RM Riggle Ents., Inc. v. Commerce Park Place Holdings, L.L.C.

2021 Ohio 4215, 180 N.E.3d 748
Ohio Court of Appeals·Decided December 2, 2021·No. 110236·Published·Cited by 3 cases

Opinion

[Cite as RM Riggle Ents., Inc. v. Commerce Park Place Holdings, L.L.C., 2021-Ohio-4215.]

COURT OF APPEALS OF OHIO

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

RM RIGGLE ENTERPRISES, INC., :

Plaintiff-Appellant, :

No. 110236

v. :

COMMERCE PARK PLACE : HOLDINGS, L.L.C., ET AL., :

Defendants-Appellees.

JOURNAL ENTRY AND OPINION

JUDGMENT: AFFIRMED

RELEASED AND JOURNALIZED: December 2, 2021

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-20-935714

Appearances:

Connick Law, L.L.C., and Thomas J. Connick, for appellant.

Thompson Hine L.L.P., William J. Hubbard, Daniel M.

Haymond, William J. Thrush, and David J. Walters, for appellee NRP Contractors L.L.C.

Hahn Loeser & Parks L.L.P., Jeffrey A. Brauer, Aaron S.

Evenchik, and Tara J. Rose, for appellee Commerce Park Place Holdings, L.L.C.

Travelers Staff Counsel of Ohio and Douglas J. May, for appellee Travelers Property Casualty Company of America.

MICHELLE J. SHEEHAN, J.:

This appeal involves the scope of appellate review when a trial court stays litigation pending arbitration pursuant to an arbitration agreement without first deciding a separate declaratory judgment action regarding a related arbitration agreement. Because an appellate court is limited in its review of whether a lower court abuses its discretion when granting a stay of litigation pending arbitration, we are unable to conclude that the trial court abused its discretion in this case.

This case concerns a commercial construction project. R.M. Riggle Enterprises, Inc. (“Riggle”) was a subcontractor for NRP, L.L.C. (“NRP”), who served as a general contractor in the construction of an apartment complex owned by Commerce Park Place Holdings, L.L.C. (“CPPH”). Riggle installed the fire suppression system in the apartment complex. Several years later, the waterlines in the fire suppression system broke, causing extensive water damage.

Both the contract between the property owner CPPH and the general contractor NRP and the contract between the NRP and the subcontractor Riggle contain arbitration agreements. CPPH commenced an arbitration proceeding before the American Arbitration Association (“AAA”) (hereafter referred to as the “CPPH/NRP arbitration”). NRP agreed to arbitration and sought to join Riggle in the CPPH/NRP arbitration. CPPH and its insurer, Travelers Property Casualty Company of America (“Travelers”), also filed an action in the common pleas court against NRP and several subcontractors, including Riggle (the “CPPH/NRP case”).

Riggle objected to being joined in the CPPH/NRP arbitration.

According to NRP, the AAA joined Riggle in the arbitration despite Riggle’s objection. Riggle then filed a declaratory judgment action in the common pleas court seeking certain judicial declarations regarding the arbitration provisions at issue; Riggle also filed a motion in the CPPH/NRP case to stay arbitration pending the resolution of its declaratory judgment action.

Subsequently, NRP filed a motion to stay proceedings in the CPPH/NRP case pending the CPPH/NRP arbitration. Upon Riggle’s request, the trial court consolidated the two cases. After the consolidation, the court granted NRP’s motion to stay proceedings pending arbitration and its judgment entry stated “all pending motions are rendered moot,” which includes Riggle’s motion to stay arbitration.

On appeal, Riggle raises the following four assignments of error:

I. The trial court erred by granting NRP LLC’s motion to stay proceedings pending arbitration.

II. The trial court erred by impliedly denying R.M. Riggle Enterprises, Inc.’s motion to stay/enjoin arbitration.

III. The trial court erred by finding that NRP LLC did not waive its right to arbitration.

IV. The trial court erred by granting NRP LLC’s motion to stay proceedings pending arbitration without conducting an evidentiary hearing.1

1 CPPH and Travelers filed a joint appellee’s brief in the appeal, and the joint brief incorporates fully the appellee brief filed by NRP.

