 F.3d 258 (Sixth Circuit, 2009)
Langley v. Prudential Mortg. Capital Co., LLC
554 F.3d 647 (Sixth Circuit, 2009)
Armstrong v. Exceptional Child Center, Inc.
575 U.S. 320 (Supreme Court, 2015)
Hall v. Edgewood Partners Insurance Center, Inc.
878 F.3d 524 (Sixth Circuit, 2017)
Rebecca Cooper v. Honeywell Int'l, Inc.
884 F.3d 612 (Sixth Circuit, 2018)
East Tennessee Natural Gas Co. v. Sage
361 F.3d 808 (Fourth Circuit, 2004)
McGirr v. Rehme
891 F.3d 603 (Sixth Circuit, 2018)