Nani Koolau Co. v. K & M Construction, Inc.

681 P.2d 580, 5 Haw. App. 137, 1984 Haw. App. LEXIS 65
CourtHawaii Intermediate Court of Appeals
DecidedApril 6, 1984
DocketNO. 9037; CIVIL NO. 63958
StatusPublished
Cited by36 cases

This text of 681 P.2d 580 (Nani Koolau Co. v. K & M Construction, Inc.) is published on Counsel Stack Legal Research, covering Hawaii Intermediate Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nani Koolau Co. v. K & M Construction, Inc., 681 P.2d 580, 5 Haw. App. 137, 1984 Haw. App. LEXIS 65 (hawapp 1984).

Opinion

*138 OPINION OF THE COURT BY

HEEN, J.

Defendant K & M Construction, Inc. (K & M), appeals from a judgment entered against it in a breach of contract action brought by plaintiff Nani Koolau Company (Nani Koolau). We affirm. Nani Koolau cross-appeals from the trial court’s denial of its request for costs and attorney’s fees. We reverse and remand in part. We will address each appeal seriatim.

Nani Koolau is a registered general partnership whose partners include I & I Investors & Associates (I & I), a general partnership, Milton Sher (Sher), an architect, and K & M, a Hawaii corporation and general contractor. On April 7, 1977, Nani Koolau and K & M entered into a contract which required K & M to construct a residential apartment building on a parcel of land located in Kaneohe. The contract included the grading of the land and construction of a retaining wall on one corner of the property.

After the apartment building was substantially completed, 1 K & M began grading and filling the property. At that time, K & M discovered that a grading permit had not been obtained from the City and County of Honolulu and the work was halted. K & M hired William Hee & Associates, Inc. (Hee), an engineering firm, to obtain a grading permit using the project’s construction plans prepared by Sher, but Hee was unsuccessful. Although there is nothing in the record to indicate why the grading permit could not be obtained, the evidence indicates that Sher’s grading plans were never approved by the City.

The partners of Nani Koolau met in January of 1979 to discuss the problems related to the plans and Philip Ing (Ing) of I & I assumed the responsibility for solving those problems. Park Engineering, Inc. (Park), was retained by Nani Koolau to prepare new plans for the wall, and to obtain the grading permit. 2

*139 Park’s new plans were approved by the City “for grading only.” In June of 1980, Nani Koolau demanded that K & M construct the retaining wall as designed by Park. K & M refused and Nani Koo-lau thereafter awarded the contract for the completion of the grading of the property and construction of the wall to Haitsuka Brothers, Ltd. (Haitsuka), on its low bid of $35,729. The construction was completed by Haitsuka, and Nani Koolau brought this action to recover damages for K & M’s alleged breach of contract. 3

After a bench trial, the court, on September 3, 1982, rendered its findings of fact, conclusions of law and judgment for $38,480.03 in favor of Nani Koolau. 4 These appeals followed.

K & M’S APPEAL

K & M contends that: (1) findings of fact 10, 12, 21, and 22 are insufficient as they do not adequately reflect the evidence presented and finding of fact 17 is clearly erroneous; and (2) conclusions of law 1,2,4,5,8, and 12 are incorrect. We find no error and affirm.

(1)

A trial court’s findings of fact will not be set aside unless (1) the findings are not supported by substantial evidence and are, consequently, clearly erroneous or (2) a reviewing court, upon examination of all the evidence, is left with a definite and firm conviction that a mistake has been made. Krohnert v. Yacht Systems Hawaii, Inc., 4 Haw. App. 190, 664 P.2d 738 (1983); Stewart v. Smith, 4 Haw. App. 185, 662 P.2d 1121 (1983); Haworth v. State, 3 Haw. App. 281, 650 P.2d 583 (1982); Geldert v. State, 3 Haw. App. 259, 649 P.2d 1165 (1982).

