Moreno-Godoy v. Kartagener

7 F.4th 78
CourtCourt of Appeals for the Second Circuit
DecidedJuly 30, 2021
Docket19-1279
StatusPublished
Cited by25 cases

This text of 7 F.4th 78 (Moreno-Godoy v. Kartagener) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moreno-Godoy v. Kartagener, 7 F.4th 78 (2d Cir. 2021).

Opinion

19-1279 Moreno-Godoy v. Kartagener 1 IN THE

2 United States Court of Appeals 3 For the Second Circuit 4 ________ 5 AUGUST TERM, 2020 6 7 ARGUED: JUNE 2, 2021 8 DECIDED: JULY 30, 2021 9 10 No. 19-1279 11 12 LUIS FELIPE MORENO-GODOY, 13 Plaintiff-Appellant, 14 15 v. 16 17 STEVEN R. KARTAGENER, ESQ., 18 Defendant-Cross-Claimant-Appellee, 19 20 GALLET DREYER & BERKEY, LLP., 21 Defendant-Counter-Defendant-Appellee, 22 23 ROGER L. STAVIS, ESQ., 24 Defendant-Appellee, 25 26 ________ 27 28 Appeal from the United States District Court 29 For the Southern District of New York. 30 14-CV-07082 – Paul Engelmayer, District Judge. 31 32 ________ 33 34 19-1279 Moreno-Godoy v. Kartagener

1 Before: CALABRESI, MENASHI, Circuit Judges, AND COTE, District Judge. 1 2 ________ 3 4 Luis Felipe Moreno-Godoy and Monzer Al Kassar retained attorney Roger 5 L. Stavis of Gallet Dreyer & Berkey (“GDB”) for a flat fee of $125,000 to represent 6 them in a criminal appeal. Seeking additional legal support, they also retained 7 attorney Steven Kartagener for a flat fee of $100,000. Al Kassar’s wife, Raghdaa 8 Habbal, transferred both fees to the attorneys. Moreno-Godoy, Al Kassar, and 9 Habbal all assert that the $100,000 transferred to Kartagener belonged to 10 Moreno-Godoy. Then, when Kartagener was unable to work on the appeal, 11 Moreno-Godoy asked for the money back. Instead, Kartagener transferred it to 12 Stavis, who kept it. Moreno-Godoy subsequently initiated this action, alleging 13 breach of contract and quasi-contract claims. The district court granted summary 14 judgment to all three defendants, GDB, Stavis, and Kartagener. 15 We conclude that the district court erred in granting summary judgment to 16 defendants on Moreno-Godoy’s breach-of-contract claim because, under New 17 York law, Moreno-Godoy can maintain a breach-of-contract claim without any 18 showing that the $100,000 belonged to him. Although Moreno-Godoy’s quasi- 19 contract claims against Stavis and GDB do require a showing that he owned the 20 money, we further conclude that the district court erred in granting summary 21 judgment to those defendants on those claims because there is sufficient evidence 22 in the record from which a jury could conclude that the money indeed belonged 23 to Moreno-Godoy. Finally, we hold that summary judgment for Stavis in his 24 individual capacity was also inappropriate. 25 We therefore VACATE the grants of summary judgment to GDB, Stavis, 26 and Kartagener and REMAND for proceedings consistent with this opinion. 27

1Judge Denise Cote, of the United States District Court for the Southern District of New York, sitting by designation.

2 19-1279 Moreno-Godoy v. Kartagener

2 JOHN M. TANSKI, Axinn, Veltrop & Harkrider LLP (Drew A. Hiller,

3 Craig M. Reiser, on the brief), in support of Plaintiff-Appellant.

4 DAVID A. ROBINSON, Esq., in support of Defendant-Appellee Steven R.

5 Kartagener, Esq.

6 DAVID S. DOUGLAS, Gallet Dryer & Berkey LLP (Jared B. Foley, on the

7 brief), in support of Defendants-Appellees Gallete Dreyer & Berkey, LLP

8 and Roger L. Stavis, Esq. 9 10

11 CALABRESI, Circuit Judge:

12 After a jury convicted them of several federal crimes, Plaintiff-Appellant

13 Felipe Moreno-Godoy and Monzer Al Kassar entered into two separate retainer

14 agreements for appellate legal services. The first stipulated that the law firm

