Tennessee Valley Authority v. Imperial Professional Coatings

599 F. Supp. 436, 32 Cont. Cas. Fed. 73,359, 1984 U.S. Dist. LEXIS 24251
CourtDistrict Court, E.D. Tennessee
DecidedAugust 20, 1984
DocketCiv. 3-84-239
StatusPublished
Cited by6 cases

This text of 599 F. Supp. 436 (Tennessee Valley Authority v. Imperial Professional Coatings) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Valley Authority v. Imperial Professional Coatings, 599 F. Supp. 436, 32 Cont. Cas. Fed. 73,359, 1984 U.S. Dist. LEXIS 24251 (E.D. Tenn. 1984).

Opinion

MEMORANDUM

HULL, District Judge.

This is an action for judicial review of a decision by the Tennessee Valley Authority [TVA] Board of Contract Appeals [Board] rendered pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 607(g) (Supp.1984). The Board held that under the Changes Clause of a requirements contract between Imperial Professional Coatings [IPC] and TVA for paint to coat concrete at proposed nuclear power plants, IPC was entitled to an equitable adjustment 1 when TVA ceased to have requirements for the paint after it decided to cancel construction of the plants. The case is before the Court on cross-motions for summary judgment.

In this case, federal law governs the contract rights and obligations of TVA. Tennessee Valley Authority v. U.S. Carbon Products, Inc., 427 F.Supp. 474, 477 (E.D.Il.1976); Tennessee Valley Authority v. Mason Coal, Inc., 384 F.Supp. 1107, 1115 (E.D.Tenn.1974) aff'd. 513 F.2d 632 (1975). The decision of the Board is final and conclusive on questions of fact and shall not be set aside unless clearly erroneous, but is not final and conclusive on questions of law. 41 U.S.C. § 609(b).

The facts of the case are agreed on by the parties, are accurately set forth in the Board’s decision, and will be only briefly recited. In 1978, pursuant to a bid, TVA awarded to IPC a contract to supply protective coating paint for proposed nuclear reactors. The estimated amount of the contract was $2,717,426.79, as reflecting the estimated amount of materials and surfaces to receive the protective coatings at the prices specified by IPC. In early 1982 TVA deferred construction of the nuclear plants. The decision to defer construction presumably was made on the basis that anticipated growth in the demand for electric power had been overestimated. (Letter to IPC from C.H. Strickland, August 6, *438 1982). Prior to deferral of construction activities by TVA, TVA had ordered and IPC had shipped approximately $1,414,-000.00 worth of the paint. After TVA notified IPC that no further orders would be placed, IPC filed a claim with the TVA contracting officer. The contracting officer held that the contract was a requirements contract and that TVA had no obligation to order more than its requirements. IPC appealed the decision to the Board which held that cancellation of the plants was unforeseen by either party, that IPC did not assume the risk of cancellation, and that IPC was entitled to an equitable adjustment under the Changes Clause of the contract.

The parties do not dispute that this is a requirements contract or that TVA made a good-faith decision to cease construction of the nuclear power plants, thereby terminating its requirement for paint. The dispute centers on whether IPC is entitled to an equitable adjustment on the theory that TVA’s decision to cease construction was a change within the changes clause of the contract.

The pertinent contract provisions are set forth below:

“Quantity. This is a requirement contract for the materials which are required for painting the areas designated in the invitation to bid, Hartsville Nuclear Plants A and B, and Phipps Bend Nuclear Plant which is expected, but not guaranteed, to be completed about first quarter 1986. The area stated is TVA’s estimated area, and the quantity is the theoretical quantity for estimated areas for the term of this contract; however, TVA does not guarantee to purchase any maximum or minimum amount as TVA’s actual requirements may differ from the TVA estimate. Any quantity for which TVA has not requested delivery as of the date of completion of painting of the designated area of each plant is automatically cancelled.

“Changes. The Contracting Officer may at any time, by written order, and without notice to the sureties, make changes in the work within the general scope of the contract, including changes in the drawings and specifications. If such changes cause an increase or decrease in the amount of work under this contract or in the time necessary for its performance, an equitable adjustment will be made in the price or the time allowed for performance, or both, and the contract shall be modified in writing accordingly____

IPC’s position is that: (1) The requirements contract provides an objective measurable standard (the designated areas described and measured in the invitation to bid) for what is required, and specifically provides for equitable adjustment if that standard is changed, such as by a decision to cancel the plants.

(2) Neither party.foresaw or contemplated a cancellation of the project and the facts and circumstances surrounding the contract indicate the parties did not intend for IPC to assume the risk of cancellation.

TVA’s position is that: (1) Because this is a requirements contract it obligated itself to purchase whatever its requirements proved to be and that IPC assumed the risk of a decrease or cessation of requirements caused by TVA’s good-faith decision to cancel the plants.

(2) A decrease in requirements caused by cancellation of the plants is not a change compensable under the changes clause.

A requirements contract is “ ‘a contract in which the purchaser agrees to buy all of its needs of a specified material from a particular supplier, and the supplier agrees, in turn, to fill all of the purchaser’s needs during the period of the contract.’ ” Mason v. United States, 615 F.2d 1343, 1346, 222 Ct.Cl. 436 (1980), quoting Media Press, Inc. v. United States, 566 F.2d 1192, 215 Ct.Cl. 985 (1977). The purpose of a requirements contract is to give the buyer an assured source of supply over an extended period of time without obliging him to purchase a specified quantity, thus enabling him to meet the fluctuating needs of his business. Note, Requirements Contracts: Problems of Drafting and Construction, 78 Harv.L.Rev. 1212, 1215 (1965). In light *439 of this purpose, courts have generally permitted a buyer to cut back or eliminate entirely his orders if there is a bona fide decrease in needs. Id.; Fort Wayne Corrugated Paper Co. v. Anchor Hocking Glass Corp., 130 F.2d 471 (3rd Cir.1942); In re United Cigar Stores, 72 F.2d 673 (2d Cir.1934), cert. den. sub nom. 293 U.S. 617, 55 S.Ct. 210, 79 L.Ed. 706 (1934).

With these general principles in mind, the Court will address IPC’s argument that although the contract at issue is a requirements contract for paint for nuclear plants and TVA’s requirement for the paint ceased with the good-faith cancellation of the plants, IPC is entitled under the contract to an equitable adjustment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in Re: Enterprise Crude Oil, LLC
Court of Appeals of Texas, 2018
Vulcan Materials Co. v. Atofina Chemicals Inc.
355 F. Supp. 2d 1214 (D. Kansas, 2005)
Park Electrochemical Corp. v. Delco Electronics Corp.
65 F. App'x 602 (Ninth Circuit, 2003)
Empire Gas Corporation v. American Bakeries Company
840 F.2d 1333 (Seventh Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
599 F. Supp. 436, 32 Cont. Cas. Fed. 73,359, 1984 U.S. Dist. LEXIS 24251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-valley-authority-v-imperial-professional-coatings-tned-1984.