Jamestowne on Signal, Inc. v. First Federal Savings & Loan Ass'n

807 S.W.2d 559, 1990 Tenn. App. LEXIS 807
CourtCourt of Appeals of Tennessee
DecidedNovember 14, 1990
StatusPublished
Cited by98 cases

This text of 807 S.W.2d 559 (Jamestowne on Signal, Inc. v. First Federal Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jamestowne on Signal, Inc. v. First Federal Savings & Loan Ass'n, 807 S.W.2d 559, 1990 Tenn. App. LEXIS 807 (Tenn. Ct. App. 1990).

Opinion

OPINION

SANDERS, Presiding Judge, Eastern Section.

The pivotal issue on this appeal is whether or not the Defendant-Appellant, First Federal Savings & Loan Association, breached an alleged oral contract to finance the total cost of construction of a condominium complex on Signal Mountain.

In September, 1985, the Plaintiffs-Appel-lees, Jamestowne on Signal, Inc. (James-towne), Fred M. Edgemon, Jr. (Edgemon), and James R. Hedges, III (Hedges), filed an application with Defendant-Appellant First Federal Savings & Loan Association (First Federal) for a construction loan on a 25-unit condominium complex on Signal Mountain. Jamestowne is a corporation and the property upon which the complex was to be constructed was titled in it. Ed-gemon and Hedges are the owners of all the capital stock of Jamestowne. The prospectus of the complex, submitted with the *560 loan application, showed an estimated cost of construction of $2,371,225, gross sales of units $3,335,000, cost of marketing $200,-106, with a net profit of $763,739. Construction was to be completed in four phases, mostly of six units each and all units were to be completed within 18 months.

First Federal issued a commitment letter agreeing to loan $2,040,000 for a term of 18 months with interest at 11% payable semiannually. The commitment was subject to the following: “1. A detailed architectural inspection report to be provided before each payout request; 2. Release amounts shall be 80% of retail prices, regardless of actual sales price; and 3. First Federal must give approval of phases II, III, and IV, before they are begun.”

The loan commitment was accepted and a note secured by a deed of trust was executed on November 5,1985, in keeping with the commitment. Edgemon and Hedges each personally endorsed the note. Simultaneously with the note and deed of trust a construction loan agreement was executed which, as pertinent here, provided: “Inspections will be made prior to any disbursements of funds by Lender in accordance with its customary inspection sheet, and Lender is under no obligation to disburse a greater portion of the loan proceeds than the percentage of completion indicated by its inspection. If the amount approved by Lender is insufficient to pay all amounts owing for labor and materials, Borrower agrees to furnish sufficient funds to make up the difference. Lender in no way guarantees Borrower that the amount loaned will be sufficient to complete construction. Lender may in its sole discretion disburse amounts in excess of the percentage indicated by its inspection but has no obligation to do so.”

Soon after the execution of the deed of trust and note, construction began on six units under phase one of the project. As construction progressed, requests for draws were submitted. As these requests were submitted, it was the duty of Mr. Davis, an appraiser for First Federal, to make an inspection of the construction completed and authorize payment of such amount as the percentage of construction relating to the total construction of the project (that is, all four phases of the complex) related to the total loan of $2,040,000. However, in April, 1986, it was discovered Mr. Davis was relating the percentage of construction of phase one of the complex to the total amount of the loan, which had resulted in his approving substantially larger amounts for draws than were authorized. At that time First Federal had over disbursed to the borrowers approximately $98,000. After discovering this overpayment Mr. Campbell, one of the loan officers, contacted Messrs. Edgemon and Hedges to discuss the matter. They stated they had had a lot of cost overruns on their sewers, extra fill dirt, underground rock removal, extra masonry fence, etc., and needed the extra money. At that time the borrowers had commitments to purchase five of the six units under construction. It was agreed the total purchase price of these houses would go to First Federal to reduce the overpayments which had occurred and would continue to accrue until the houses were sold. Based upon this agreement, First Federal continued to make overpayments through August and it built up to a total of $239,000. One of the houses sold on July 31 and four of them sold in September, which reduced the over-disbursement to about $37,000.

