Michigan Timber & Truss, Inc. v. Summit Bldg. Servs., L.L.C.

2021 Ohio 3158
CourtOhio Court of Appeals
DecidedSeptember 14, 2021
Docket20AP-557
StatusPublished
Cited by2 cases

This text of 2021 Ohio 3158 (Michigan Timber & Truss, Inc. v. Summit Bldg. Servs., L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan Timber & Truss, Inc. v. Summit Bldg. Servs., L.L.C., 2021 Ohio 3158 (Ohio Ct. App. 2021).

Opinion

[Cite as Michigan Timber & Truss, Inc. v. Summit Bldg. Servs., L.L.C., 2021-Ohio-3158.]

IN THE COURT OF APPEALS OF OHIO

TENTH APPELLATE DISTRICT

Michigan Timber & Truss, Inc., :

Plaintiff-Appellee, :

v. : No. 20AP-557 Summit Building Services, LLC, et al., : (C.P.C. No. 19CV-10385)

Defendants-Appellees/ : Third-Party Plaintiffs, (ACCELERATED CALENDAR) v. :

Ruscilli Construction Co., Inc., et al., :

Third-Party Defendants/ : Appellants. :

D E C I S I O N

Rendered on September 14, 2021

On brief: McDonald Hopkins LLC, Peter D. Welin, and John A. Gambill; Andrew R. Fredelake, for appellant Ruscilli Construction Co. Argued: John A. Gambill.

On brief: Taft Stettinius & Hollister LLP, James D. Abrams, and Joseph C. Pickens, for appellee Summit Building Services, LLC. Argued: James D. Abrams.

APPEAL from the Franklin County Court of Common Pleas SADLER, J. {¶ 1} Appellant/third-party-counterclaim defendant, Ruscilli Construction Co., Inc. ("Ruscilli"), appeals from a judgment of the Franklin County Court of Common Pleas denying its motion to stay proceedings and compel arbitration with appellee/third-party- No. 20AP-557 2

counterclaim plaintiff, Summit Building Services, LLC ("Summit"). For the following reasons, we reverse the trial court judgment. I. FACTS AND PROCEDURAL HISTORY {¶ 2} Ruscilli is the general contractor for a commercial construction project located at 230 E. Long Street in Columbus, Ohio. Ruscilli entered into a subcontract with Summit pursuant to which Summit agreed to perform the rough carpentry for the project. Summit then entered into a contract/purchase order with Michigan Timber & Truss, Inc. ("MTT") whereby MTT agreed to supply Summit with lumber materials for the carpentry work. {¶ 3} A dispute arose between MTT and Summit regarding whether MTT provided defective and/or noncompliant materials. After failing to resolve their differences, Summit declared MTT in default of their contract and terminated the purchase order in October 2019. A few months later, in December 2019, since Summit had not fully paid MTT under the purchase contract, MTT filed the instant lawsuit claiming breach of contract, conversion, and unjust enrichment against Summit, and lien on discharge bond and violation of the Ohio Prompt Payment Act against Summit and bond-issuer Employers Mutual Casualty Company ("EMCC"). {¶ 4} On March 2, 2020, Summit and EMCC filed a combined answer, third-party complaint against an insurance company, counterclaim against MTT for breach of contract ("Count I"), and—pertinent to this appeal—counterclaim for declaratory judgment against MTT and "[t]hird-party [c]ounterclaim [d]efendants" identified as Ruscilli and the property owner ("Count II"). (Answer & Counterclaims at 8, 12.) The counterclaim for declaratory judgment in Count II involved "whether Ohio's Prompt Pay Act, R.C. 4113.61(A)(1)(b) required Summit to make payments to MTT when Summit has unapplied charge-backs and other deductions that apply to MTT's pay applications and where Ruscilli has not made payment to Summit for its pay applications that included MTT's work." (Answer & Counterclaims at 11.) Summit asserted in pertinent part that Ruscilli was "required to be named in this claim pursuant to R.C. 2721.12(A) because [it has] an interest that may be effected by the declaration requested [in the counterclaim]." (Answer & Counterclaims at 12.) No. 20AP-557 3