After a careful review of the record and applicable law, we do not find the trial court abused its discretion staying the proceedings and denying the pending motions and therefore affirm the trial court’s judgment. The Contracts and the Arbitration Agreements In 2013, CPPH entered into a construction contract with NRP for NRP to serve as a general contractor for the construction of a residential apartment complex known as “The Vue” located in Beachwood, Ohio. NRP, in turn, entered into a subcontract agreement with Riggle for the installation of the fire sprinklers. Both the construction contract and the subcontract agreement contain an arbitration provision.

Article 21 of the construction contract between CPPH and NRP is titled “CLAIMS AND DISPUTES.” Section 21.1 states that claims and disputes arising out of or relating to the contract are subject to arbitration. Section 21.4 states that the arbitration is to be administered by the AAA in accordance with the Construction Industry Arbitration Rules. Furthermore, Sections 21.5 and 21.6 state the following regarding joinder:

21.5 Either party, at its sole discretion, may consolidate an arbitration conducted under this agreement with other arbitration to which it is a party provided that (1) the arbitration agreement governing the other arbitration permits consolidation; (2) the arbitrations to be consolidated substantially involve common questions of law or fact; and (3) the arbitrations employ materially similar procedural rules and methods for selecting arbitrator(s).

21.6 Any party to an arbitration may include by joinder persons or entities substantially involved in a common question of law or fact whose presence is required if complete relief is to be accorded in

arbitration provided that the party sought to be joined consents in writing to such joinder. Consent to arbitration involving an additional person or entity shall not constitute consent to arbitration of a Claim not described in the written Consent.

The arbitration agreement contained in the subcontract agreement between NRP and Riggle states, in pertinent part:

18. BINDING ARBITRAITON. Claims, dispute and other matters in question arising out of or relating to this Agreement, the Work or the Project shall be decided by binding arbitration which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect. The demand for arbitration shall be filed in writing with the other party to this Agreement and with the American Arbitration Association and shall be made within a reasonable time after the dispute has risen. * * * Arbitration arising out of or relating to the Contract Document shall include, by consolidation, joinder or in any other manner, any person or entity having an interest in who may be accountable for the claim.

Arbitration Before the AAA and Litigation in the Common Pleas Court In January 2018, the fire suppression supply lines broke in several units, causing extensive water damage. On January 2, 2020, the property owner CPPH and its insurer Travelers filed a demand for arbitration before the AAA pursuant to the arbitration provision in its contract with NRP, referred to above as the CPPH/NRP arbitration.

Simultaneously, CPPH and Travelers filed a complaint in the common pleas court against NRP and several other parties involved in the construction of the fire suppression system, including Riggle, claiming defects in the construction, referred to above as the CPPH/NRP case.2 Subsequently, AAA joined Riggle in the CPPH/NRP arbitration. In response, Riggle filed a declaratory judgment action in the common pleas court, seeking a declaration that it should not be joined in the CPPH/NRP arbitration. In the following, we describe these procedures in more detail.

a. Arbitration

Free access — add to your briefcase to read the full text and ask questions with AI

RM Riggle Ents., Inc. v. Commerce Park Place Holdings, L.L.C., 2021 Ohio 4215, 180 N.E.3d 748 (Ohio Ct. App. 2021).

2021 Ohio 4215 (RM Riggle Ents., Inc. v. Commerce Park Place Holdings, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Price v. Jeff Wyler Eastgate, Inc.
2025 Ohio 4707 (Ohio Court of Appeals, 2025)
KeyBank, N.A. v. David
2024 Ohio 5333 (Ohio Court of Appeals, 2024)
Youngstown Professional Firefighters v. Youngstown
2024 Ohio 940 (Ohio Court of Appeals, 2024)