Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, a Joint Venture

773 F.2d 633, 1985 U.S. App. LEXIS 23566
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 11, 1985
Docket85-4125
StatusPublished
Cited by60 cases

This text of 773 F.2d 633 (Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, a Joint Venture) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, a Joint Venture, 773 F.2d 633, 1985 U.S. App. LEXIS 23566 (5th Cir. 1985).

Opinion

JOHNSON, Circuit Judge:

Parsons-Gilbane appeals from an order of the district court staying pending arbitration proceedings. On appeal, Parsons-Gilbane asserts that the district court erroneously concluded that a dispute with Mar-Len of Louisiana, Inc. (Mar-Len) regarding the validity of certain contract modifications is beyond the scope of an arbitration agreement between the parties. This Court finds that the dispute is subject to the party’s arbitration agreement. The order of the district court is vacated and remanded.

I. BACKGROUND

Acting as construction manager of the Department of Energy’s Strategic Petroleum Reserve Project, Parsons-Gilbane contracted with Mar-Len of Louisiana, Inc. on April 28, 1981, to construct and install a fire and flushwater system at West Hack-berry, Louisiana. The original contract between Parsons-Gilbane and Mar-Len provided that Mar-Len would complete construction and testing of the system by December 18, 1981, and would be paid $4,387,-500.

Eventually, the parties added thirty-nine modifications to the basic contract. These modifications increased the contract price to $5,607,205.30 and extended the completion date for the contract work to January 29, 1982. Two of these modifications are central to the current dispute. In Modification 22, Parsons-Gilbane granted Mar-Len a waiver of a backfill specification that Mar-Len considered expensive and time consuming. The contract originally required that pipeline hydrostatic testing be done before backfilling was accomplished. Modification 22 granted Mar-Len a performance time extension and a change to allow post-back-fill testing. In return, Mar-Len agreed to waive certain delay claims.

On September 3, 1982, after Mar-Len’s activities at the worksite had ceased, Mar-Len delivered to Parsons-Gilbane a seven-volume claim package alleging various deficiencies and inefficiencies and requiring that Mar-Len receive an additional $6,153,-629.25 for performance of the contract work. Attempts to resolve this dispute concerning the amount of compensation due Mar-Len for its performance began shortly after the claim package was reviewed by Parsons-Gilbane and government auditors, but only a partial compromise was reached. This compromise became Modification 39. Modification 39 granted Mar-Len an additional $300,000 in compensation for work done at the site which Mar-Len claimed was beyond the scope of its contractual responsibilities. Mar-Len later repudiated Modifications 22 and 39 alleging that they were obtained without its consent due to the exertion of economic duress by Parsons-Gilbane.

The Parsons-Gilbane/Mar-Len contract contains the following language governing the resolution of disputes between the parties:

“ARTICLE XIY — Disputes (July 1979)
1.0 Any dispute arising under this subcontract that is not settled by agreement of the parties, or pursuant to the administrative relief provided for in the following paragraphs of this Article, shall be settled by arbitration as provided in Clause 5.0 of this Article.
5.0 In the event of any dispute not settled by agreement of the parties, or pursuant to the administrative relief provided for in the preceding Paragraphs 1.0, 2.0, or 3.0 of this Article, between Contractor and Subcontractor with respect to the interpretation or performance of this Subcontract, the same shall be settled by arbitration by the American Arbitration Association (“Association”) before a single arbitrator in accordance with the Association’s Construction Industry Arbitration Rules, at New Orleans, Louisiana.” (emphasis added).

Because Mar-Len had repudiated the two modifications, Parsons-Gilbane initiated arbitration on January 17, 1983, before the American Arbitration Association. In the *635 arbitration proceeding, Parsons-Gilbane sought a declaration that Modification 22 waived certain delay claims contained in the seven-volume claim package and that Modification 39 settled amounts Mar-Len claimed for extra work. Arbitration proceedings were stayed to.allow the parties time to explore settlement negotiations. The stay ended on July 18, 1983, after attempts at amicable resolution had failed.

Mar-Len then filed suit on August 5, 1983, in the Fourteenth Judicial District Court, Calcasieu Parish, Louisiana, seeking reformation or voidance of Modifications 22 and 39 of its contract with Parsons-Gilbane based on lack of consent (economic duress) in contracting for these two provisions. On August 16, 1983, Parsons-Gilbane removed the action to the United States District Court, Western District of Louisiana. Parsons-Gilbane then filed a motion to compel arbitration and to stay the proceedings. On November 30, 1983, the federal district court denied the motion to stay and to compel arbitration and ordered the trial of Mar-Len’s action. The district court concluded that the Parsons-Gilbane/Mar-Len arbitration agreement was “not susceptible of an interpretation that covers the asserted dispute.” The district court held that the arbitration agreement covered only disputes involving the interpretation and performance of the contract but not challenges to the validity of subsequent contract modifications.

Parsons-Gilbane appealed the district court’s determination to this Court. In Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, 732 F.2d 444 (5th Cir.1984), a divided panel of this Court dismissed the appeal. This Court concluded that the district court’s denial of Parsons-Gilbane s motion to stay and to compel arbitration was not an appealable interlocutory order under 28 U.S.C. § 1292(a)(1).

Subsequent to this Court’s order dismissing Parsons-Gilbane’s appeal, Mar-Len filed a motion requesting the district court to issue an injunction prohibiting any further proceedings in the pending arbitration. On December 12, 1984, the district court issued the requested injunction based on that court’s earlier conclusion that the dispute between Mar-Len and Parsons-Gil-bane is not within the scope of their arbitration agreement. On January 2, 1985, Parsons-Gilbane properly perfected this appeal from the district court’s order granting the injunction. 1 On appeal, ParsonsGilbane argues that the district court improperly stayed the arbitration because of the district court’s erroneous conclusion that the Mar-Len/Parsons-Gilbane dispute was not arbitrable.

II. ARBITRABILITY

The question of arbitrability is determined on the basis of the existence of an arbitration clause that on its face appears broad enough to encompass the parties’ claims. Commerce Park at DFW Freeport v. Mardian Construction Co., 729 F.2d 334, 338 (5th Cir.1984). A presumption of arbitrability exists requiring that whenever the scope of an arbitration clause is fairly debatable or reasonably in doubt, the court should decide the question of construction in favor of arbitration. United Steelworkers of America v. Warrior & Gulf Navigational Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Papalote Creek II, L.L.C. v. Lower Colorado River
918 F.3d 450 (Fifth Circuit, 2019)
Digital Landscape Inc. v. Media Kings LLC
2018 COA 142 (Colorado Court of Appeals, 2018)
Elkjer v. Scheef & Stone, L.L.P.
8 F. Supp. 3d 845 (N.D. Texas, 2014)
Renfrew Centers, Inc. v. UNI/CARE Systems Inc.
920 F. Supp. 2d 572 (E.D. Pennsylvania, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
773 F.2d 633, 1985 U.S. App. LEXIS 23566, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mar-len-of-louisiana-inc-v-parsons-gilbane-a-joint-venture-ca5-1985.