Marketing & Management Information, Inc. v. United States

62 Fed. Cl. 126, 2004 U.S. Claims LEXIS 243, 2004 WL 2095568
CourtUnited States Court of Federal Claims
DecidedSeptember 20, 2004
DocketNo. 99-1094C
StatusPublished
Cited by6 cases

This text of 62 Fed. Cl. 126 (Marketing & Management Information, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marketing & Management Information, Inc. v. United States, 62 Fed. Cl. 126, 2004 U.S. Claims LEXIS 243, 2004 WL 2095568 (uscfc 2004).

Opinion

OPINION

BRUGGINK, Judge.

This case arises out of a contract awarded by the Defense Commissary Agency (“DCA”) to plaintiff, Marketing and Management Information, Inc. (“MMI”), on October 26,1995, to purchase and process scanner data collected by military commissaries. It is the termination of that contract which is in dispute. In this court’s prior opinion, Marketing & Management Information, Inc. v. United States, 57 Fed.Cl. 665 (2003), we ruled that the Brooks Automatic Data Processing Act (“Brooks Act”) did not apply to the contract and thus the contract was not void ab initio, that the government was not entitled to terminate the contract for convenience, and that the government did not act in bad faith when it cancelled its solicitation. We went on to [128]*128hold that, in the absence of the power to terminate for convenience, “the government’s termination constituted a breach.” Id. at 675. The issue of relief was not addressed. Trial is currently set for November 2, 2004.

Pending are the parties’ motions in limine on four issues: when the breach of contract occurred, whether the two option years on the contract should be included for purposes of calculating damages, whether plaintiff is entitled to recover interest on any damages awarded, and whether plaintiffs proposed expert witness, Mr. Kenneth Metcalfe, is qualified to testify as to damages. Oral argument was held on September 9, 2004. For reasons set out below, we conclude that the contract was breached on September 30, 1996, that plaintiff is barred as a matter of law from asserting damages flowing out of the two option years, that plaintiff is entitled to interest on any damage award, and that the qualifications of Mr. Metcalfe will be determined during trial. In addition, defendant raised certain defenses in its motion in limine, which, although more properly the subject of a motion for summary judgment, we address below.

BACKGROUND

DCA, an agency of the Department of Defense charged with operating military commissaries, issued Request for Proposal (“RFP”) DCA01-94-R-0068 on June 1, 1995, for a sales contract pursuant to which DCA would release product movement sales data from its commissaries to the contractor in exchange for a share in the revenue generated by sale of that information and for “Analytical Support Services for Category Management.” The RFP, therefore, contemplated no money flowing from the agency to the contractor.

The RFP provided for an award to a single contractor who would have the exclusive right to process and sell product movement sales data from the commissaries operated by DCA. The RFP called for a base term of three years with two one-year option periods at the election of DCA. The RFP intentionally omitted a termination for convenience clause.

MMI submitted a proposal to DCA in August 1995. A.C. Nielsen Company (“Nielsen”), Information Resources, Inc. (“IRI”), and Management Science Associates, Inc. (“MSA”) also submitted proposals. DCA awarded the contract to MMI on October 26, 1995. Section B of the contract, which calculates the amount payable to DCA, refers to the basic contract period as running from January 1,1996, to December 31, 1998. Section C, labeled as “Statement of Work,” does not give specific dates for performance but simply states that the basic contract period will be “three years” in order to defray the contractor’s initial start-up costs. Section F, labeled “Deliveries or Performance,” also states that the term of the contract runs from January 1, 1996, to December 31, 1998.

On November 6, 1995, Nielsen filed a protest at the General Services Administration Board of Contract Appeals (“GSBCA”) challenging the award to MMI. IRI and MSA intervened to support the protest. In response to the protest, the contracting officer issued a stop work order on November 14, 1995. MMI was ordered to cease all work for “a period not to exceed 90 calendar days ... or until this order is cancelled by the Contracting Officer.” In order to avoid a disruption in services, a previous contract between MMI and the Air Force for processing raw scanner data was extended from December 31,1995, to March 31,1996.1

In its protest, Nielsen argued that the solicitation was void because it failed to comply with the Brooks Act, which required federal agencies to obtain a delegation of procurement authority from the General Services Administration (“GSA”) before acquiring automatic data processing equipment (“ADPE”) or services. Brooks Automatic Data Processing Act, 40 U.S.C. § 759 (1995) (repealed 1996). On February 23, 1996, GSBCA held that the contract was, indeed, void ab initio because it was subject to, but did not comply with, the Brooks Act. DCA was directed to reassess the procurement in [129]*129accordance with the Brooks Act and appropriate regulations.

MMI appealed GSBCA’s decision to the Federal Circuit on March 21, 1996.2 During the pendency of that appeal, on September 30, 1996, DCA issued Amendment 0002 to the RFP cancelling the solicitation. DCA and the successful protestors then moved to dismiss MMI’s appeal. On May 19, 1998, the Federal Circuit dismissed the appeal as moot and simultaneously vacated GSBCA’s decision. Mktg. & Mgmt. Info., Inc. v. Beale, No. 96-1270, 1998 WL 314626, 1998 U.S.App. LEXIS 10199 (Fed.Cir. May 19, 1998).

On June 12,1998, MMI sent a letter to the contracting officer expressing its desire to perform the contract as awarded and explaining that, because the Federal Circuit had vacated the GSBCA decision, there was no further bar to MMI performing on the contract. On the same day, however, DCA sent a “Notice of Termination” to MMI. In the notice, DCA explained that it considered the Federal Circuit’s dismissal to have “recognized that ... the agency’s cancellation of the solicitation in September of 1996 constituted a withdrawal of the contract,” and furthermore, that the cancellation of the solicitation effectively terminated the contract for the convenience of the government.

On September 10, 1998, MMI submitted a certified claim for approximately $44.6 million in damages. The contracting officer issued a final decision denying the claim on February 25, 1999. Plaintiff filed this action on April 2, 1999. The case was transferred to this judge in May 2001.

DISCUSSION

Date of Breach

Defendant asks the court to determine that breach could not have occurred prior to June 12, 1998, when the contracting officer issued the notice of termination. The underlying argument is that no breach could have occurred between the time that GSBCA ruled the contract void ab initio (February 23, 1996) and the subsequent vacation of that decision by the Federal Circuit (May 18, 1998). In effect, defendant claims that the GSBCA decision shields it from a claim of breach prior to the time the Federal Circuit vacated the GSBCA decision. It follows, according to defendant, that only action taken after the GSBCA decision was vacated could constitute a breach.

Plaintiffs motion asks the court to find that the date of breach was April 1, 1996— the date the prior contract expired and, it alleges, performance under the new contract should have commenced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mecom v. Morris
N.D. Oklahoma, 2022
East Coast Resources, LLC v. Town of Hempstead
707 F. Supp. 2d 401 (E.D. New York, 2010)
Terrell v. District of Columbia
703 F. Supp. 2d 17 (District of Columbia, 2010)
Magic Brite Janitorial v. United States
72 Fed. Cl. 719 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
62 Fed. Cl. 126, 2004 U.S. Claims LEXIS 243, 2004 WL 2095568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marketing-management-information-inc-v-united-states-uscfc-2004.