Transwestern Pipeline Co. v. 17.19 Acres of Property Located in Maricopa County

550 F.3d 770, 2008 U.S. App. LEXIS 24968, 2008 WL 5173111
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 11, 2008
Docket08-15991
StatusPublished
Cited by26 cases

This text of 550 F.3d 770 (Transwestern Pipeline Co. v. 17.19 Acres of Property Located in Maricopa County) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transwestern Pipeline Co. v. 17.19 Acres of Property Located in Maricopa County, 550 F.3d 770, 2008 U.S. App. LEXIS 24968, 2008 WL 5173111 (9th Cir. 2008).

Opinion

HALL, Senior Circuit Judge:

Transwestern Pipeline Co. (Transwest-ern) appeals the district court’s denial of its preliminary injunction motion seeking immediate possession of appellee landowners’ parcels of land. As a holder of a valid Federal Energy Regulatory Commission (FERC) certificate, Transwestern claims it is entitled to condemn appellees’ land pursuant to § 717f(h) of the Natural Gas Act (NGA). The district court denied the injunction, holding that, until condemnation proceedings are completed, Tran-swestern maintains no substantive right of possession and therefore the district court lacked authority to grant preliminary equitable relief. The district court had jurisdiction pursuant to 15 U.S.C. § 717f(h) and 28 U.S.C. § 1331. We have jurisdiction pursuant to 28 U.S.C. § 1292(a)(1). We affirm and hold that, until an order of condemnation issues pursuant to the requirements of 15 U.S.C. § 717f(h), Tran-swestern has no substantive right of possession.

I. Background

Transwestern owns and operates natural gas pipelines serving much of the Southwest. Following the review of its application and completion of public hearings, the Federal Energy Regulatory Commission (FERC) issued a Certificate of Public Convenience and Necessity (the Certificate) approving Transwestern’s proposed construction and expansion of a natural gas pipeline to meet the demands of a growing Phoenix market. The Certificate provided that Transwestern was to complete the construction within one year of issuance, or by November 15, 2008. 1

Several property owners affected by the Certificate, most prominently the Town of Buckeye, Arizona, opposed the Certifi *773 cate’s issuance and filed a petition for rehearing of the Certificate with FERC. The petition alleged insufficient process in approving the Certificate and requested that the proposed pipeline route bypass a number of master planned communities. FERC denied the petition for rehearing, see 2008 WL 461054 (F.E.R.C.) and, pursuant to the process outlined by the Natural Gas Act (NGA), several petitioners appealed the denial to the D.C. Circuit. See 15 U.S.C. § 717r. These appeals have since been dismissed during the pendency of this appeal. See Town of Buckeye v. F.E.R.C., No. 08-1126 (D.C.Cir. filed June 27, 2008); El Paso Natural Gas Co. v. F.E.R.C., No. 08-1161 (D.C.Cir. filed Aug. 25, 2008). 2

Because neither the rehearing nor the appeal automatically stayed the Certificate’s enforcement, see § 717r(c), Tran-swestern continued to pursue its construction objectives throughout this time. Transwestern was able to reach an agreement on an easement price with most of the 897 affected landowners. With regard to the remaining 129 parcels, Tran-swestern filed condemnation actions in the district court of Arizona. The NGA authorizes FERC Certificate holders to acquire necessary land by the exercise of the right of eminent domain, after negotiations with affected landowners fail. § 717f(h). 3

After consolidating the actions, Tran-swestern sought a preliminary injunction to obtain immediate possession of the contested parcels. Transwestern claimed entitlement to relief under the court’s equitable powers and, specifically, Rule 65 of the Federal Rules of Civil Procedure. Tran-swestern argued that the FERC certificate and NGA § 717f(h) guaranteed its success on the merits, and it would suffer irreparable harm if it could not take possession immediately, citing construction delays and resulting expenses, the necessity of complying with the timeline provided by the Certificate, its desire to meet contractual forecasts with suppliers and customers, and the public interest in getting the pipeline in service before fall 2008. The landowners argued the Certificate was improperly granted and also contested the severity and nature of Transwestern’s harm. They argued primarily that any harm incurred by Transwestern was illusory and created by Transwestern’s own choice to prematurely enter contracts, and that Transwestern could easily obtain an extension of the FERC deadline.

Following a lengthy evidentiary hearing, the district court denied the preliminary injunction. Without reaching the parties’ factual contentions or balancing hardships, the district court held that it lacked au *774 thority to grant immediate possession under the terms of the NGA, and doing so would effectively grant Transwestern a substantive quick-take power not authorized by the statute.

During this appeal process, Transwest-ern was able to settle with all but one affected landowner, Agua Fria Investments, LLC, the remaining appellee in this action.

II. Standard of Review

“In general, we review the denial of a preliminary injunction for abuse of discretion. The district court, however, necessarily abuses it discretion when it bases its decision on an erroneous legal standard or on clearly erroneous findings of fact. When the district court is alleged to have relied on an erroneous legal premise, we review the underlying issues of law de novo.” Earth Island Inst. v. U.S. Forest Serv., 351 F.3d 1291, 1298 (9th Cir. 2003) (citations omitted). Here, the district court found that it lacked authority to grant the preliminary injunction. This appeal thus presents a legal question that we review de novo.

III. Discussion

A. Statutory Right to Possession Under NGA § 717f(h)

The usual process by which the government or another authorized party takes property for public use is through the straight condemnation proceeding. In straight condemnation actions, the government takes possession of the land following an order of condemnation and a trial determining just compensation. See 40 U.S.C. § 3113; Kirby Forest Ind., Inc. v. United States, 467 U.S. 1, 3-4, 104 S.Ct. 2187, 81 L.Ed.2d 1 (1984) (outlining different authority and procedures used by the government to condemn property).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C.F. Hughes v. UGI Storage Co.
Commonwealth Court of Pennsylvania, 2020
Mountain Valley Pipeline, LLC v. Simmons
307 F. Supp. 3d 506 (U.S. District Court, 2018)
Equitrans, L.P. v. 0.56 Acres More or Less of Permanent Easement
145 F. Supp. 3d 622 (N.D. West Virginia, 2015)
Moore v. Equitrans, L.P.
49 F. Supp. 3d 456 (N.D. West Virginia, 2014)
GSS, LLC v. Centerpoint Energy Gas Transmission Co.
2014 Ark. 144 (Supreme Court of Arkansas, 2014)
Alliance Pipeline L.P. v. 4.500 Acres of Land
911 F. Supp. 2d 805 (D. North Dakota, 2012)
Alliance Pipeline L.P. v. 2.679 Acres of Land
911 F. Supp. 2d 816 (D. North Dakota, 2012)
Alliance Pipeline L.P. v. 3.304 Acres of Land
911 F. Supp. 2d 826 (D. North Dakota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
550 F.3d 770, 2008 U.S. App. LEXIS 24968, 2008 WL 5173111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transwestern-pipeline-co-v-1719-acres-of-property-located-in-maricopa-ca9-2008.