Nebraska Builders Products Co. v. Industrial Erectors, Inc.

478 N.W.2d 257, 239 Neb. 744, 16 U.C.C. Rep. Serv. 2d (West) 568, 1992 Neb. LEXIS 4
CourtNebraska Supreme Court
DecidedJanuary 3, 1992
Docket89-368
StatusPublished
Cited by32 cases

This text of 478 N.W.2d 257 (Nebraska Builders Products Co. v. Industrial Erectors, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nebraska Builders Products Co. v. Industrial Erectors, Inc., 478 N.W.2d 257, 239 Neb. 744, 16 U.C.C. Rep. Serv. 2d (West) 568, 1992 Neb. LEXIS 4 (Neb. 1992).

Opinion

Hastings, C.J.

Appellant, Nebraska Builders Products Co. (Nebraska Builders), brought this action against the appellee, The Industrial Erectors, Inc. (Industrial), to recover the excess costs of substitute performance on an alleged purchase contract for cranes. Nebraska Builders appeals from a judgment of the trial court declaring that there was no enforceable contract between the parties but that, instead, the parties contemplated a written contract which was never executed. We reverse, and remand for further proceedings.

In reviewing a judgment in a bench trial of a law action, the Supreme Court does not reweigh the evidence but considers the evidence in the light most favorable to the successful party and resolves evidentiary conflicts in favor of the successful party, who is entitled to every reasonable inference deducible from the *747 evidence. Albee v. Maverick Media, Inc., ante p. 60, 474 N.W.2d 238 (1991). In a bench trial of a law action, a trial court’s factual findings have the effect of a verdict and will not be set aside unless clearly erroneous. Id. However, when such judgment is not supported by the evidence, it is clearly wrong and must be set aside. Hammond v. Streeter, 225 Neb. 491, 406 N.W.2d 633 (1987). Regarding a question of law, an appellate court has an obligation to reach a conclusion independent of that of the trial court in a judgment under review. Knox v. Cook, 233 Neb. 387, 446 N.W.2d 1 (1989).

The record reflects the following facts: In early 1985, the Omaha Public Power District (O.P.P.D.) invited bids for the construction of a service center near Elkhorn, Nebraska. William Hawkins, on behalf of Nebraska Builders, an Omaha-based company engaged in the business of selling construction products, obtained the plans and specifications which identified supplies, materials, and equipment to be used in the construction of the service center. Nebraska Builders intended to submit its bid as a subcontractor or material supplier to the companies bidding for the general contract for the construction of the service center later that year. Hawkins identified many items in the plans and specifications which Nebraska Builders could potentially supply for the project, including several types of crane systems. Previously, Nebraska Builders had purchased such cranes from Industrial. Industrial is a Chicago-based company which manufactures various types of cranes and also sells cranes manufactured by others.

Hawkins contacted Timothy Brennan, Industrial’s sales manager, in February 1985, to inquire if Industrial was interested in submitting a bid on the cranes. Brennan traveled to Omaha on February 28, 1985, to review the plans and specifications for the crane systems. Brennan obtained the information necessary to prepare a bid, including Section 11520 of the specifications — Material Handling and Associated Equipment. The specifications were very detailed, specifying manufacturer, model number, electrical requirements, capacity, speed, control system, and other performance characteristics. Variance in equipment had to be approved in writing by the project engineer pursuant to a procedure set forth in the *748 specifications. Both Brennan and Hawkins were aware of this procedure.

On March 12 or 13, 1985, Brennan telephoned Hawkins and told him that Industrial would sell and install the crane systems as per specifications for a total sum of $449,920, which consisted of $399,935 for materials and $49,985 for installation. Brennan stated that there were some minor exceptions to the specifications, but those could be worked out with the O.P.P.D. engineer. Nebraska Builders submitted a bid based, in part, on Industrial’s bid. On March 26,1985, Brennan confirmed the telephone conversation with a letter to Hawkins stating Industrial’s proposal.

By this letter, exhibit 14, Industrial “propose[d] to furnish all Crane Systems, Jib Cranes and Monorail Systems per Specification #11520 dated 2/26/85 including the three Addendums.” Then followed a detailed listing of the specific items which Industrial agreed to furnish at a total material cost of $399,935, plus $49,985 if Industrial was to install the listed equipment.

