Old Republic Surety Company v. J. Cumby Construction, Inc.

CourtDistrict Court, N.D. Mississippi
DecidedAugust 16, 2022
Docket1:21-cv-00126
StatusUnknown

This text of Old Republic Surety Company v. J. Cumby Construction, Inc. (Old Republic Surety Company v. J. Cumby Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Old Republic Surety Company v. J. Cumby Construction, Inc., (N.D. Miss. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF MISSISSIPPI ABERDEEN DIVISION

OLD REPUBLIC SURETY COMPANY PLAINTIFF Vv. NO: 1:21CV126-GHD-DAS J, CUMBY CONSTRUCTION, INC. AND DEFENDANTS WESTFIELD INSURANCE COMPANY

MEMORANDUM OPINION Before the Court is Defendants J. Cumby Construction, Inc. (“JCC”) and Westfield Insurance Company’s (“Westfield”) Motion to Stay and Compel Mediation and Arbitration. [8]. Plaintiff Old Republic Surety Company (“Old Republic”) has responded in opposition to this motion. Upon due consideration, for the reasons set forth herein, the Court hereby grants the Defendants’ motion. Factual Background JCC is the general contractor on an installation project known as Tupelo Raw Water Supply Facilities Contract A — Intake and Pumping Northeast Mississippi Regional Water Supply District Itawamba County, Mississippi (“The Project”) located in Fulton, Mississippi. JCC initially entered into a subcontract with Huffman Contractors, LLC (“Huffman”) in which Huffman was to, among other things, install underwater intake piping, pilings, and air burst lines. Huffman was later terminated by JCC and Huffiman’s surety, Old Republic, stepped in to bring in another contractor to complete the remaining work, JCC and Old Republic entered into a Takeover Agreement for Old Republic to “undertake the completion of the remaining work and the Principal’s obligations under the Bonded Contract in accordance with and subject to the terms of the Performance Bond

and this agreement [and] in doing so surety will receive payment of the total amount that is due....” [8-4]. Disputes arose between JCC and Old Republic regarding the quality of Old Republic’s completion contractor and JCC alleges that the completion contractor’s work did not comply with the quality of the subcontract. JCC states that another contractor was retained to complete the remaining work and that several aspects of Old Republic’s completion contractor’s work was defective and required significant costs to correct. Old Republic has now brought multiple claims against defendants, alleging that JCC and Westfield have refused to pay the remaining $970,665.39 balance owed for work on the project. In response to the complaint, defendants have alleged that this current action before the Court is improper as the relevant agreements and contracts contain an arbitration clause. Discussion The Court generally assesses whether the parties agreed to arbitrate the dispute in question using a two-step process: “(1) whether there is a valid agreement to arbitrate between the parties; and (2) whether the dispute in question falls within the scope of that arbitration agreement.” See Gross v. GGNSC Southaven, L.L,.C., 817 F.3d 169, 176 (5th Cir, 2016), Ifthe Court finds that the parties have a valid agreement to arbitrate and that the dispute is within the scope of the arbitration agreement, the Court generally examines whether any legal constraints foreclose arbitration of those claims. See Brown v. Pac. Life Ins. Co., 462 F.3d 384, 396 (Sth Cir. 2006) (citing Mitsubishi Motors Corp., 473 U.S. at 628, 105 S. Ct. 3346)). Courts must “apply the federal policy favoring arbitration when addressing ambiguities regarding whether a question falls within an arbitration agreement’s scope, but... do not apply this policy when determining whether a valid agreement exists.” Sherer vy. Green Tree Servicing LLC, 548 F.3d 379, 381 (Sth Cir. 2008), See Volt Info.

