M. R. Stokes Company, Inc. v. Michael L. Shular

CourtCourt of Appeals of Tennessee
DecidedFebruary 26, 2008
DocketM2006-02659-COA-R3-CV
StatusPublished

This text of M. R. Stokes Company, Inc. v. Michael L. Shular (M. R. Stokes Company, Inc. v. Michael L. Shular) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. R. Stokes Company, Inc. v. Michael L. Shular, (Tenn. Ct. App. 2008).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE September 11, 2007 Session

M. R. STOKES COMPANY, INC. v. MICHAEL L. SHULAR, ET AL.

A Direct Appeal from the Circuit Court for Sumner County No. 27058 The Honorable C. L. Rogers, Judge

No. M2006-02659-COA-R3-CV - Filed February 26, 2008

This is a construction case. In a contract prepared by the plaintiff, contractor agreed to install sewer lines, water lines, roads and to perform certain site preparation work for a section of a subdivision development owned by the defendant-owner. The total contract price is $925,000, which includes the material and labor to complete the project. The trial court entered judgment for contractor. Owner appeals and contractor cross-appeals. We affirm in part, reverse in part, and remand for further proceedings consistent with this opinion.

Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Circuit Court Affirmed in Part, Reversed in Part and Remanded

W. FRANK CRAWFORD , J., delivered the opinion of the court, in which ALAN E. HIGHERS, P.J., W.S. and JEFFREY F. STEWART , SP.J., joined.

Cecil D. Meek, Jr., and Edward L. Summers of Knoxville, Tennessee for Appellants, Michael L. Shular, Trustee and Ohio Casualty Insurance Company

Mary Beth Hagan and Gareth S. Aden of Nashville, Tennessee for appellee and Cross-Appellant, M. R. Stokes Company, Inc.

OPINION

Facts and Procedural History

In 2003, Defendants, Michael L. Shular, Trustee, Shular Contracting, and Ohio Casualty Insurance Company1 (hereinafter collectively, “Owner”) planned the development of Somerset Downs (hereinafter, “the Project”), a residential subdivision in Sumner County, Tennessee. Owner, by and through Shular Contracting, Inc., submitted a letter of intent to enter into a contract with

1 Ohio Casualty Insurance Company is the surety on a bond, which was executed to “bond off” a mechanics and materialman’s lien filed by the Contractor. Its interest is identical to that of Michael L. Shular, Trustee. Plaintiff, M. R. Stokes Company, Inc. (hereinafter, “Contractor”) for Contractor to perform all work under the plans and specifications, including the installation of sewer lines, water lines, roads, and certain site preparation work for the total sum of $925,000.00. In determining its bid, Contractor reviewed the construction plans given to him by Owner. Contractor then submitted a written, one- page “Proposal” (hereinafter, “Contract”) to Owner. Both parties signed the Contract, together with an attached Addendum, on August 6, 2003. In the Contract, Contractor agreed to furnish material and labor to complete the Project, in accordance with the specifications listed on the Contract for $925,000.00. The Contract incorporated certain pages of the development plans and stated that Contractor would perform the following work:

1. Install roads and widening of Long Hollow Pike per plans.

2. Road drainage with structures, drain lines and outlet headwalls.

3. Sewer line connected to manhole M21 (but not including manhole).

4. Detention pond #3 and site drainage areas.
5. Water lines and tap assemblies.
6. 600 feet of ductile sewer line is included, if required.

7. All labor, materials, (as noted) and required equipment to do the work as shown on contract drawings C1.00 to C1.04, C2.01 to C2.10, and C3.01, C4.01 and C4.02.

8. All work shall meet all Sumner County and White House Utility specifications.

The Contract further stipulated that “[a]ny alteration or deviation from above specifications involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate.” Additionally, the Addendum, which is signed by both parties, specifies in part that a “5% [r]etainage [is] to be withheld from each Progress Payment” and that “[r]etainage [is] to be paid within 30 days of completion . . . .”

Contractor commenced working on the Project, including installing the gravity sewer lines in Phase 1 of the Project. When an inspector from White House Utility District (hereinafter, “WHUD”) examined the gravity sewer lines, he found that 5% of the sewer lines did not conform to WHUD’s written specification that the sewer pipe “shall be straight and show a uniform grade between manholes.” Contractor did not attempt to fix the problems, and ceased working on the Project in December of 2004. On January 10, 2005, the Contractor submitted its last “pay application” to Owner. This pay application requested payment of the remaining 5% “retainage”

-2- amount, a total of $43,676.25, that had been set aside during the course of the Project. Owner refused to pay Contractor.

