Petska v. Olson Gravel, Inc.

500 N.W.2d 828, 243 Neb. 568, 1993 Neb. LEXIS 165
CourtNebraska Supreme Court
DecidedJune 4, 1993
DocketS-91-106
StatusPublished
Cited by26 cases

This text of 500 N.W.2d 828 (Petska v. Olson Gravel, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petska v. Olson Gravel, Inc., 500 N.W.2d 828, 243 Neb. 568, 1993 Neb. LEXIS 165 (Neb. 1993).

Opinion

White, J.

Defendant, Olson Gravel, Inc. (Olson), appeals from a jury verdict and the judgment entered thereon which awarded plaintiffs damages in the amount of $50,075.80. We affirm.

In December 1978, appellee Kerry P. Petska entered into a 10-year gravel lease with appellant, Olson. Although Petska was not the owner of the leased premises, he executed the contract with the consent of and on behalf of the landowners, his parents, Donald L. Petska and Norma E. Petska. The lease provided that Olson was granted permission to remove from the leased premises as much sand, gravel, and rocks as could be found. In exchange, Olson was to pay a royalty of 20 cents per cubic yard on gravel removed. The payment due dates for these royalties were set out by the contract as follows:

*570 7. Lessee agrees to pay to Lessor a royalty .... Said royalty shall be payable to Lessor on July 1st for gravel hauled between January 1st and June 30th of each year, October 1st for the third quarter; and December 31st for the fourth quarter.
8. Lessee agrees to pay Lessor a gravel royalty prepayment of $5,000.00 per year commencing with the execution of this agreement. Subsequent payments shall be made the 31st of December of each year. If at any time the royalty computed under paragraph 7 hereof exceeds the payments made under paragraph 8, royalty payments shall be made quarterly as scheduled in paragraph 7. In the event the said $50,000.00 credit is not used at the end of ten years, the excess shall be applied to gravel royalty computed during the second ten year period .... If Lessee fails to renew the lease into the second ten year period, any of the $50,000.00 credit shall remain with Lessor.

Although the parties executed the lease in 1978, Olson did not commence mining until 1985. It was not until near the end of the 10-year lease term that a dispute arose between the parties over the accounting of the amount of gravel removed from the leased premises. Olson claimed that the royalty prepayments it made pursuant to paragraph 8 of the lease were sufficient to meet the total amount of royalties due. The Petskas claimed that Olson’s accounting of the removed gravel was underestimated and that therefore Olson owed additional royalties not covered by the prepayments.

Petska, along with his parents, filed suit against Olson in Valley County District Court. The Petskas’ petition alleged two causes of action, one for forcible entry and detainer and a second for recovery of unpaid royalties. Both claims were based upon an alleged breach of the lease by Olson.

The two claims were tried separately. The first cause of action was tried before the court in October 1989. On November 1, after completion of the trial, the district court dismissed the first claim based on its finding that plaintiffs failed to prove Olson had violated any terms of the lease. Yet in the same ruling, the court stated that “there appears to be a dispute as to the accounting of removed material.” Olson was then given 10 *571 days to plead or 20 days to answer the second cause of action for recovery of unpaid royalties.

On November 7, Olson filed a demurrer to the Petskas’ second cause of action. The demurrer was overruled. On January 19,1990, Olson filed its answer in which it alleged that under the doctrines of res judicata and collateral estoppel, the trial court’s order dismissing plaintiffs’ first cause of action operated as a bar to plaintiffs’ second cause of action. Olson then moved for summary judgment, asserting that there was no issue of material fact because plaintiffs’ claim was barred by the doctrines of res judicata and collateral estoppel. The motion was denied.

The second cause of action was tried before a jury on November 26 and 27, 1990. Plaintiffs’ first witness was their expert witness, a land surveyor who was hired by plaintiffs to determine the amount of gravel removed from the leased premises. Plaintiffs’ expert testified that 513,782 cubic yards of sand, gravel, and rocks had been removed from the leased premises. Then plaintiffs introduced into evidence royalty summaries which were prepared by Dennis Olson, president of defendant. These summaries stated that defendant had removed only 97,368 cubic yards of sand, gravel, and rocks from the Petskas’ land. However, on direct examination by plaintiff, Dennis Olson admitted that the numbers in the royalty summaries indicating the amount of gravel removed from the Petska property from 1985 through 1988 were estimates which he determined by merely looking at the piles of removed gravel. Olson provided no expert testimony, but, rather, relied upon the royalty summaries as evidence of the actual amount of gravel removed. Defendant did provide evidence in the form of canceled checks to support his contention that $50,000 in royalty prepayments required by paragraph 8 of the lease had been paid to plaintiffs.