Where the determination of an issue depends upon the credibility of witnesses, the scope of review of an appellate court is limited *140 by the due regard given to the opportunity of the trial court to judge the credibility of witnesses. Marshall v. Kirkland, 602 F.2d 1282 (8th Cir. 1979). See Rule 52(a), Hawaii Rules of Civil Procedure (HRCP) (1972, as amended); 5A Moore & Lucas, Moore’s Federal Practice ¶ 52.03[1] (1982). “An appellate court will not pass upon issues dependent upon credibility of witnesses and the weight of the evidence; this is the province of the trial judge.” Shannon v. Murphy, 49 Haw. 661, 667, 426 P.2d 816, 820 (1967). See also MPM Hawaiian, Inc. v. Amigos, Inc., 63 Haw. 485, 630 P.2d 1075 (1981); Molokoa Village Development Co. v. Kauai Electric Co., 60 Haw. 582, 593 P.2d 375 (1979); Lennen & Newell, Inc. v. Clark Enterprises, Inc., 51 Haw. 233, 456 P.2d 231 (1969). Cf. Shinn v. Edwin Yee, Ltd., 57 Haw. 215, 553 P.2d 733 (1976).

Where an appellant alleges that the trial court failed to make adequate findings of fact, the appellate court will examine all the findings, as made, to determine whether they are (1) supported by the evidence; and (2) sufficiently comprehensive and pertinent to the issues in the case to form a basis for the conclusions of law. Palama v. Sheehan, 50 Haw. 298, 440 P.2d 95 (1968); Shannon v. Murphy, 49 Haw. 661, 426 P.2d 816 (1967); Ventura v. Grace, 3 Haw. App. 371, 650 P.2d 620 (1982); Scott v. Contractors License Board, 2 Haw. App. 92, 626 P.2d 199 (1981). If those findings include sufficient subsidiary facts to disclose to the reviewing court the steps by which the lower court reached its ultimate conclusion on each factual issue, then the findings are adequate. See Tugaeff v. Tugaeff, 42 Haw. 455 (1958).

K & M argues that findings of fact 10, 12, 21, and 22 5 are *141 inadequate because the court failed to include any findings relating to K 8c M’s defenses that (1) Nani Koolau had failed to obtain city approval of the grading plans, and as a result, K & M was unable to obtain a grading permit and could not construct the wall; and (2) K & M was relieved of further responsibility to construct the wall when Ing undertook to solve the problems involving the plans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marco Polo Realty, LLC. v. Kim
Hawaii Intermediate Court of Appeals, 2025
SA v. AE
527 P.3d 479 (Hawaii Intermediate Court of Appeals, 2023)
Brown v. BWC Hawaii, LLC
524 P.3d 1269 (Hawaii Intermediate Court of Appeals, 2023)
In re: DM
502 P.3d 1025 (Hawaii Intermediate Court of Appeals, 2022)
Minton v. Quintal
369 P.3d 853 (Hawaii Intermediate Court of Appeals, 2016)
Yoneji v. Yoneji
370 P.3d 704 (Hawaii Intermediate Court of Appeals, 2016)
Boyd v. Hawai'i State Ethics Commission
358 P.3d 709 (Hawaii Intermediate Court of Appeals, 2015)
State v. Ramos-Saunders
349 P.3d 406 (Hawaii Intermediate Court of Appeals, 2015)
Arquette v. State.
290 P.3d 493 (Hawaii Supreme Court, 2012)
State v. Rodrigues.
286 P.3d 809 (Hawaii Supreme Court, 2012)
Daiichi Hawai'i Real Estate Corp. v. Lichter
82 P.3d 411 (Hawaii Supreme Court, 2003)
Matsunaga v. Matsunaga
53 P.3d 296 (Hawaii Intermediate Court of Appeals, 2002)
Nakamura v. State
47 P.3d 730 (Hawaii Supreme Court, 2002)
Booth v. Booth
978 P.2d 851 (Hawaii Supreme Court, 1999)
Canalez v. Bob's Appliance Service Center, Inc.
972 P.2d 295 (Hawaii Supreme Court, 1999)
Rezentes v. Rezentes
965 P.2d 133 (Hawaii Intermediate Court of Appeals, 1998)
United Truck Rental Equipment Leasing, Inc. v. Kleenco Corp.
929 P.2d 99 (Hawaii Intermediate Court of Appeals, 1996)
People v. Williams
908 P.2d 1157 (Colorado Court of Appeals, 1995)
People v. Chavez
902 P.2d 891 (Colorado Court of Appeals, 1995)
Amfac, Inc. v. Waikiki Beachcomber Investment Co.
839 P.2d 10 (Hawaii Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
681 P.2d 580, 5 Haw. App. 137, 1984 Haw. App. LEXIS 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nani-koolau-co-v-k-m-construction-inc-hawapp-1984.