McCloskey & Company, Inc. v. Wright

363 F. Supp. 223, 1973 U.S. Dist. LEXIS 13097
CourtDistrict Court, E.D. Virginia
DecidedJune 20, 1973
DocketCiv. A. 102-73-R
StatusPublished
Cited by18 cases

This text of 363 F. Supp. 223 (McCloskey & Company, Inc. v. Wright) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCloskey & Company, Inc. v. Wright, 363 F. Supp. 223, 1973 U.S. Dist. LEXIS 13097 (E.D. Va. 1973).

Opinion

*225 MEMORANDUM

MERHIGE, District Judge.

McCloskey & Company-C. H. Leavell Company, a joint venture (hereafter “builders”) brings this action against Marcellus Wright, J., and other architects (hereafter “architects”) for damages allegedly incurred by virtue of faulty construction design. Jurisdiction is attained by virtue of 28 U.S.C. § 1332. The parties are presently before the Court pursuant to the architects’ motion to dismiss. Respective counsel have briefed the issues raised thereby, and it is upon same that this matter is ripe for disposition.

The basic and undisputed facts are as follows. On June 30, 1966 the United States contracted with the architects for the design of a post office building in Richmond, Virginia and the supervision of its construction. Pursuant to that contract the architects developed plans and specifications. Subsequently plaintiff builders were awarded a contract from the United States to build the post office. In February of 1968 the United States assigned to the builders the drawings and specifications prepared by the architects for construction of the project. The builders proceeded to erect the post office upon the architects’ design. The United States took possession of the post office on October 1, 1970 but withheld formal acceptance of the project because of a defective roof. Builders allege that they have been forced to incur additional expense to repair the roof and seek damages here from the architects on the premise that construction inadequacies were caused by faulty design and/or construction supervision by the architects. Builders also seek indemnity from the architects for legal expenses involving litigation with the roofing subcontractor.

Specifically, the amended complaint sets forth five theories of recovery:

1. Count I: breach of warranty and breach of contract,
2. Count II: breach of contract for a third party beneficiary,
3. Count III: negligence in design,
4. Count IV: negligence in supervision,
5. Count V: indemnity for litigation expenses incurred by builders in suits against them by the roofing subcontractor.

The legal issues posed with respect to each count will be considered seriatim.

Count I

The gravamen of Count I is that architects warranted that the project design was fit, accurate and complete and that for the alleged breach of said warranty, builders may recover expenses caused it in repairing the roof. Architects have moved to dismiss Count I on several grounds, but in view of the Court’s disposition of their plea of the statute of limitations only the latter need be treated.

The applicable statute of limitations is supplied by the law of Virginia, the lex fori, see Hospelhorn v. Corbin, 179 Va. 348, 19 S.E.2d 72 (1942). Va. Code § 8-13 provides a period of limitations of five years for actions based upon contracts in writing not under seal. Under familiar principles of law, the statute begins to run from the time of a violation or breach of a legal duty or obligation owed a plaintiff by a defendant. Caudill v. Wise Rambler, Inc., 210 Va. 11, 168 S.E.2d 257 (1969). See also Kilduff v. United States, 248 F.Supp. 310 (E.D.Va.1961).

The architects allege in support of their motion that up to the date of the assignment of plans, the government had a cause of action, if any, for breach of warranty. This theory impliedly states that the violation of the warranty occurred at the tendering to the government of the design, discussion infra. They therefore assert that builders’ claim should be measured from no later than the date of assignment, 2/12/68. The builders agree in part with this reasoning but contend that the assignment was not effective until March 11, 1968, when they accepted the assignment by *226 the government of the plans and drawings. Because the complaint was filed March 2, 1973, under this theory of arising obligation developed by counsel, the date of effective transfer of obligations is crucial. Builders also allege, however, that the breach did not precede the assignment of the plans but rather that it occurred at the time the government required McCloskey to do corrective work. While that date is not specified, it obviously was subsequent to the acceptance of the assignment and within the five year period.

These contentions in turn raise two issues. First, when did the alleged breach occur, at the time the plans were submitted to the government or at the time the present plaintiff suffered monetary injury? Second, when did the legal obligation, which was allegedly breached, arise, on February 12, 1968 (date of assignment), March 11, 1968 (date of acceptance), or from the date the obligation arose to builders’ assignor ?

In Richmond Redevelopment and Housing Authority v. Laburnum Construction Corporation, 195 Va. 827, 80 S.E.2d 574 (1954), the Virginia Supreme Court ruled that a property damage claim upon a theory of tortious breach of warranty arises at the time the defect or condition causing the breach occurs. Thus in Laburnum, a defective gas pipe was installed six feet under ground. Several years later gas leaked from the pipe and caused an explosion. Plaintiff had no knowledge that the pipe was defective and it was undisputed that acquiring that knowledge before the explosion would be difficult. The Court held that the cause accrued from the time the pipe was instálled because the warranty applied to the pipe. While damages caused by the explosion were “consequential” and thus possibly recoverable, the direct damage in violation of the warranty giving rise to the cause of action was the installation of the defective pipe. Moreover, the Court added, significantly for these purposes, that “the difficulty in ascertaining that a cause of action exists plays no part in the general rule.” This ruling was subsequently reaffirmed in Caudell, 168 S.E.2d 257, and recognized as controlling by the United States Court of Appeals for the Fourth Circuit in Sides v. Richard Machine Works, Inc., supra, 406 F.2d 445 (1969). While Laburnum strictly deals with the tortious act of breaching a contract, rather than liability under the contract for breach of same, the conclusion that the same principle applies to accrual of the cause of action is inescapable.

Applying this reasoning to the present matter, the breach of warranty occurred at the time the architects tendered allegedly defective plans to the government. The fact that the defect may not have been ascertainable until a later date is of no consequence under the Laburnum rule. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heckler & Koch, Inc. v. German Sport Guns GmbH
71 F. Supp. 3d 866 (S.D. Indiana, 2014)
Lone Mountain Processing, Inc. v. Bowser Morner, Inc.
94 F. App'x 149 (Fourth Circuit, 2004)
Thweatt v. Jackson
838 S.W.2d 725 (Court of Appeals of Texas, 1992)
Tucker v. Metcalf & Associates
25 Va. Cir. 334 (Albemarle County Circuit Court, 1991)
Welch v. Engineers, Inc.
495 A.2d 160 (New Jersey Superior Court App Division, 1985)
Lehner v. United States
1 Cl. Ct. 408 (Court of Claims, 1983)
Picture Lake Campground, Inc. v. Holiday Inns, Inc.
497 F. Supp. 858 (E.D. Virginia, 1980)
A. J. Aberman, Inc. v. Funk Building Corp.
420 A.2d 594 (Superior Court of Pennsylvania, 1980)
Byrne v. Autohaus on Edens, Inc.
488 F. Supp. 276 (N.D. Illinois, 1980)
Davidson & Jones, Inc. v. County of New Hanover
255 S.E.2d 580 (Court of Appeals of North Carolina, 1979)
Comptroller Ex Rel. Virginia Military Institute v. King
232 S.E.2d 895 (Supreme Court of Virginia, 1977)
Smithfield Packing Co., Inc. v. Dunham-Bush, Inc.
416 F. Supp. 1156 (E.D. Virginia, 1976)
Federal Reserve Bank of Richmond v. Wright
392 F. Supp. 1126 (E.D. Virginia, 1975)
Insurance Co. of North America v. General Electric Co.
376 F. Supp. 638 (W.D. Virginia, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
363 F. Supp. 223, 1973 U.S. Dist. LEXIS 13097, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccloskey-company-inc-v-wright-vaed-1973.