{¶ 5} On July 21, 2020, MTT filed a motion for leave to amend its complaint to join Ruscilli and the property owner as defendants and to add a claim of unjust enrichment against them. On August 13, 2020, Ruscilli and the property owner filed a joint motion to dismiss Count II of Summit's counterclaim or, alternatively, to stay proceedings as to that count and compel arbitration pursuant to the terms of the subcontract. Later that month, Ruscilli filed a related motion to stay discovery. {¶ 6} Summit opposed Ruscilli's motion to dismiss or stay and compel arbitration, arguing in pertinent part that a declaratory judgment action is not a "dispute" as set forth in the subcontract clauses dealing with arbitration. (Memo. Contra at 2, 7-8.) Specifically, Summit contended that the unambiguous language of the subcontract required only disputes arising "during the 'course of construction' " to be arbitrated, and therefore that clause is not applicable in this case since the subcontract was terminated by Ruscilli. (Memo. Contra at 7-8, citing Subcontract, Article 11.1.) {¶ 7} In an October 29, 2020 decision, the trial court denied Ruscilli's motion to stay and order arbitration, but did so for reasons other than those raised by the parties. The trial court stated: Instead of addressing whether a declaratory judgment claim is a dispute within the contract, however, the Court finds a more straightforward reason that the request for a stay is not currently persuasive. Even if the declaratory judgment action was a dispute set forth in the contract, Ruscilli has shown no evidence that arbitration is the correct stage of the dispute resolution process as set forth in the contract for the matters at hand. Indeed, there are two conditions precedent before arbitration is permitted: 1) attempting to settle through direct discussion by and between the parties' respective Project Managers and 2) pursuing mediation. If the Court were to consider a stay, Ruscilli would need to show that it had first attempted to settle through direct discussion with SBS and then, second, mediation with SBS. Ruscilli has not currently met this burden, and thus the Court declines to stay the proceedings against Ruscilli stemming from count II of SBS's counterclaim.

(Oct. 29, 2020, Trial Court Judgment at 11-12.) {¶ 8} In response to the trial court's assertion that it "had shown no evidence" of the conditions precedent being met, in November 2020 Ruscilli filed a "Motion to Stay No. 20AP-557 4

Pursuant to R.C. 2711.02 and Compel Arbitration Pursuant to R.C. 2711.03" with (what it asserts to be) evidence it satisfied all conditions precedent attached to the motion. Ruscilli filed a notice of appeal, and the November 2020 motion to stay remains pending in the trial court. II. ASSIGNMENTS OF ERROR {¶ 9} Ruscilli submits two assignments of error for our review: ASSIGNMENT OF ERROR NO. 1: The Trial Court Erred In Denying Ruscilli's Motion To Dismiss Or, Alternatively, To Stay Pending Arbitration Based Upon Ruscilli's Failure To Prove That All Conditions Precedent Had Been Satisfied Because Issues Of Procedural Arbitrability Are Reserved For The Arbitrator.

ASSIGNMENT OF ERROR NO. 2: The Trial Court Erred In Denying Ruscilli's Motion To Dismiss Or, Alternatively, To Stay Pending Arbitration Because Ruscilli Adequately Showed That Summit's Declaratory Judgment Action Is Subject To Mandatory And Binding Arbitration.

III. STANDARD OF REVIEW {¶ 10} An appellate court generally reviews an appeal from a motion to stay proceedings pending arbitration for an abuse of discretion. Morris v. Morris, 189 Ohio App.3d 608, 2010-Ohio-4750, ¶ 15 (10th Dist.). An abuse of discretion implies the trial court decision is unreasonable, arbitrary, or unconscionable. Blakemore v. Blakemore, 5 Ohio St.3d 217, 219 (1983). However, an appellate court employs a de novo standard of review where the appeal of a motion to stay proceedings pending arbitration presents a question of law. Morris at ¶ 15. "Thus, '[a] trial court's decision granting or denying a stay of proceedings pending arbitration is * * * subject to de novo review on appeal with respect to issues of law, which commonly will predominate because such cases generally turn on issues of contractual interpretation or statutory application.' " Id. citing Hudson v. John Hancock Fin. Servs., 10th Dist. No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rice v. Stuckey
2025 Ohio 2242 (Ohio Court of Appeals, 2025)
State ex rel. Staple v. State Emp. Relations Bd.
2024 Ohio 140 (Ohio Court of Appeals, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2021 Ohio 3158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-timber-truss-inc-v-summit-bldg-servs-llc-ohioctapp-2021.