State Ex Rel. Laclede Gas Co. v. Public Service Commission

535 S.W.2d 561, 1976 Mo. App. LEXIS 1922, 1976 WL 352276
CourtMissouri Court of Appeals
DecidedMarch 29, 1976
DocketKCD 27958
StatusPublished
Cited by24 cases

This text of 535 S.W.2d 561 (State Ex Rel. Laclede Gas Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Laclede Gas Co. v. Public Service Commission, 535 S.W.2d 561, 1976 Mo. App. LEXIS 1922, 1976 WL 352276 (Mo. Ct. App. 1976).

Opinion

WASSERSTROM, Judge.

The question here for decision is whether Laclede Gas Company should have been granted an interim rate increase by the Public Service Commission of Missouri pending determination by that Commission of whether a permanent rate increase should be allowed. This problem comes before a Missouri appellate court now for the first time.

On February 1, 1974, Laclede filed its application No. 18015 before the Commission for an increase in rates calculated to produce an additional $12,475,000 in additional revenue. This application and the proceedings thereon is referred to as the “permanent” rate case.

On February 15, 1974, Laclede filed a second proceeding, entitled “Application for Partial Increase after Hearing,” which was given the separate number No. 18021 and is referred to as the “interim” rate case. This latter application sought to increase revenues by $5,440,000 during the interim peri *564 od until action by the Commission in the permanent rate case. Laclede alleged that the interim increase had become necessary because it could no longer earn a fair return on the fair value of its property because of inflationary cost increases and because of a precipitous decline in revenue resulting from the national fuel conservation program. Applications were filed with the Commission by a number of public bodies and industries (including the “Industrial In-tervenors” who have appeared in this court) to intervene in the interim proceeding, which applications were all granted.

A one day hearing was held by the Commission on March 21, 1974, at which time Laclede offered testimony and statistical documents to sustain the allegations of its petition. In very brief summary, its evidence was that since 1969 when its rates had last been set by the Commission, Lac-lede had suffered a decline in rate of return on total invested capital and in the return on its common equity; that the costs of all types of financing had increased substantially with the result that the imbedded cost of the company’s debt had increased and would increase further; that because of inflationary increase in costs there was a net decrease in operating income; that because of conservation measures there had resulted a substantial load loss in therm use per customer; that earnings per share of $2.46 in the fiscal year of 1973 had dropped to $2.14 per share by the end of the calendar year 1973, and absent rate relief was projected to fall in fiscal 1974 to approximately $1.67 to $1.70 per share; that Lac-lede stock had fallen in value and had been selling below book value for about a year; that interest coverage on the company bonds had fallen. However, Laclede’s president admitted in his testimony that Lac-lede was able to arrange debt financing; that even if interim relief was not granted, Laclede would not become insolvent, be unable to serve its present customers, or be unable to pay dividends; further, that it had not been necessary for Laclede to reduce salaries or terminate any personnel; and the failure of the Commission to grant interim relief would not affect the credit rating of Laclede bonds. A staff accountant of the Commission testified that he had made a summary review of the Laclede application and exhibits and found nothing materially wrong with them as presented; no audit had been conducted by the Commission staff which had relied entirely upon the figures provided by the company.

On May 2,1974, the Commission issued an order denying the interim rate increase by a 3 to 2 vote. Laclede filed a motion for rehearing which was overruled and then filed petition for review in the circuit court of Cole County under the provisions of § 386.510. (All statutory references herein being to RSMo 1969.) While that proceeding was pending in the circuit court, the Commission on August 22, 1974, issued its order in the permanent rate case granting Laclede a rate increase in the amount of $11,350,000.

On December 30, 1974, the Circuit Court of Cole County entered its judgment affirming the decision of the Commission on the grounds that the Commission action was a proper exercise of its discretion and also on the basis that the Commission’s order in the permanent rate case had rendered the interim rate proceeding moot.

Laclede thereupon filed notice of appeal to the Missouri Supreme Court, setting forth in its Notice of Appeal that the Commission’s order constituted a confiscation of Laclede’s property in violation of its constitutional rights. On April 14, 1975, the Supreme Court ordered the transfer of the appeal to this court “in which jurisdiction is vested.”

I.

