A. J. Aberman, Inc. v. Funk Building Corp.

420 A.2d 594, 278 Pa. Super. 385, 1980 Pa. Super. LEXIS 2647
CourtSuperior Court of Pennsylvania
DecidedJune 6, 1980
Docket39
StatusPublished
Cited by45 cases

This text of 420 A.2d 594 (A. J. Aberman, Inc. v. Funk Building Corp.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. J. Aberman, Inc. v. Funk Building Corp., 420 A.2d 594, 278 Pa. Super. 385, 1980 Pa. Super. LEXIS 2647 (Pa. Ct. App. 1980).

Opinion

SPAETH, Judge:

This is an appeal from an order refusing to take off a compulsory nonsuit. The issue is whether the lower court correctly ruled that appellants’ action was barred by the statute of limitations.

In 1964, appellee Funk Building Corporation entered into a written contract with appellants for the construction of a shopping center. The contract provided for the installation of a twenty year bonded roof. 1 Funk subcontracted the roofing work to appellee General Roofing Company, and appellee Koppers Company provided the bond. The roof was installed and the building was completed by June 1965. The roof began to leak in 1965 and continued to leak thereafter. Funk originally repaired the leaks, but in September 1967 refused to undertake any further repairs and informed appellants to look elsewhere for relief. Thereafter, appellants hired Jack Josowitz, a local roofer, to repair the leaks. Josowitz repaired leaks from November 1967 until May 1973. All attempts at repair ultimately proved futile, however, and in June 1973 appellants had a new roof installed. They filed their complaint in the present action against Funk on December 21, 1973. General Roofing and Koppers were joined as additional defendants on February 24, 1974.

After appellants had finished presenting their evidence, appellees moved for and were granted a compulsory nonsuit on the ground that the action was barred by the six year statute of limitations applicable to actions on contracts. Appellants first argue that this statute was not applicable. Appellants next argue that even if the six year statute was *389 applicable, a nonsuit should not have been entered, for the jury might have found that the statute had been tolled.

-1-

In ruling that appellants’ action was barred, the lower court applied the six year statute of limitations set forth in the Act of March 27, 1713, 1 Sm.L. 76, § 1, 12 P.S. § 31 (Purdon’s 1953) (Act of 1713), 2 which provides in pertinent part that “[a]ll actions . . . shall be commenced and sued . . . within six years next after the cause of such actions or suit and not after.” Appellants argue that the lower court should have applied the twelve year provision contained in the Act of December 22, 1965, P.L. 1183, § 1, 12 P.S. § 65.1 (Purdon’s Supp.1977) (Act of 1965). 3 The Act of 1965 provides:

“§ 65.1 Twelve years
No action (including proceedings) whether in contract, in tort or otherwise, to recover damages:
(1) For any deficiency in the design, planning, supervision or observation of construction or construction of an improvement to real property,
(2) For injury to property, real or personal, arising out of any such deficiency,
(3) For injury to the person or for wrongful death arising out of any such deficiency, or
(4) For contribution or indemnity for damages sustained on account of any injury mentioned in clauses (2) and (3) hereof, shall be brought against any person lawfully performing or furnishing the design, planning, supervision or observation of construction, or construction of such improvement more than twelve years after completion of such an improvement.
§ 65.2 Injury, twelfth year after improvement completed
*390 Notwithstanding the provisions of section [65.1], in the case of such an injury to property or the person, or such an injury causing wrongful death, which injury occurred during the twelfth year after such completion, an action in tort to recover damages for such an injury or wrongful death may be brought within two years after the date on which such injury occurred: Provided, That in the case of wrongful death, such action shall also be brought within one year of the date of death. In no event, however, may any of such actions be brought more than fourteen years after the completion of construction of such an improvement.
§ 65.3 Extending limitation periods
Nothing in this act shall be construed as extending the period prescribed by the laws of this Commonwealth for the bringing of any action.
§ 65.4 Defense by person in possession or control of improvement
The limitation prescribed by this act shall not be asserted by way of defense by any person in actual possession or the control, as owner, tenant or otherwise, of such an improvement at the time any deficiency in such an improvement constitutes the proximate cause of the injury or death for which it is proposed to bring action.
§ 65.5 Definitions
As used in this act, the term ‘person’ shall mean an individual, corporation, partnership, business trust, unincorporated organization, association, professional association or joint stock company.”

