Crane Co. v. Roberts Supply Co.

241 N.W.2d 516, 196 Neb. 67, 1976 Neb. LEXIS 743
CourtNebraska Supreme Court
DecidedMay 5, 1976
Docket40274
StatusPublished
Cited by9 cases

This text of 241 N.W.2d 516 (Crane Co. v. Roberts Supply Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crane Co. v. Roberts Supply Co., 241 N.W.2d 516, 196 Neb. 67, 1976 Neb. LEXIS 743 (Neb. 1976).

Opinion

White, C. J.

This is an action brought by the plaintiff, Crane Co. (hereinafter referred to as Crane), against the defendant, Roberts Supply Company (hereinafter referred to as Roberts), alleging that Roberts was indebted to Crane in the amount of $29,828.85, for termination charges on valves which were either completed or partially completed pursuant to two purchase orders placed by Roberts with Crane. Roberts claimed it was justified in terminating these orders due to Crane’s failure to deliver on the dates specified in their agreement. Roberts also filed a cross-petition, claiming that as a result of Crane’s delay in delivery on these two orders, Roberts lost other government contracts and resulting profits.

The case was tried to the court which found for Crane in the amount of $29,828.25 with interest of $9,704.11, for a total of $39,532.36, plus costs of $195.60. Roberts’ cross-petition was dismissed. Roberts filed a motion for a new trial which was overruled. This appeal followed. We affirm the judgment of the District Court.

The record reveals the following transaction. On June 11, 1968, Crane mailed Roberts a price quotation on *69 80 %"> 64 and 70 1" GS globe valves. On June 19, 1968, Roberts offered to furnish these valves to the Defense Supply Agency (hereinafter referred to as DSA). On September 12,1968, the DSA awarded Roberts contract No. DSA 700-69-C-2241 for the above valves. According to the contract the valves were to be shipped to Columbus, Ohio, within 350 days from the date of the award, or by August 25, 1969.

On October 31, 1968, Roberts offered to furnish the DSA with 38 and 39^" GS globe valves. On November 1, 1968, Crane mailed Roberts its price quotation on these valves. On December 17, 1968, the DSA awarded Roberts contract No. DSA 700-69-C-6451 for these valves. According to the contract these valves were to be shipped to Columbus, Ohio, and Oakland, California, within 350 days from the date of the award, or by November 30,1969.

On February 11, 1969, Crane received Roberts’ purchase order G-3795, for 80 64 and 70 1" GS globe valves. Enclosed with this order was a copy of DSA contract No. 700-69-C-2241, and a copy of the notice of award. The order specified the delivery date as “before August 25,1969,” the same as Roberts’ delivery date under DSA contract No. 700-69-C2241. Roberts did not place its order with Crane for the valves required under this government contract until almost 5 months had elapsed from the date the contract was awarded. Robert Swartz, chairman of the board of Roberts at the time, testified the delay was caused by Roberts’ unsuccessful attempt to get the government to accept a valve from a different manufacturer.

On the same date, Crane also received Roberts’ purchase order G-3796, for 38 %" and 49 GS globe valves. Enclosed with this order was a copy of DSA contract No. 700-69-C-6451, and a copy of the notice of award. This order specified the delivery date as “before November 30,1969,” which was the same as Roberts’ delivery date under DSA contract No. 700-69-C-6451. *70 This order was not placed until almost 2 months after the date of the award.

On February 12, 1969, Cornelius Ausema, Navy and Marine government sales manager of Crane, wrote to Morris Karpen, sales manager of Roberts, acknowledging receipt of the orders, but refusing to accept the delivery dates specified by Roberts. Ausema wrote: “Due to the late receipt of these orders it will be impossible to meet due dates measured from dates of contracts. We will, of course, be committed to deliver valves within the forecasts named in our proposals measured from date of receipt, namely February 11, 1969. The valves on Order G-3794 and G-3795 will be due on January 27, 1970 (350 days from February 11, 1969). Valves on Order G-3796, will be scheduled for shipment on/or before February 6, 1970 (360 days from February 11, 1969).

