N. Elec. Inc. v. Amsdell Constr., Inc., Unpublished Decision (8-11-2005)

2005 Ohio 4134
CourtOhio Court of Appeals
DecidedAugust 11, 2005
DocketNo. 85293.
StatusUnpublished
Cited by4 cases

This text of 2005 Ohio 4134 (N. Elec. Inc. v. Amsdell Constr., Inc., Unpublished Decision (8-11-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N. Elec. Inc. v. Amsdell Constr., Inc., Unpublished Decision (8-11-2005), 2005 Ohio 4134 (Ohio Ct. App. 2005).

Opinion

JOURNAL ENTRY AND OPINION
{¶ 1} The appellant, Target Screen L.L.C. ("Target"), appeals from the trial court's finding of a valid and enforceable arbitration agreement and holding the decision of the arbitration panel to be binding. It is Target's contention that, although the arbitration agreement in question should be deemed valid, it has lapsed because of time restrictions. After reviewing the record and for the reasons set forth below, we affirm the trial court's ruling.

{¶ 2} This matter derives from a contract dispute that arose between a general contractor and a subcontractor who contracted to build a commercial building for Target. Additional parties to the construction project were appellees Amsdell Construction, Inc. ("Amsdell"), who served as the general contractor, and Randall S. Smith and Davidson Smith Certo Architects (jointly "Smith"), who provided architectural services. Thereafter several derivative claims spun off involving a plethora of legal claims and parties. At issue in this appeal are disputes arising from Target's contractual relationships with both Amsdell and Smith.

{¶ 3} The contracts originally entered into between the parties contained provisions stating that all disputes arising out of or relating to the contract[s] should be submitted to arbitration; said provisions read in pertinent part:

{¶ 4} "* * * All claims or disputes between the Contractor and the Owner arising out or relating to the Contract, or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association ("AAA") currently in effect unless the parties mutually agree otherwise and subject to an initial presentation of the claim or dispute to the Architect * * *."

{¶ 5} Nevertheless, Target filed its initial lawsuit in the common pleas court by way of a third-party complaint after it had been sued for foreclosure by one of its subcontractors. On July 8, 1997, Amsdell and Smith, third-party defendants to this claim, filed motions with the court to dismiss or stay all claims due to contractual agreements requiring arbitration. On April 28, 1998, the trial court ultimately referred the matter for arbitration.

{¶ 6} Subsequently, two separate arbitration proceedings began with the AAA; one involved the dispute between Target and Amsdell and the other involved the dispute between Target and Smith. After a number of changes of counsel by the parties, as well as failed settlement negotiations, these arbitration proceedings were still no closer to resolution.

{¶ 7} On October 29, 2001, the parties negotiated and executed a Consolidated Agreement and Substitute Arbitration Agreement ("New Agreement"). After execution of this New Agreement, a considerable amount of time again passed without the parties coming any closer to a resolution of their claims with the reasons for such delay in dispute. Then on June 6, 2002, Target retained new counsel and moved the trial court for a status conference. Consequently, a hearing was held in October 2002, and new counsel for Target argued that the matter should be remanded to the common pleas court for trial instead of arbitration. On October 1, 2002, the trial court once again ordered that the case be submitted for arbitration and appointed three arbitrators to hear the matter.

{¶ 8} Arbitration was set for January 31, 2003. Prior to the scheduled arbitration, Amsdell requested from Target permission to inspect the premises at issue. Target opposed this request, and that dispute was submitted to the arbitration panel. The panel subsequently ordered Target to allow Amsdell to inspect the premises.

{¶ 9} In response to this arbitration order, Target filed a motion seeking a dismissal of arbitration because the underlying arbitration contract was invalid. On February 11, 2003, Target filed an additional motion to enforce the arbitration agreement and declare the same invalid. Essentially, Target contends that the New Agreement was the applicable, enforceable contract at bar, but that the agreement is no longer valid due to a lapse in the time guidelines.