In September and October the borrowers submitted draws for more than the percentage of work that had been completed. First Federal, however, approved these draws based upon the representations of the borrowers that they had a lot of people interested in purchasing houses.

In the latter part of October Messrs. Edgemon and Hedges mentioned to some of the First Federal officers that they were going to require additional financing. They were requested to submit a recap on what was needed. On November 7, 1986, they submitted a recap of construction cost showing an estimated cost for completion of the project of $1,060,000. By that time approximately 75% of the construction loan had been disbursed, the project was approximately 51% to 52% complete, and there was only $526,000 of undisbursed *561 loan funds left in the loan fund account. Also, on October 20, 1986, Libby Shorbe, loan closing officer for First Federal, had written to Edgmon and Hedges reminding them that accrued interest on the loan in the amount of $47,828.78 would be due on November 1, but this was not paid.

On or about November 20 a draw request for $121,025 was submitted. After an inspection of the percentage of construction completed, First Federal approved $82,000 of the request but advised Edgem-on and Hedges they would need to furnish more collateral before the balance could be disbursed. Edgemon and Hedges refused to furnish additional collateral. They also failed “to furnish sufficient funds to make up the difference,” as required by the construction loan agreement. Instead, they ceased all construction on the project.

On December 9, 1986, Plaintiffs sent First Federal a request for an additional $900,000 funding for the project. They offered specific additional collateral for the loan and asked for an extension of the due date of the original loan to April 30, 1988. After considerable negotiation, a modified agreement was reached whereby the Plaintiffs would execute a note for $250,000 and pledge an additional $250,000 collateral. Then the $526,000 balance of the original loan would be disbursed as follows: Past-due interest, $50,000; payment of outstanding bills, $120,000; cost of completion of four units, completion of the exterior of five units, development site and pool construction, $360,000. First Federal would finance each unfinished unit as it was sold.

The project proceeded under this arrangement until September 22, 1987, when the Plaintiffs submitted a proposal to First Federal to loan them an additional $881,000 which was needed to complete the entire project. In this proposal it was estimated that completing all of the units and selling them would bring enough to pay off the loan. This would make First Federal come out even. First Federal agreed to make the additional loan and a new deed of trust and note were entered into on October 1, 1987, which would mature May 1, 1988.

Construction proceeded until April, 1988, when Appellants requested an additional $240,000 to complete the project. First Federal refused because there was no security for the additional loan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leonard Gamble v. Eric Brian Friend
Court of Appeals of Tennessee, 2025
Cynthia Thompson v. Stormy W. Moody
Court of Appeals of Tennessee, 2025
Abraham Anderson v. Alice Musick
Court of Appeals of Tennessee, 2024
SH Trelleborg Cadence, LLC v. Thomas Smythe
Court of Appeals of Tennessee, 2024
Michael Vitellaro v. Donna Goodall
Court of Appeals of Tennessee, 2024
Murali Ponnapula v. Immanuel Wright
Court of Appeals of Tennessee, 2024
Julie Clark v. Wanda Givens
Court of Appeals of Tennessee, 2023
Lawrence Simonetti v. Thomas Frank McCormick
Court of Appeals of Tennessee, 2022
Granoff v. Steed (TV2)
E.D. Tennessee, 2022
Ingram v. ADT LLC
E.D. Tennessee, 2021
The Estate of Stella Ruth Hughes v. C. Ray Adams
Court of Appeals of Tennessee, 2021
Adams v. Delk, Inc.
M.D. Tennessee, 2021
Don Gatlin v. Linda L. Scott
Court of Appeals of Tennessee, 2019
In Re Estate of John E. Mayfield
Court of Appeals of Tennessee, 2019

Cite This Page — Counsel Stack

Bluebook (online)
807 S.W.2d 559, 1990 Tenn. App. LEXIS 807, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jamestowne-on-signal-inc-v-first-federal-savings-loan-assn-tennctapp-1990.