William Hawkins contacted Hawkins Construction Company (Hawkins Construction), the general contractor with the lowest bid, to see if Nebraska Builders was the low bidder on any of the items Hawkins Construction had bid on. This conversation led to a period of negotiations between Industrial and Nebraska Builders. During the negotiations, Nebraska Builders put together a “package bid” and gave Hawkins Construction a lump-sum price on several items, including the cranes. Nebraska Builders alleges that upon its request Industrial reduced its bid twice. Industrial disputes the second reduction and argues that the bid was only once reduced, by $4,500. However, exhibit 46 consists of a series of adding machine tapes including notations admittedly made by Brennan of Industrial. These tapes indicate a second reduction of $26,937, with additions of $2,400 for each interlock device. As testified to by Hawkins, there were four interlock devices, and this total reduction was therefore $17,337.

At the time Nebraska Builders submitted its package bid to Hawkins Construction, William Hawkins had reviewed Industrial’s proposal and knew that the items proposed were *749 different models made by different manufacturers than those called for in the specifications; however, the proposal stated that Industrial would furnish all crane systems as required by Section 11520 of O.P.P.D.’s specifications. Hawkins was also aware that any deviations needed specific approval. He was not concerned about the deviations, since O.P.P.D. was required to accept alternatives if they were of equal quality. Since Industrial was in the business of manufacturing and selling cranes and had stated that the proposal was per specifications and any deviations from the specifications were “minor,” Hawkins believed that the cranes set forth in Industrial’s proposal were of equal quality, and thus, approval of the deviations would not be a problem.

During early May, Hawkins was informed by Hawkins Construction that Nebraska Builders’ bid on the crane systems, as well as on various other items, was accepted. Hawkins testified that he immediately telephoned Industrial to accept Industrial’s offer. He does not remember whether he talked to Brennan or Jerry Cole, the president of Industrial. Brennan testified that he did not have that conversation with Hawkins. Cole did not testify at the trial.

Although Brennan denies his having the conversation in which Nebraska Builders accepted Industrial’s bid, Industrial and Nebraska Builders exchanged correspondence concerning the variance approval and exceptions to the specifications between May 31 and August 9, 1985. In a letter dated May 31, 1985, Brennan assured Nebraska Builders that Industrial had adhered to all of O.P.P.D.’s specifications in preparing its bid and that all equipment “will be equal to or better than” the equipment specified in the plans and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rinderknecht v. Luck
965 P.2d 564 (Court of Appeals of Utah, 1998)
State v. Karen D.
526 N.W.2d 439 (Nebraska Court of Appeals, 1994)
In Re Guardianship of Bloomquist
514 N.W.2d 656 (Nebraska Court of Appeals, 1994)
Newman v. Hinky Dinky Omaha-Lincoln, Inc.
512 N.W.2d 410 (Nebraska Court of Appeals, 1994)
Kopecky v. National Farms, Inc.
510 N.W.2d 41 (Nebraska Supreme Court, 1994)
Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)
Shkolnick v. American Family Mutual Insurance
506 N.W.2d 356 (Nebraska Court of Appeals, 1993)
T.O. Haas Tire Co. v. Futura Coatings, Inc.
507 N.W.2d 297 (Nebraska Court of Appeals, 1993)
ENTERPRISE CO., INC. v. Americom Corp.
510 N.W.2d 537 (Nebraska Court of Appeals, 1993)
State v. Owen
510 N.W.2d 503 (Nebraska Court of Appeals, 1993)
Warsocki v. City of Omaha
510 N.W.2d 446 (Nebraska Court of Appeals, 1993)
Petska v. Olson Gravel, Inc.
500 N.W.2d 828 (Nebraska Supreme Court, 1993)
State v. Hernandez
511 N.W.2d 535 (Nebraska Court of Appeals, 1993)
Clausen v. Columbia National Insurance
510 N.W.2d 399 (Nebraska Court of Appeals, 1993)
Milnes v. Jacobs
510 N.W.2d 395 (Nebraska Court of Appeals, 1993)
Gatewood v. Powell
511 N.W.2d 159 (Nebraska Court of Appeals, 1993)
State v. Barnett
511 N.W.2d 150 (Nebraska Court of Appeals, 1993)
Lewis v. Opstein
510 N.W.2d 382 (Nebraska Court of Appeals, 1993)
Fowler v. Lester Electric
501 N.W.2d 728 (Nebraska Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
478 N.W.2d 257, 239 Neb. 744, 16 U.C.C. Rep. Serv. 2d (West) 568, 1992 Neb. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nebraska-builders-products-co-v-industrial-erectors-inc-neb-1992.