On June 17, 2005, Contractor filed suit claiming that Contractor had completed the work under the Contract, had performed additional work outside the Contract, and was due $97,646.61. Contractor also alleged that it was due the fair market value for topsoil, which Contractor allegedly had been promised, and which had been distributed to a third party by Owner. On August 24, 2005, Contractor amended its Complaint to allege that an additional $11,871.72 was due under the Contract. Owner answered and argued that there was not an agreement for any changes to be paid at the end of the Project unless those changes were evidenced by a written change order. The Contractor submitted eleven “pay applications” over the period of 15 months, none containing any “changes.” Owner also alleged that Contractor had not properly completed the Contract. Furthermore, Owner sought set-offs and/or recoupment for work performed by a third party at Owner’s expense after Contractor allegedly walked off the Project.

The matter was heard before the Circuit Court of Sumner County, Tennessee. After a three- day bench trial, the trial court rendered a judgment in favor of the Contractor against the Owner in the amount of $69,927.18 ($43,678,00 for the unpaid retainage and $26,249.18 for extra costs from alterations or deviations from the Contract specifications), plus 8% pre-judgment interest from January 1, 2005. The trial court found that Owner had breached its Contract with Contractor, denied Owner’s claim for credit, offset, and/or breach of contract by Contractor, and denied Contractor’s claim for the fair market value of the topsoil.

Contractor filed a motion to alter or amend and a motion for discretionary costs. On January 8, 2007, the trial court entered an Order striking any judgment against Michael Shular and Teddy Adams, in their individual capacities, and amended the parties against whom the judgment should apply to Defendant Michael Shular, Trustee, and Defendant Ohio Casualty. Furthermore, the Order granted Contractor’s discretionary costs in the amount of $3,519.03 for a total Judgment of $73,446.21, plus 8% pre-judgment interest per annum from January 5, 2005. The trial court also granted Owner’s Motion to Stay pending appeal. Owner appeals.

Issues on Appeal

On appeal, Owner’s issues are as follows:

1. Whether the trial court erred in concluding that the contractual provision requiring written change orders for any alteration or deviation from specifications involving extra costs was waived, and/or in concluding that any oral agreements had been reached involving such extra costs.

2. Whether the trial court erred in not enforcing the terms of the written contract between the parties, including, the contractual

-3- obligation of contractor that “all work shall meet all Sumner County and White House Utility specifications.”

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Progressive Casualty Insurance Co. v. Chapin
243 S.W.3d 553 (Court of Appeals of Tennessee, 2007)
Whitehaven Community Baptist Church v. Holloway
973 S.W.2d 592 (Tennessee Supreme Court, 1998)
Ganzevoort v. Russell
949 S.W.2d 293 (Tennessee Supreme Court, 1997)
Scholz v. S.B. International, Inc.
40 S.W.3d 78 (Court of Appeals of Tennessee, 2000)
Calabro v. Calabro
15 S.W.3d 873 (Court of Appeals of Tennessee, 1999)
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
Gray v. Estate of Gray
993 S.W.2d 59 (Court of Appeals of Tennessee, 1998)
Mitchell v. Archibald
971 S.W.2d 25 (Court of Appeals of Tennessee, 1998)
Long v. Long
957 S.W.2d 825 (Court of Appeals of Tennessee, 1997)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
Massachusetts Mutual Life Insurance Co. v. Jefferson
104 S.W.3d 13 (Court of Appeals of Tennessee, 2002)
Johnson v. Central National Ins. Co. of Omaha, Neb.
356 S.W.2d 277 (Tennessee Supreme Court, 1962)
Heyer-Jordan & Associates, Inc. v. Jordan
801 S.W.2d 814 (Court of Appeals of Tennessee, 1990)
NSA DBA Benefit Plan, Inc. v. Connecticut General Life Insurance Co.
968 S.W.2d 791 (Court of Appeals of Tennessee, 1997)
Bowman v. Bowman
836 S.W.2d 563 (Court of Appeals of Tennessee, 1991)
Rainey v. Stansell
836 S.W.2d 117 (Court of Appeals of Tennessee, 1992)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Jamestowne on Signal, Inc. v. First Federal Savings & Loan Ass'n
807 S.W.2d 559 (Court of Appeals of Tennessee, 1990)
Hennessee v. Wood Group Enterprises, Inc.
816 S.W.2d 35 (Court of Appeals of Tennessee, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
M. R. Stokes Company, Inc. v. Michael L. Shular, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-r-stokes-company-inc-v-michael-l-shular-tennctapp-2008.