15 Gallet Dreyer & Berkey LLP (“GDB”) would provide them both with “all post-

16 verdict legal services” for a flat fee of $125,000 (“GDB Agreement”). JA 217. All

17 agree that the $125,000 paid to GDB belonged to Al Kassar. When Moreno-

18 Godoy expressed interest in adding an additional lawyer to their team, Moreno-

19 Godoy and Al Kassar brought on Steven R. Kartagener as additional counsel at

20 the suggestion of GDB partner Roger L. Stavis. They signed a second retainer

21 agreement (“Kartagener Agreement”) providing that Kartagener would

22 represent both men in post-verdict legal proceedings for a flat fee of $100,000.

23 Because both men were in prison, Al Kassar’s wife Raghdaa Habbal handled the

24 payment to the respective attorneys. Moreno-Godoy, Al Kassar, and Habbal all

25 assert that the $100,000 paid to Kartagener belonged to Moreno-Godoy.

3 19-1279 Moreno-Godoy v. Kartagener

1 But Kartagener never provided any legal services. Nor did he return the

2 $100,000 fee, as Moreno-Godoy requested. Instead, he transferred it to Stavis,

3 who in due course remitted them to GDB.

4 Moreno-Godoy brought this lawsuit. He alleged breach of contract against

5 Stavis, GDB, and Kartagener, as well as quasi-contract claims for unjust

6 enrichment, money had and received, and constructive trust against Stavis and

7 GDB. The district court (Engelmayer, J.) believed that Moreno-Godoy’s claims all

8 turned on whether he could prove ownership of the $100,000, because otherwise,

9 Moreno-Godoy could not prove that he was damaged by the defendants’ breach.

10 The district court did not find enough admissible evidence in the record for the

11 question of Moreno-Godoy’s ownership of the money to reach a jury, and so

12 granted summary judgment to defendants.

13 We see things differently. To prove damages for his breach-of-contract

14 claim, Moreno-Godoy did not need to make any showing that he owned the

15 $100,000. See Markson v. Markson’s Furniture Stores, 195 N.E. 824, 826 (N.Y. 1935).

16 Rather, he was entitled to expectation damages, so long as he could “show a

17 stable foundation for a reasonable estimate” of Kartagener’s services. Tractebel

18 Energy Mktg., Inc. v. AEP Power Mktg., Inc., 487 F.3d 89, 110 (2d Cir. 2007); see also

19 Freund v. Washington Square Press, Inc., 34 N.Y.2d 379, 383 (1974) (articulating the

20 “stable foundation for reasonable estimate” standard); Broadway Photoplay Co. v.

21 World Film Corp., 225 N.Y. 104, 109 (1919) (requiring “some basis of computation”

22 for expectation damages).

23 To prevail on his quasi-contract claims, however, Moreno-Godoy did need

24 to prove that he owned the $100,000. On our de novo review of the record, we find

4 19-1279 Moreno-Godoy v. Kartagener

1 sufficient evidence for these claims to proceed. If Moreno-Godoy can convince a

2 jury that he owned the funds paid to Kartagener, he may prevail on the quasi-

3 contract claims against Stavis and GDB, assuming, of course, that he can also

4 satisfy the other elements of those claims.

5 Finally, the district court granted summary judgment to Stavis in his

6 personal capacity on the grounds that New York Partnership Law § 26(a) shields

7 him from personal liability. Based on the record before us, we believe a jury

8 could find that Stavis committed a “wrongful act or misconduct” for which he

9 could be held personally liable under New York Partnership Law § 26(b).

10 We therefore VACATE the district court’s grants of summary judgment to

11 GDP, Kartagener, and Stavis, and REMAND for proceedings consistent with this

12 opinion.

13 BACKGROUND

14 A. Factual Background

15 In November of 2008, a federal jury convicted Felipe Moreno-Godoy and

16 Monzer Al Kassar of several criminal charges, including conspiracy to kill

17 officers and employees of the United States, and money laundering. They asked

18 their trial counsel, Roger L. Stavis, Esq., of the firm Gallet Dreyer & Berkey

19 (“GDB”) to represent both of them in all post-conviction proceedings. While

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
7 F.4th 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moreno-godoy-v-kartagener-ca2-2021.