The Commission, the industrial in-tervenors and amicus curiae Jackson County all join in urging that this appeal be dismissed on the simple ground that the case has become moot. They argue that the permanent rate increase has already been granted by the Commission, that the permanent increase includes the relief sought by way of interim increase, that under the law the increase cannot be made retroactive

*565 to the interim period, February 15 to August 22,1974, and that since no relief can be granted, it is a futile exercise for this court to retain jurisdiction. They cite in support State ex rel. Capital City Water Co. v. Public Service Commission, 298 Mo. 524, 252 S.W. 446 (banc 1923).

Nevertheless, even though relief may no longer be available to Laclede by means of this proceeding, still the question here presented is a recurring one of great public concern. This is evidenced by the considerable number of interventions before the Commission in this court and the appearances in this court as amici curiae. Among the parties so appearing as amici are seven electrical utility companies, who point out that the problem raised herein by Laclede (which is a gas utility) also extends with like force to the electric utilities of this state, as evidenced by the “Union Electric order” issued by the Commission on March 29, 1974, in case No. 17965, denying interim relief. See also State ex rel. Gas Service Co. v. Public Service Commission, Mo.App. 536 S.W.2d 491, No. KCD27987, being decided concurrently herewith.

In its very nature, an interim rate request is merely ancillary to a permanent rate request, and in overwhelming probability the permanent rate request will have been granted before any denial of an interim increase can work its way to the point of decision by an appellate court. If the important legal propositions presented by this appeal are to be decided at the appellate level at all, it is apparent that jurisdiction for that purpose must be exercised despite the technical point of mootness. Because of these considerations, this case should be retained and decided. In re Marshall, 478 S.W.2d 1, 5 (Mo. banc 1972); O_ H_ v. French, 504 S.W.2d 269 (Mo.App.1973); Lawyers’ Association of St. Louis v. City of St. Louis, 294 S.W.2d 676 (Mo.App.1956).

II.

Logical order calls for consideration next of the contention by amicus curiae Jackson County that the Commission has no power to grant interim rate increases. If this contention be sound, then it would become unnecessary to consider anything further.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Monsanto Co. v. Public Service Commission
716 S.W.2d 791 (Supreme Court of Missouri, 1986)
Osage Outdoor Advertising, Inc. v. State Highway Commission
699 S.W.2d 791 (Missouri Court of Appeals, 1985)
State ex rel. Fischer v. Public Service Commission of Missouri
670 S.W.2d 24 (Missouri Court of Appeals, 1984)
Columbia Gas of West Virginia, Inc. v. Public Service Commission
311 S.E.2d 137 (West Virginia Supreme Court, 1983)
Mid-America Television Co. v. State Tax Commission
652 S.W.2d 674 (Supreme Court of Missouri, 1983)
Potomac Electric Power Co. v. Public Service Commission
457 A.2d 776 (District of Columbia Court of Appeals, 1983)
Application of Northwestern Bell Tel. Co.
326 N.W.2d 100 (South Dakota Supreme Court, 1982)
State Ex Rel. Missouri Public Service Co. v. Fraas
627 S.W.2d 882 (Missouri Court of Appeals, 1981)
Lester E. Cox Medical Center v. Labor & Industrial Relations Commission
608 S.W.2d 442 (Missouri Court of Appeals, 1980)
Colorado Municipal League v. Public Utilities Commission
591 P.2d 577 (Supreme Court of Colorado, 1979)
In Re Kauai Electric Division of Citizens Utilities Co.
590 P.2d 524 (Hawaii Supreme Court, 1978)
State ex rel. City of Cape Girardeau v. Public Service Commission
567 S.W.2d 450 (Missouri Court of Appeals, 1978)
State ex rel. Reser v. Rush
562 S.W.2d 365 (Supreme Court of Missouri, 1978)
Public Utility Commission of Texas v. City of Corpus Christi
555 S.W.2d 509 (Court of Appeals of Texas, 1977)
State ex rel. Gas Service Co. v. Public Service Commission
536 S.W.2d 491 (Missouri Court of Appeals, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
535 S.W.2d 561, 1976 Mo. App. LEXIS 1922, 1976 WL 352276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-laclede-gas-co-v-public-service-commission-moctapp-1976.