“As already stated verbally we cannot agree to accept penalties or price considerations for delayed deliveries, i.e., deliveries measured from dates of award. We need your acknowledgment of this agreement.”

Swartz testified that when Roberts received Ausema’s letter dated February 12, 1969, it became concerned and wanted the delivery dates on the orders clarified. He testified that Karpen called Crane in Chicago, and as a result Mr. Peter Pagratis of Crane came to Roberts’ Omaha office in mid-February. During their meetings, Swartz testified, Pagratis called someone in Chicago, and thereafter assured Roberts that Crane would make delivery on the dates specified in Roberts’ purchase orders or sooner. George Shafer, vice president of Roberts, testified that he saw Pagratis in Roberts’ offices in mid-February, in the presence of Karpen and Swartz, and that Pagratis stated he could improve upon the deliveries and would do everything in his power to expedite shipment. Don Foy, a Roberts’ employee at this time, testified he heard Pagratis say Crane would come close to, if not meet, the required government delivery dates on the two orders. Pagratis, a Crane employee at this *71 time, after refreshing his recollection with weekly travel expense reports, testified that he was not in Omaha at any time between February 2, 1969, and April 26, 1969.

On March 3, 1969, Karpen wrote back to Ausema: “We acknowledge receipt of your letter of February 12, 1969 and ask that you please exert every effort to conform to the delivery date which we have specified. In the event that it is through our fault that any penalties are incurred, we will stand these.”

Karpen’s letter made no mention of Pagratis’ alleged visit or of any of the representations Pagratis was alleged to have made at this time.

On March 18, 1969, Crane advised Roberts concerning order G-3795, that it could furnish an additional 34 %" GS globe valves at the same price each as in the original order, but advised: “It is important, however, that the additional order be in our hands within ten (10) days to permit simultaneous manufacture.”

On April 11, 1969, Crane received Roberts’ purchase order G-3795 ADD, adding 34 %" valves to its order, G-3795. Roberts wrote: “We are enclosing herewith our Purchase Order # G-3795-ADD and a copy of the Government Modification adding 34 valves to our original order. Will you please do all you can to expedite shipment.”

On August 4, 1969, Karpen wrote W. J. Seebauer of Crane, concerning order G-3795: “The government requests that we do all we can do to expedite shipment of the valves required on the Basic Contract and we are to advise them as soon as possible regarding this.

“We note that this is scheduled for shipment January 2nd. Will you please see if you can accelerate shipment and let us know by return mail.”

In mid-October, Roberts made a telephone appeal to E. Dykhuis of Crane for improved delivery on orders G-3795 and G-3795 ADD. In mid-July 1969, and on November 5, 1969, Roberts contacted Crane urging improved delivery on order G-3796.

*72 On November 21, 1969, Roberts wired Crane advising that purchase order G-3795 had been terminated by the government, and that Crane should stop all production on order G-3795, which Crane did.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nebraska Builders Products Co. v. Industrial Erectors, Inc.
478 N.W.2d 257 (Nebraska Supreme Court, 1992)
Paasch v. Brown
351 N.W.2d 74 (Nebraska Supreme Court, 1984)
V.P.O., Inc. v. Money
266 N.W.2d 79 (Nebraska Supreme Court, 1978)
Fisher v. Beebe & Runyan Furniture Co.
263 N.W.2d 826 (Nebraska Supreme Court, 1978)
Clemens Mobile Homes, Inc. v. Liberty Homes, Inc.
262 N.W.2d 463 (Nebraska Supreme Court, 1978)
Schuler-Olsen Ranches, Inc. v. Garvin
250 N.W.2d 906 (Nebraska Supreme Court, 1977)
Mickelson & Mickelson Hay Contractors v. Christensen
246 N.W.2d 655 (Nebraska Supreme Court, 1976)
MICKELSON & MICKELSON, ETC. v. Christensen
246 N.W.2d 655 (Nebraska Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
241 N.W.2d 516, 196 Neb. 67, 1976 Neb. LEXIS 743, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crane-co-v-roberts-supply-co-neb-1976.