Utah International, Inc. v. Colorado-Ute Electric Ass'n

425 F. Supp. 1093, 1976 U.S. Dist. LEXIS 11839
CourtDistrict Court, D. Colorado
DecidedDecember 14, 1976
DocketCiv. A. 75-A-526
StatusPublished
Cited by11 cases

This text of 425 F. Supp. 1093 (Utah International, Inc. v. Colorado-Ute Electric Ass'n) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah International, Inc. v. Colorado-Ute Electric Ass'n, 425 F. Supp. 1093, 1976 U.S. Dist. LEXIS 11839 (D. Colo. 1976).

Opinion

MEMORANDUM OPINION AND ORDER

ARRAJ, District Judge.

Plaintiff Utah International, a mining company with international operations, brings this declaratory judgment action against Colorado-Ute Electric Association, Inc., Platte River Power Authority, TriState Generation and Transmission Association, and Salt River Project Agriculture Improvement and Power District, all wholesalers of electric power and energy. Plaintiff seeks a declaration of its rights and duties as a party to a contract for the sale of coal, and defendants have counterclaimed for the specific performance of that contract.

The contract in question is a thirty five year requirements contract containing a maximum sales obligation and minimum purchase obligation. Plaintiff as seller claims that defendants have breached the contract by building electric generating units with generating capacities larger than specified in the sales contract. As a result of such construction, plaintiff contends that it will be required to provide more coal than was anticipated by this requirements contract and that its contractual obligations thereunder should, therefore, be terminated. Trial was to the Court and this Opinion shall constitute the findings of facts and conclusions of law in conformance with Fed.R.Civ.P. 52(a).

In 1969, the four defendants, along with Public Service Company of Colorado, Inter-mountain Consumers Power Association, and Arizona Public Service formed the Western Colorado Resource Study to consider the possibility of constructing coal- *1095 fired electric generating units near Craig, Colorado. This project later became known as the Yampa Project. These original participants appointed a Steering Committee to be in overall charge of the project, the membership consisting of senior executives of each defendant and representatives of the United States Bureau of Reclamation. This committee in turn created a task force system to carry out specific study assignments.

On April 18, 1970 the participants' commenced negotiations with plaintiff for the supply of fuel for the Yampa Project and sent to plaintiff, and to other prospective suppliers an invitation to submit proposals for the mining and delivery of coal fuel. The amount of coal contemplated as necessary to fuel the project was at that time undetermined but the participants provided coal consumption estimates for the different unit alternatives then being considered. In response, plaintiff proposed a pricing schedule based on calculations made from the estimated coal consumption figures provided by defendants in their invitation.

In December of 1970, defendant Salt River, as the participant in charge of the initial purchase negotiations for the project’s turbine-generators, obtained a quotation from General Electric for two 450,000 kilowatt generators. In March of the following year, Salt River and General Electric executed a letter of intent for these generators with the stipulation that the size of the units could subsequently be changed.

By early 1971 Public Service Company of Colorado, Intermountain Consumers Power Association, and Arizona Public Service Company had withdrawn from the Western Colorado Resource Study leaving the defendants as the remaining participants. As a result of that withdrawal the participants began re-evaluating their projected consumer power demands and their plans regarding the size of the generating units to be constructed. By December of 1971 they had decided that two units, each rated at 350,000 kilowatts net, would be capable of providing the generating capacity necessary to meet their re-evaluated projections.

In choosing the machine to meet their needs, defendants operated under certain assumptions generally accepted by the electrical generating industry. The first and most important assumption is that a generating unit of the type being installed at Craig will not operate at 100% capacity but rather at approximately 75% capacity over an extended period, such as the thirty five year term of this contract. The reason for this is that all such machines require regularly scheduled maintenance periods and also periods of unanticipated maintenance during which it is necessary to shut down the machines.

Once the unit size was chosen, the parties then calculated the amount of coal that such units would burn over thirty five years. This process was a joint effort between representatives of the defendants and representatives of the plaintiff. Both parties used the net figure 350,000 kilowatts as a starting point in estimating the probable coal consumption and then communicated their calculations to the other party for verification. Gradually, through this process, the estimates became refined, and both parties as of May of 1972 understood that there would be constructed two generators of approximately 350,000 kilowatt net capacity each, which machines would operate at an average capacity factor of about 75% and would burn approximately 76 million tons of coal over the life of the contract. It was additionally understood that the generating units would operate at almost 90% capacity during the first ten years of the contract and then steadily decline in capacity during the balance of the term of the contract. The parties expected some variance from these predicted capacity factors and these predictions for coal consumption but there was no suggestion that it was expected by either party that the variance would be substantial.

It is clear that the generating unit size and the coal consumption calculations derived from the customary operation of such units were important to plaintiff during the negotiations of this contract. Plaintiff relied on the calculations in conducting its *1096 feasibility study, developing a pricing schedule, and designing its mine. Defendants were aware that plaintiff was so utilizing these figures. It is noted that defendants’ expert witness testified to the effect that it is a common procedure in the negotiation of such a fuel contract for the public utility or other buyer of coal to calculate the amount of coal expected to be burned and then to communicate such calculations to the coal miner.

Negotiations between defendants and plaintiff were completed by February 3, 1973 and the contract in question was signed April 6,1973. The contract provides that plaintiff’s obligation is to supply the coal requirements for two generating units, each with a capacity of about 350,000 kilowatts net. Plaintiff’s sales obligation, however, is not to exceed the mining and delivery of coal sufficient to produce 1830 trillion Btu’s over the thirty five year life of the contract. Defendants’ purchase obligation is to pay for a yearly quantity of coal, regardless of whether they order that amount. This quantity is a negotiated figure based on a calculation of 85% of the expected coal consumption of the machines. Between these maximum and minimum limits, the contract provides that the actual requirements of the units is to be determinative of the amount of coal ordered and delivered.

It is noted that shortly after the execution of the contract, coal prices began to rise dramatically, due in part to the Arab oil embargo in September of 1973. Prior to that time the price of coal had reflected only a slight upward trend.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Empire Gas Corporation v. American Bakeries Company
840 F.2d 1333 (Seventh Circuit, 1988)
Louisiana Power & Light Co v. United Gas Pipe Line Co.
642 F. Supp. 781 (E.D. Louisiana, 1986)
United States v. McBride
571 F. Supp. 596 (S.D. Texas, 1983)
Carfield & Sons, Inc. v. Cowling
616 P.2d 1008 (Colorado Court of Appeals, 1980)
Homestake Mining Co. v. Washington Public Power Supply System
476 F. Supp. 1162 (N.D. California, 1979)
MaceRich Real Estate Co. VI v. Holland Properties Co.
454 F. Supp. 891 (D. Colorado, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
425 F. Supp. 1093, 1976 U.S. Dist. LEXIS 11839, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utah-international-inc-v-colorado-ute-electric-assn-cod-1976.