EDP Enterprises, Inc. v. United States

56 Fed. Cl. 498, 2003 U.S. Claims LEXIS 144, 2003 WL 21354617
CourtUnited States Court of Federal Claims
DecidedMay 30, 2003
DocketNo. 03-1281C
StatusPublished
Cited by5 cases

This text of 56 Fed. Cl. 498 (EDP Enterprises, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EDP Enterprises, Inc. v. United States, 56 Fed. Cl. 498, 2003 U.S. Claims LEXIS 144, 2003 WL 21354617 (uscfc 2003).

Opinion

ORDER DENYING TEMPORARY RESTRAINING ORDER

FIRESTONE, Judge.

Pending before the court is plaintiff EDP Enterprises, Inc.’s (“plaintiffs”) motion for a temporary restraining order. The plaintiff [499]*499seeks to enjoin the government from commencing activities on contract no. DABJ41-03-D-0003 (“interim contract”), a contract for food services for the Department of Army, Fort Riley, Kansas (“Army” or “government”). Plaintiff objects to the bundled-service form of the solicitation for the interim contract. Plaintiff bases its challenge to the form of the bundled-services interim contract solicitation on its success before the General Accounting Office (“GAO”) over a protest of A-76 solicitation no. DAKF19-99-R-0014 (“A-76 RFP”), a solicitation for many of the same services as the interim contract that it is now protesting. A hearing on the TRO was held on May 29, 2003, at which time Logistics & Environmental Services Corporation (“LESCO”), the interim contract awar-dee, was allowed to intervene.

For the reasons that follow, the plaintiffs motion is DENIED.

BACKGROUND

The following facts are not disputed. The plaintiff is the incumbent contractor to provide food services to the Army at Fort Riley, Kansas. Its contract, scheduled to end on June 1, 2003, contained a negotiated provision for two one-month contract extensions if the Army saw fit. The Army decided not to exercise the option to extend the contract beyond the June 1, 2003 end date.

In 1999, the Army issued the A-76 RFP seeking certain logistics services, such as food services and maintenance, transportation, and warehousing services. The services sought were bundled into a single solicitation because the Army had determined the single-contract approach was more cost effective. The A-76 solicitation was put on hold during the appeal process.

While the A-76 RFP was on hold, in April 2002, the Army issued the solicitation for the subject interim contract. The solicitation for the interim contract called for the same bundling of services called for in the A-76 RFP. Proposals for the interim contract were received in May 2002. On March 7, 2003, the Army awarded the contract to LESCO, the only responsive bidder. Plaintiff does not dispute that it did not object to the bundling of services in the interim contract solicitation during the entire ten months between issuance of the interim contract solicitation and the award of the interim contract.

Plaintiff did, however, object to the bundling of services under the A-76 RFP once the hold was lifted. On February 11, 2003, before the closing date, plaintiff filed a protest with the GAO concerning the A-76 RFP. The plaintiff argued that the bundling of food services with the other logistic services was improper. The GAO issued its decision sustaining the plaintiffs protest on May 19, 2003, agreeing with the plaintiff that the government failed to provide a reasonable justification that bundling was necessary.

Armed with the GAO decision from the challenged A-76 RFP, the plaintiff filed its complaint and motion for a temporary restraining order on May 28, 2003 in this court challenging the interim contract on the same basis. At the hearing on May 29, 2003, the court heard from counsel and the contracting officer from Fort Riley, Kansas.

DISCUSSION

A. Standard of Review

Motions for temporary restraining orders are treated in accordance with the rules governing injunctions. Rule 65 of the United States Court of Federal Claims.1

In order to obtain a temporary restraining order, the plaintiff must show the following:

(1) it will suffer irreparable injury unless the temporary restraining order issues; (2) the threatened injury to the moving party outweighs any damage to the opposing party; (3) the temporary restraining order, if issued, will not be adverse to the public interest; and (4) a substantial likelihood exists that the moving party will prevail on the merits.

[500]*500OAO Corp. v. United States, 49 Fed.Cl. 478, 480 (2001); Cincom Sys., Inc. v. United States, 37 Fed.Cl. 266, 268 (1997). A temporary restraining order is an “extraordinary and drastic remedy, one that should not be granted unless the movant, by a clear showing, carries the burden of persuasion.” Ma-zurek v. Armstrong, 520 U.S. 968, 972, 117 S.Ct. 1865, 138 L.Ed.2d 162 (1997) (citing 11A C. Wright, A. Miller, & M. Kane, Federal Practice and Procedure § 2948 129-130 (2d ed.1995)); Minor Metals, Inc. v. U.S., 38 Fed.Cl. 379, 381 (1997) (citing Golden Eagle Refining Co. v. United States, 4 Cl.Ct. 622, 624 (1984)).

B. Plaintiff is not entitled to a temporary restraining order

The government and LESCO argue that plaintiff does not have any likelihood of success on the merits on the grounds that its bid protest is untimely as a matter of law.2 Specifically, the government and LESCO argue that under the GAO rule governing bid protests, a protestor must file its protest based on errors on the face of a solicitation prior to the close of the solicitation. The GAO rule, § 21.2 Time for filing, states:

(a)(1) Protests based upon alleged improprieties in a solicitation which are apparent prior to bid opening or the time set for receipt of initial proposals shall be filed prior to bid opening or the time set for receipt of initial proposals. In procurements where proposals are requested, alleged improprieties which do not exist in the initial solicitation but which are subsequently incorporated into the solicitation must be protested not later than the next closing time for receipt of proposals following the incorporation.

4 C.F.R. § 21.2(a)(1) (2003). According to the government and LESCO, every court to examine the issue has concluded that where, as here, the error complained of is apparent on the face of the solicitation, the protestor must file its protest before the receipt of proposals or at the latest before award. See ABF Freight System, Inc. v. United States, 55 Fed.Cl. 392, 399 (2003) (citing North Carolina Div. of Servs. For Blind v. United States, 53 Fed.Cl. 147 (2002); Aerolease Long Beach v. United States, 31 Fed.Cl. 342, aff'd 39 F.3d 1198, 1994 WL 572795 (1994)); see also MVM, Inc. v. United States, 46 Fed.Cl. 126, 130 (2000) (citations omitted). Because plaintiffs bid protest action was filed after award, the government and LES-CO contend that the court will ultimately be required to dismiss the protest as untimely.

The plaintiff argues that this court is not bound to follow the GAO rule and that the GAO rules, themselves, do not necessarily bar a post-award protest where the issue is significant. Plaintiff argues that this case presents such a situation. The plaintiff contends that because the GAO sustained the protest against the A-76 RFP, which had identical bundled services, that decision provides a justification for not following the ordinary GAO rule, and that this court should allow the protest to go forward.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geo Group, Inc. v. United States
100 Fed. Cl. 223 (Federal Claims, 2011)
Jones Automation, Inc. v. United States
92 Fed. Cl. 368 (Federal Claims, 2010)
Marketing & Management Information, Inc. v. United States
62 Fed. Cl. 126 (Federal Claims, 2004)
Software Testing Solutions, Inc. v. United States
58 Fed. Cl. 533 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
56 Fed. Cl. 498, 2003 U.S. Claims LEXIS 144, 2003 WL 21354617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edp-enterprises-inc-v-united-states-uscfc-2003.