M. W. Kellogg Co. v. Standard Steel Fabricating Co. Standard Steel Fabricating Co. v. M. W. Kellogg Co.

189 F.2d 629
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 10, 1951
Docket4189_1
StatusPublished
Cited by6 cases

This text of 189 F.2d 629 (M. W. Kellogg Co. v. Standard Steel Fabricating Co. Standard Steel Fabricating Co. v. M. W. Kellogg Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. W. Kellogg Co. v. Standard Steel Fabricating Co. Standard Steel Fabricating Co. v. M. W. Kellogg Co., 189 F.2d 629 (10th Cir. 1951).

Opinions

MURRAH, Circuit Judge.

This appeal arises out of a breach of contract action, and involves the interpretation of a purchase order contract for the purpose of determining the quantity of fabricated steel the M. W. Kellogg Company agreed to purchase from the Standard Steel Fabricating Company, for use in constructing a fluid catalytic cracking unit for the Texas Company at Tulsa, Oklahoma, and designated as Job 7110.

The purchase order issued by Kellogg to Standard, in words and figures, is as follows :

“Quantity Description Price
Enter our order for furnishing the following material:
1 lot Steel and connectors for pipe Supports in accordance with Drawings furnished and attached three (3) sheets ‘Terms of Purchase Order’
Approximately first 30 tons @ 32c per lb. subject to stipulations on attached three (3) sheets .............. 19,200.00
Approximately 95 tons @ 30c per lb. subject to stipulations on attached three (3) sheets 57,000.00
Total 125 tons, more or less; Approximately .................. 76,200.00”

The attached “Terms of Purchase Order” provide in material part as follows:

“c. Supports marked ‘FS’ which are to be rod hangers will be furnished by the Vendor, if the Purchaser’s Engineering Department deems it advisable. These will be subject to a change to this purchase order to be covered at a later date.
"a. Height of base support upright members will be determined by the Purchaser’s Engineering Department and this information will be transmitted to the Vendor by Purchaser.”

Completion of Job 7110, according to the drawings and specifications required a little more than 52 tons of steel, and Kellogg refused to purchase any more steel than its requirements for completion of the job. Standard, having been incorporated for the performance of this contract alone, and having purchased the entire 125 tons mentioned in the contract, brought this action for performance or for loss of the profits it would have realized on the undelivered portion of steel.

The issue clearly presented to the trial court and here on appeal, is whether under the terms of the purchase order Kellogg agreed to purchase only the amount of steel required for construction of the fluid catalytic cracking unit, according to specifications and the drawings referred to in the purchase order, or whether it agreed to purchase the 125 ton quantity mentioned in the contract. In short, the question is whether the purchase order is one for a specific and definite quantity of steel or one for the requirements of Job 7110.

Holding that the purchse order was not a requirement contract, but one for 125 tons of steel, with only slight or immaterial variations, and that Kellogg and the Texas Company had breached the contract, the trial court gave judgment for $8,683.72, as loss of profits under the contract.

The ready formula for construction of contracts of this nature was first promulgated in the early case of Brawley v. United States, 96 U.S. 168, 24 L.Ed. 622, involving a contract somewhat similar to ours. Mr. Justice Bradley speaking for the court stated:

“Where a contract is made to sell or furnish certain goods identified by reference to independent circumstances, such as-an entire lot deposited in a certain warehouse, or all that may be manufactured by the vendor in a certain establishment, or that may be shipped by his agent or correspondent in certain vessels, and the.[631]*631quantity is named with the qualification of ‘about’, or ‘more or less’, or words of like import, the contract applies to the specific lot; and the naming of the quantity is not regarded as in the nature of a warranty, but only as an estimate of the probable amount, in reference to which good faith is all that is required of the party making * * *

“But when no such independent circumstances are referred to, and the engagement is to furnish goods of a certain quality or character to a certain amount, the quantity specified is material, and governs the contract. The addition of the qualifying words, ‘about’, ‘more or less’ and the like, in such cases, is only for the purpose of providing against accidental variations arising from slight and unimportant excesses or deficiencies in number, measure, or weights.”

Since the Brawley case, the judicial process has consisted primarily of the application of these rules to particular contracts before the courts. Thus, in Smoot v. United States, 237 U.S. 38, 35 S.Ct. 540, 59 L.Ed. 829, the contract was to furnish 140,200 cubic yards, more or less, of filter sand, to be deposited in twenty-nine filter beds, at $2.65 per yard. Holding that the contract was for the purchaser’s requirements, the court stated that the “dominant measure” of the sand to be furnished was what was needed for the filters, and that the cubic feet estimated by the purchaser’s engineer was not controlling. See also, Wolff v. Wells, Fargo & Co., 9 Cir., 115 F. 32; Marx v. American Malting Co., 6 Cir., 169 F. 582; Maryland Dredging & Contracting Company v. Coplay Cement Mfg. Co., 265 F. 842; Barkemeyer Grain & Seed Co. v. Hannant, 66 Mont. 120, 213 P. 208; Ruth-Hastings Glass Tube Co. v. Slattery, 266 Pa. 288, 109 A. 695; Annotation 7 A.L.R. 498, supplemented 27 A.L.R. 127. On the other hand, when the only measure is the estimate itself, the courts have allowed only a small variation from the estimate. See United States v. Republic Bag & Paper Co., 2 Cir., 250 F. 79; Norrington v. Wright, 115 U.S. 188, 6 S.Ct. 12, 29 L.Ed. 366; Annotation 7 A.L.R. 498, supplemented 27 A.L.R. 127.

This contract is controlled by Oklahoma law, and the Oklahoma Supreme Court in Sherman Machine & Iron Works v. Carey, Lombard, Young & Co., 100 Okl. 29, 227 P. 110, applying the Brawley formula to a contract for 600 barrels “more or less” of cement at a stipulated price, for the construction of a waterworks, held that the contract between the seller and the purchaser was for the amount of cement necessary to complete the purchaser’s contract for the construction of the waterworks, and that the 600 barrels mentioned was merely,an estimate of what was needed to perform the contract. Paraphrasing the Brawley formula, the court went on to say that where the buyer purchases a specific amount of certain material, to be used for no particular or specific purpose, as where a retail merchant purchases merchandise to be retailed to his customers generally, the quantity specified controls, with slight variations. But, where the purchase is for material to be used for a definite purpose or specific project, all of which facts are made known to the seller, such as a quantity of cement sufficient for the construction of a plant which the purchaser has agreed to build, then the amount of material required to complete the specific project becomes the essence of the contract rather than the specification wherein a certain amount of material is designated, more or less.

The trial court thought our case was more like Budge v. United Smelting & Refining Co., 9 Cir., 104 F. 498, where the contract was to furnish the mining company all mining timbers required and used on its lease during the year.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
189 F.2d 629, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-w-kellogg-co-v-standard-steel-fabricating-co-standard-steel-ca10-1951.