Mountain States Telephone & Telegraph Co. v. Public Utilities Commission

345 F. Supp. 80, 1972 U.S. Dist. LEXIS 12894, 1972 WL 233038
CourtDistrict Court, D. Colorado
DecidedJuly 5, 1972
DocketCiv. A. C-4009
StatusPublished
Cited by8 cases

This text of 345 F. Supp. 80 (Mountain States Telephone & Telegraph Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mountain States Telephone & Telegraph Co. v. Public Utilities Commission, 345 F. Supp. 80, 1972 U.S. Dist. LEXIS 12894, 1972 WL 233038 (D. Colo. 1972).

Opinions

PER CURIAM

This is a utility rate case which is now in process before the Colorado Public Utilities Commission. Jurisdiction is asserted to exist on the basis of 28 U.S. C. § 1331, it being the contention of plaintiff that the refusal of the defendants to allow a temporary adjustment in plaintiff’s telephone rates pending the decision of the Commission in the proceedings that are now going on constitutes a deprivation of property contrary to the Fourteenth Amendment of the Constitution of the United States. The demand is for a mandatory injunction directed to the Commission requiring it to immediately and forthwith allow Mountain Bell to increase its rates on an interim and temporary basis giving effect to its current operating and construction programs which are said to be, and no doubt are, extensive. Mountain Bell offers to deposit a bond to secure refunds should it be determined that the rates are excessive, unjust or unreasonable.

The central point in Mountain Bell’s demand is that the defendant Commission has heretofore held that Mountain Bell is entitled to earnings and revenues which will insure a rate of 8.9 percent. It is said that under their current expansion and expenditure program their revenues have fallen below 8.9 percent, and even though they may be earning a substantial percentage, it nevertheless becomes a confiscatory rate if at any time their earnings fall below the fixed percentage previously determined to be reasonable. Thus, they maintain that any deviation from the 8.9 percent is per se confiscation and a violation of Mountain Bell’s rights under the Fourteenth Amendment.

The present proceedings were instituted before the Commission in January 1972, and at that time a demand was [82]*82made to increase the rates on a temporary basis, but this request was denied. Subsequent similar requests were made and were also rejected by the Commission.1 This action was filed May 16, 1972, no effort having been made to obtain relief in the courts of Colorado. The excuse given for this by-pass of state remedies on the part of Mountain Bell is that in a previous case, their 1971 rate case, they sought to obtain relief by applying for injunction in the state court. This request was denied and that denial was affirmed by the Colorado Supreme Court in Mountain States T. & T. Co. v. Public Utilities Com’n, Colo., 494 P.2d 76 (1972). Subsequent to the Commission’s order in the 1971 rate case, Mountain Bell again prosecuted a proceeding through the state courts séeking various relief including recoupment of losses occurring during the interim period and demanding that their rates be increased to coincide with the current wage levels and additional capital losses (in other words, the current economic situation). Mountain Bell was denied relief at both the district and Supreme Court levels.

Mountain Bell points to these unsuccessful 1 efforts as justifying its failure and refusal to seek a review of the defendant Commission’s denial of its application to put into effect interim rates pending the 1972 determination.

As we view it, the crux of this controversy is then the alleged losses suffered by Mountain Bell during the rate-making process. A related problem is the utilization by the Commission of a historic period in determining rate base and its refusal to adjust the rates on an entirely current basis, for example, month to month.

There is no complaint that the Public Utilities Commission has not been devoting its time and efforts to Mountain Bell’s problems. The present hearings have been going on for some weeks, and it is predicted that they will continue until approximately July 15. After completion of these hearings, a prompt decision is likely because if no decision is forthcoming, Mountain Bell’s requested increased rates will go into effect as a matter of law and regardless of decision.

This court’s jurisdiction is, of course, limited. It exists only to the extent that a federal question as described in 28 U.S.C. § 1331 exists. Thus, the matter must arise under the Constitution and laws or treaties of the United States. Clearly, we do not have plenary authority to adjust rates that we consider to be unfair; in short, we are not a rate-making authority and no amount of invective or ’ characterization serves to create jurisdiction to grant relief. Congress, in 28 U.S.C. § 1342, has further restricted our jurisdiction in rate cases.2 The narrow question is then whether there has been a violation of substantive due process and, if so, whether § 1342, supra, precludes our going forward. A reading of this specific statutory limitation clearly shows that we have jurisdiction to proceed only if part 4 of § 1342 requires it, that is, if nonexistence of a plain, speedy and efficient remedy in the courts of the state is shown. As we read the statute, its plain object is to prevent federal courts from intervening [83]*83in the state rate-making process even though the matter might be repugnant to the Federal Constitution, unless the remedy in state courts is inadequate.

I.

Mountain Bell is certainly not without a formal remedy since the state machinery for review of Commission decisions is elaborate. C.R.S.1963 § 115-6-14(1) calls for a motion for rehearing within 20 days after a decision of the Commission. A failure on the part of the Commission to act on such a motion within 30 days constitutes a denial. Within 30 days after denial of the application for rehearing, the aggrieved party may apply to the state district court for a writ of certiorari for the purpose of “having the lawfulness of the final decision inquired into and determined.” This is a review of the record made before the Commission. This section contemplates that the district judge hear and determine questions of law including Constitutional questions. The Supreme Court of Colorado then has jurisdiction by writ of error to review the district court’s decision.

Section 115-6-17 requires that these actions be preferred over all other actions except election causes. There is no restriction as to the kind of decision that can be reviewed, and presumably a decision denying the application for immediate effectiveness of the rate schedule pending hearing, based as it is in this case particularly on the allegation that vast amounts are involved, could be reviewed. Thus, it is impossible to understand why Mountain Bell has failed to utilize this procedure and why it has allowed it to lapse. In fact, Mountain Bell did not try out this procedure in its 1971 rate case, but rather at the interim stages sought injunctive relief and, indeed, it came to this court in quest of such an injunction. See Mountain States Telephone and Telegraph Company v. Public Utilities Commission, 324 F.Supp. 857 (D.Colo.1971). On that occasion it sought to have the statute which authorizes suspension of interim rates declared unconstitutional, and it was also contending that the state process was inadequate during the interim period. However, this court did not reach these questions because a final decision of the Commission was entered on the day that the cause was tried.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Columbia Gas of West Virginia, Inc. v. Public Service Commission
311 S.E.2d 137 (West Virginia Supreme Court, 1983)
Potomac Electric Power Co. v. Public Service Commission
457 A.2d 776 (District of Columbia Court of Appeals, 1983)
Application of Hawaii Elec. Light Co., Inc.
594 P.2d 612 (Hawaii Supreme Court, 1979)
State Ex Rel. Laclede Gas Co. v. Public Service Commission
535 S.W.2d 561 (Missouri Court of Appeals, 1976)
Zucker v. Bell Telephone Company of Pennsylvania
373 F. Supp. 748 (E.D. Pennsylvania, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
345 F. Supp. 80, 1972 U.S. Dist. LEXIS 12894, 1972 WL 233038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mountain-states-telephone-telegraph-co-v-public-utilities-commission-cod-1972.