{¶ 10} On August 27, 2004, the trial court held the following:

{¶ 11} "THE COURT FINDS THAT THERE IS A VALID AND ENFORCEABLE ARBITRATION AGREEMENT SIGNED BY THE PARTIES IN OCTOBER 2001. IT IS UNDISPUTED THAT THE AGREEMENT TO ARBITRATE WAS SIGNED BY ALL PARTIES, THAT THERE WAS A `MEETING OF THE MINDS' AND NO FRAUD INVOLVED IN THE DRAFTING OR TERMS OF THE CONTRACT. AMSDELL CONSTRUCTION HAS MOVED TO DECLARE THE AGREEMENT INVALID AS ALL PERTINENT DATES AGREED TO IN THE CONTRACT TO ARBITRATE HAVE PASSED. THE REASONS FOR THIS FAILURE TO ABIDE BY THE TERMS OF THE ARBITRATION AGREEMENT ARE IN DISPUTE BUT ARE LARGELY RELATED TO CHANGES IN COUNSEL FOR PARTIES ON BOTH SIDES. THE COURT NOTES THAT THE PARTIES AGREED THAT SAID ARBITRATION WOULD BE BINDING AND THAT THE PROCEEDINGS WOULD BE GOVERNED BY AAA ARBITRATION RULES. PURSUANT TO THE ARBITRATION AGREEMENT AND AAA RULES ANY DISCOVERY DISPUTES, PROCEDURAL ISSUES AND CONTINUANCES ARE TO BE RESOLVED BY THE ARBITRATION PANEL. THEREFORE THIS COURT FINDS THAT THE ARBITRATION CLAUSE IS VALID AND ENFORCEABLE AND THAT THE DECISION OF THE ARBITRATION PANEL WAS TO BE BINDING * * *. THE COURT FINDS THAT THERE IS NO JUST REASON FOR DELAY."

{¶ 12} Target now timely appeals from this decision, raising three assignments of error. We assess all three assignments of error under one analysis and find them all to be without merit.

{¶ 13} "I. THE TRIAL COURT ERRED IN REFERRING THE MATTER TO ARBITRATION WHERE THE ARBITRATORS WERE DIVESTED OF JURISDICTION UNDER THE TERMS OF THE ARBITRATION CONTRACT.

{¶ 14} "II. THE TRIAL COURT ERRED IN ITS AUGUST 27, 2004 JOURNAL ENTRY BY REFERRING THE MATTER TO ARBITRATION WHERE THE CONTRACT PROVISION THAT AUTHORIZED ARBITRATION EXPIRED AND THE APPELLEES WAIVED THEIR RIGHT TO ARBITRATION.

{¶ 15} "III. THE TRIAL COURT ERRED IN REVERSING ITSELF AND EXPANDING THE AMOUNT OF TIME AVAILABLE TO THE PARTIES TO COMPLETE DISCOVERY."

{¶ 16} Appellant contends that the trial court was at error in holding that the decision of the arbitration panel was binding and ordering the case to be submitted for arbitration. This court has held that an order that grants or denies (or likewise reaffirms) a stay of any action pending arbitration is a final appealable order for appeal purposes. See Dunn v. LM Building,Inc. (Mar. 25, 1999), Cuyahoga App. No. 75203. Thus the applicable standard of review here is abuse of discretion.Carter Steel Fabricating Co. v. Danis Bldg. Constr. Co. (1998), 126 Ohio App.3d 251, 2542-55, 710 N.E.2d 299. An abuse of discretion connotes more than an error of law or judgment, it implies that the court's attitude is unreasonable, arbitrary or unconscionable. Blakemore v. Blakemore (1983),5 Ohio St.3d 217, 219, 5 Ohio B. 481, 450 N.E.2d 1140. Absent a clear abuse of that discretion, the lower court's decision should not be reversed. Mobberly v. Hendricks

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RM Riggle Ents., Inc. v. Commerce Park Place Holdings, L.L.C.
2021 Ohio 4215 (Ohio Court of Appeals, 2021)
Michigan Timber & Truss, Inc. v. Summit Bldg. Servs., L.L.C.
2021 Ohio 3158 (Ohio Court of Appeals, 2021)
N. Electric, Inc. v. Amsdell Constr., Inc.
2013 Ohio 5433 (Ohio Court of Appeals, 2013)
Blanchard Valley Health Sys. v. Canterbury Holdings, Inc.
2012 Ohio 5134 (Ohio Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 4134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/n-elec-inc-v-amsdell-constr-inc-unpublished-decision-8-11-2005-ohioctapp-2005.