The jury returned a verdict in favor of plaintiffs and assessed damages in the amount of $50,075.80. The trial court entered judgment on the verdict, awarding plaintiffs $50,075.80 for unpaid royalties. Olson’s motions for judgment notwithstanding the verdict and new trial were overruled. Thus, Olson has brought this appeal.

*572 Appellant’s first assignment of error contests the trial court’s denial of its motion for summary judgment. We have held that a denial of a motion for summary judgment is not a final order and therefore is not appealable. Commerce Sav. Scottsbluff v. F.H. Schafer Elev., 231 Neb. 288, 436 N.W.2d 151 (1989). Appellant argues that in Wibbels v. Unick, 229 Neb. 184, 426 N.W.2d 244 (1988), this court appeared to apply a contrary rule by reviewing and reversing the lower court’s denial of a motion for summary judgment.

In Wibbels, defendant served a request for admissions upon petitioner in order to establish proof of his counterclaim against a petitioner in intervention. Petitioner failed to respond within the 30 days required by statute. Thereafter, defendant filed a motion for summary judgment which was based on the admissions in the discovery request. After service of the motion, but prior to the hearing, petitioner sent to defendant responses to the request for admissions. At the summary judgment hearing, petitioner introduced these responses into evidence, but did not explain its previous failure to respond within the time period prescribed by statute. The trial court denied defendant’s motion for summary judgment. After trial, the court ruled in favor of petitioner on defendant’s counterclaim. In defendant’s appeal we held that petitioner’s failure to respond within the statutory period conclusively established the requested admissions and that the admissions established the elements necessary for defendant’s recovery as a matter of law. Thus, we reversed the trial court’s final judgment as well as its denial of defendant’s motion for summary judgment.

Although our decision in Wibbels

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chrysler Corp. v. Jim Earp Chrysler-Plymouth, Ltd.
602 N.W.2d 43 (Nebraska Court of Appeals, 1999)
Pipe & Piling Supplies (U.S.A.), Ltd. v. Betterman & Katelman
596 N.W.2d 24 (Nebraska Court of Appeals, 1999)
PIPE AND PILING v. Betterman & Katelman
596 N.W.2d 24 (Nebraska Court of Appeals, 1999)
Vann v. Norwest Bank Nebraska, N.A.
591 N.W.2d 574 (Nebraska Supreme Court, 1999)
Doe v. Zedek
587 N.W.2d 885 (Nebraska Supreme Court, 1999)
Cunningham v. Prime Mover, Inc.
567 N.W.2d 178 (Nebraska Supreme Court, 1997)
Thomsen v. Greve
550 N.W.2d 49 (Nebraska Court of Appeals, 1996)
Farmers and Merchants Bank v. Grams
548 N.W.2d 764 (Nebraska Supreme Court, 1996)
Koster v. P & P ENTERPRISES, INC.
539 N.W.2d 274 (Nebraska Supreme Court, 1995)
Farm Credit Bank of Omaha v. Stute
537 N.W.2d 496 (Nebraska Supreme Court, 1995)
Hartley ex rel. Hartley v. Guthmann
532 N.W.2d 331 (Nebraska Supreme Court, 1995)
HARTLEY BY AND THROUGH HARTLEY v. Guthmann
532 N.W.2d 331 (Nebraska Supreme Court, 1995)
State v. Fahlk
524 N.W.2d 39 (Nebraska Supreme Court, 1994)
In Re Estate of Wagner
522 N.W.2d 159 (Nebraska Supreme Court, 1994)
Bradley v. Hopkins
522 N.W.2d 394 (Nebraska Supreme Court, 1994)
MacHolan v. Wynegar
513 N.W.2d 309 (Nebraska Supreme Court, 1994)
Kudlacek v. Fiat S.P.A.
509 N.W.2d 603 (Nebraska Supreme Court, 1994)
Kopecky v. National Farms, Inc.
510 N.W.2d 41 (Nebraska Supreme Court, 1994)
State v. White
508 N.W.2d 554 (Nebraska Supreme Court, 1993)
VonSeggern v. Willman
508 N.W.2d 261 (Nebraska Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
500 N.W.2d 828, 243 Neb. 568, 1993 Neb. LEXIS 165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petska-v-olson-gravel-inc-neb-1993.