Seis., Inc, v. Bd. of Trs. of Leland Stanford Jr. Univ,, 489 U.S. 468, 475-76, 109 8. Ct. 1248, 103 L. Ed. 2d 488 (1989); Banc One Acceptance Corp. v. Hill, 367 F.3d 426, 429 (Sth Cir. 2004) (citing Will-Drill Res., Ine. v. Samson Res, Co,, 352 F.3d 211, 214 (Sth Cir. 2003)); Westmoreland v. Sadoux, 299 F.3d 462, 465 (Sth Cir, 2002). The determination of whether a party is bound by an arbitration agreement is included within the broader issue of whether the parties agreed to arbitrate. Bridas SA.P.LC. v. Gov't of Turkmenistan, 345 F.3d 347, 355 (Sth Cir, 2003) (citing Smith/Enron Cogeneration Ltd. P’ship, Inc. v. Smith Cogeneration Int'l, Inc., 198 F.3d 88, 95 (2d Cir, 1999)). “The purpose of the FAA is to give arbitration agreements the same force and effect as other contracts—-no more and no less.” Washington Mut. Fin. Grp., LLC v. Bailey, 364 F.3d 260, 264 (5th Cir. 2004) (citing 9 U.S.C. § 2); see Pennzoil Expl. & Prod. Co. v. Rainco Energy Ltd, 139 F.3d 1061, 1064 (Sth Cir. 1998) (“[ajrbitration is a matter of contract between the parties”). It is undisputed that plaintiff Old Republic is a nonsignatory to the Subcontract, “Arbitration agreements apply to nonsignatories only in rare circumstances.” Bridas SA.P.LC. v, Gov't of Turkmenistan, 345 F.3d 347, 358 (Sth Cir. 2003) (citing Westmoreland v. Sadoux, 299 F.3d 462, 465 (Sth Cir, 2002)). Where a nonsignatory to the agreement to arbitrate is involved, the Court must find that the nonsignatory meets one or more of six theories in order to bind the nonsignatory to arbitrate a dispute: (1) incorporation by reference, (2) assumption, (3) agency, (4) alter ego, (5) estoppel, or (6) third-party beneficiary. Hellenic Investment Fund y. Det Norske Veritas, 464 F.3d 514, 517 (Sth Cir. 2006). Defendants assert only incorporation by reference and as such the Court does not consider the remaining theories, Defendants assert that the entirety of the Subcontract, including the arbitration clause, was incorporated by reference into the performance bond. Specifically, Defendants argue that the

following language in the performance bond requires incorporation by reference of all clauses of the Subcontract: WHEREAS, Principal has by written agreement dated 8/28/2018 entered into a subcontract with Obligee for Project #18123: Tupelo — Raw Water Intake, Subcontract #18123-016, Tupelo, MS which subcontract is by reference made a part hereof, and is referred to as subcontract. [8-3]. Defendants assert that the performance bond language illustrates Old Republic’s intent to complete the subcontract in place of Huffman and to be bound by all the terms and conditions to the subcontract. Further, Defendants state that the takeover agreement between Oid Republic and JCC demonstrates further evidence of the parties’ intent to be bound by the subcontract, as the agreement provides in pertinent part that “Surety (Old Republic) is willing to undertake the completion of the Remaining Work and the Principal’s (Huffman’s) obligations under the Bonded Contract in accordance with and subject to the terms of the Performance Bond and _ this Agreement.” [8-3].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bridas S.A.P.I.C. v. Government of Turkmenistan
345 F.3d 347 (Fifth Circuit, 2003)
Will-Drill Resources, Inc. v. Samson Resources Co.
352 F.3d 211 (Fifth Circuit, 2003)
Washington Mutual Finance Group, LLC v. Bailey
364 F.3d 260 (Fifth Circuit, 2004)
Banc One Acceptance Corp. v. Hill
367 F.3d 426 (Fifth Circuit, 2004)
Brown v. Pacific Life Insurance
462 F.3d 384 (Fifth Circuit, 2006)
Baudoin v. Mid-Louisiana Anesthesia Consultants, Inc.
306 F. App'x 188 (Fifth Circuit, 2009)
Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Sherer v. Green Tree Servicing LLC
548 F.3d 379 (Fifth Circuit, 2008)
Shirley Cotton v. GGNSC Batesville, L.L.C.
817 F.3d 169 (Fifth Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Old Republic Surety Company v. J. Cumby Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/old-republic-surety-company-v-j-cumby-construction-inc-msnd-2022.