Appellants’ argument is without merit. By its own terms, the Act of 1965 provides that “[n]othing in this act shall be construed as extending the period prescribed by the laws of this Commonwealth for the bringing of any action,” 12 P.S. § 65.3, and in Misitis v. Steel City Piping Co., 441 Pa. 339, 272 A.2d 883 (1971), the Supreme Court specifically ruled that the Act of 1965 did not create a procedural change in the statute of limitations but a substantive change. See Comment, Limitations of Action Statutes for Architects and *391 Builders-Blueprint for Non-Action, 18 Cath.U.L.Rev. 361, 384 (1969) (statutes effect change in substantive law). A true statute of limitations normally commences to run from the date of injury. The Act of 1965, however, protects certain persons from all claims arising more than twelve years after construction regardless of when the cause of action or injury arises. See Freezer Storage v. Armstrong Coke Co., 476 Pa. 270, 382 A.2d 715 (1978); Misitis v. Steel City Piping Co., supra ; Comment, supra at 363. See also Jostan Aluminum Prod. Co., Inc. v. Mount Carmel District Indus. Fund, 256 Pa.Super. 353, 389 A.2d 1160 (1978); Leach v. Philadelphia Sav. Fund Society, 234 Pa.Super. 486, 340 A.2d 491 (1975); General State Authority v. Kline, 29 Pa.Cmwlth. 232, 370 A.2d 402 (1977). Thus, for example, if an injury should occur after the twelve year period, the particular statute of limitations applicable to the action might not commence to run until the date of injury, but the bar of the Act of 1965 would preclude any action against the persons protected by the Act without regard to whether the action was timely filed under that statute of limitations. See Misitis v. Steel City Piping Co., supra

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Borel Builders, Inc. v. Burke, B.&P.
Superior Court of Pennsylvania, 2023
Tong-Summerford, A. v. Abington Mem. Hosp.
Superior Court of Pennsylvania, 2018
Bobbett, C. v. Fosco, A.
Superior Court of Pennsylvania, 2014
Sabella, D. v. Appalachian Development Corp.
103 A.3d 83 (Superior Court of Pennsylvania, 2014)
Montgomery v. South Philadelphia Medical Group, Inc.
656 A.2d 1385 (Superior Court of Pennsylvania, 1995)
Romeo & Sons, Inc. v. P.C. Yezbak & Son, Inc.
652 A.2d 830 (Supreme Court of Pennsylvania, 1995)
Resolution Trust Corp. v. Farmer
865 F. Supp. 1143 (E.D. Pennsylvania, 1994)
CLL Associates Ltd. Partnership v. Arrowhead Pacific Corp.
497 N.W.2d 115 (Wisconsin Supreme Court, 1993)
Romeo & Sons, Inc. v. P.C. Yezbak & Son, Inc.
617 A.2d 1320 (Superior Court of Pennsylvania, 1992)
Garvey v. Rosanelli
601 A.2d 1334 (Commonwealth Court of Pennsylvania, 1992)
Gallucci v. Phillips & Jacobs Inc.
13 Pa. D. & C.4th 413 (Philadelphia County Court of Common Pleas, 1991)
Amodeo v. Ryan Homes, Inc.
595 A.2d 1232 (Superior Court of Pennsylvania, 1991)
Bowser v. Lee Hospital
582 A.2d 369 (Supreme Court of Pennsylvania, 1990)
Levenson v. Souser
557 A.2d 1081 (Supreme Court of Pennsylvania, 1989)
Francabandera v. Indian Mountain Lake Development Corp.
48 Pa. D. & C.3d 246 (Monroe County Court of Common Pleas, 1988)
Cucchi v. Rollins Protective Services Co.
546 A.2d 1131 (Supreme Court of Pennsylvania, 1988)
Berns Const. Co., Inc. v. Miller
491 N.E.2d 565 (Indiana Court of Appeals, 1986)
Dillon County School District Number Two v. Lewis Sheet Metal Works, Inc.
332 S.E.2d 555 (Court of Appeals of South Carolina, 1985)
Leibowitz v. H.A. Winston Co.
493 A.2d 111 (Supreme Court of Pennsylvania, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
420 A.2d 594, 278 Pa. Super. 385, 1980 Pa. Super. LEXIS 2647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-j-aberman-inc-v-funk-building-corp-pasuperct-1980.